SlideShare une entreprise Scribd logo
1  sur  17
Télécharger pour lire hors ligne
13th Australia New Zealand Conference on Geomechanics 2019
The design evolution of
replacement motorway bridge
approach embankments
N. Campbell and C. Bridges
13th Australia New Zealand Conference on Geomechanics 2019
Brisbane
Airport
Gateway
Motorway
Gateway Upgrade North
N
N/B
S/B
September 2016
New N/B
Abutment B
New N/B
Abutment A
13th Australia New Zealand Conference on Geomechanics 2019
May 2018
13th Australia New Zealand Conference on Geomechanics 2019
October 2017
13th Australia New Zealand Conference on Geomechanics 2019
Design Inputs
• Loading History
• Previous construction details
• Performance criteria
• Ground Model
(Site investigation)
13th Australia New Zealand Conference on Geomechanics 2019
June 2017
Design Inputs
• Loading History
• Previous construction details
• Performance criteria
• Ground Model
(Site investigation)
13th Australia New Zealand Conference on Geomechanics 2019
Time Activity
1m/week Construct existing embankment
24 years Current embankment
1 week Infill Median (Nov 2016)
Pause
1m/week Commence Widening (April 2017) Hold at
piling platform (RL +7)
Abutment A: 3 weeks
Abutment B: 3 weeks
Preloading NB widening, install piles (A then
B)
4 weeks Continue widening, raise to Abutment soffit
(RL +8.1)
3 days Install end spans of structure
1m/week Widen and raise to Final Surface Level (FSL)
1 month Preload at final level
1 week Apply final pavement load (Set as PCS
Reference)
40 years Measure Post Construction Settlement (PCS)
Design Inputs
• Loading History
• Previous construction details
• Performance criteria
• Ground Model
(Site investigation)
13th Australia New Zealand Conference on Geomechanics 2019
Design Inputs
• Loading History
• Previous construction details
• Performance criteria
• Ground Model
(Site investigation)
13th Australia New Zealand Conference on Geomechanics 2019
Slope Stability
Short term factor of safety ≥ 1.3
Long term factor of safety ≥ 1.5
Settlement
Post construction settlement (PCS) < 50mm over 40 years
Differential settlement limited to 0.5% over any 5m length
Design Inputs
• Loading History
• Previous construction details
• Performance criteria
• Ground Model
(Site investigation)
13th Australia New Zealand Conference on Geomechanics 2019
Year Investigation Type No. of Test Points
1984 CPT 1
1985 Boreholes 11
1985 CPT 5
2011 Borehole 1
2016 Borehole 8
2016 CPT 4
2017 Test Pits 2
2017 Test Pits during
construction 3
Design Inputs
• Loading History
• Previous construction
details
• Performance criteria
• Ground Model
(Site investigation)
13th Australia New Zealand Conference on Geomechanics 2019
Abutment A
Abutment B
Abutment A
Abutment B
Abutment B
Abutment A
13th Australia New Zealand Conference on Geomechanics 2019
Additional SI
Load Transfer
Platform
Expanded
Polystyrene
Pulverised Fly
Ash
Preolading
Update
Ground
Model
Calibrate
Model
Updated
Contractor
Input
Preolading
Construction
Verification
Monitoring
Tender Design Detailed Design Construction
13th Australia New Zealand Conference on Geomechanics 2019
13th Australia New Zealand Conference on Geomechanics 2019
Criteria Outcome
Durability No structural elements 
Aesthetics Temporary: no screens required
Permanent: Unchanged

-
Whole of Life Improvement to rideability, no hard to soft pavement interface between piled vs
non piled section

Sustainability No emissions intensive elements (reinforced concrete, transportation, heavy plant
and machinery). Use of existing ground’s load carrying potential

Design Life Unchanged -
Safety Eliminated heavy plant operations to handle, pitch and drive piles. Eliminate
constructability issued with piling under existing high voltage power lines

Functional
Performance
No closely spaced piles which would have limited or constrained future works or
installations (eg. Poles, gantries, light fittings)

Program Less time required for earthworks compared to load transfer platform / piling
installation. Adjacent works could continue during preloading period

Cost Decreased cost in materials, time and equipment 
Comparison between concept and current design
Lessons Learnt
• Confirm the design assumptions at the outset (i.e.
following the Tender Phase)
• Seek input from construction team early in the design
process
• Undertake additional ground investigation to fill in the
gaps
• It is useful to have new investigation positions adjacent to
historic locations, to calibrate settlement models
• Update the analysis with ‘as encountered’ conditions
during construction
• There is great value in regular monitoring, enabling back
analysis and greater confidence in forward predictions.
13th Australia New Zealand Conference on Geomechanics 2019

Contenu connexe

Tendances

Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Crosstown TO
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCrosstown TO
 
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017Crosstown TO
 
Applications of EPS Geofoam in Civil Engineering
Applications of EPS Geofoam in Civil EngineeringApplications of EPS Geofoam in Civil Engineering
Applications of EPS Geofoam in Civil EngineeringLawrence Le Roux
 
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Crosstown TO
 
Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Crosstown TO
 
T.Shaji George - Copy - Copy ts
T.Shaji George - Copy - Copy tsT.Shaji George - Copy - Copy ts
T.Shaji George - Copy - Copy tsSHAJI GEORGE
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Crosstown TO
 
Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Crosstown TO
 
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017Crosstown TO
 
David Matthew Resume2
David Matthew Resume2David Matthew Resume2
David Matthew Resume2David Matthew
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Crosstown TO
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarAssociation for Project Management
 
Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017Crosstown TO
 
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017Crosstown TO
 
Phillip james hawley august 2015
Phillip james hawley august 2015Phillip james hawley august 2015
Phillip james hawley august 2015Phillip Hawley
 
Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Crosstown TO
 
Raytec Presentation1
Raytec Presentation1Raytec Presentation1
Raytec Presentation1raytec
 

Tendances (20)

Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
 
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
 
Applications of EPS Geofoam in Civil Engineering
Applications of EPS Geofoam in Civil EngineeringApplications of EPS Geofoam in Civil Engineering
Applications of EPS Geofoam in Civil Engineering
 
Marks Sess13 102309
Marks Sess13 102309Marks Sess13 102309
Marks Sess13 102309
 
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
 
Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017
 
T.Shaji George - Copy - Copy ts
T.Shaji George - Copy - Copy tsT.Shaji George - Copy - Copy ts
T.Shaji George - Copy - Copy ts
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
 
Canal City - Poster-
Canal City - Poster-Canal City - Poster-
Canal City - Poster-
 
Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017
 
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
 
David Matthew Resume2
David Matthew Resume2David Matthew Resume2
David Matthew Resume2
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
 
Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017
 
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
 
Phillip james hawley august 2015
Phillip james hawley august 2015Phillip james hawley august 2015
Phillip james hawley august 2015
 
Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017
 
Raytec Presentation1
Raytec Presentation1Raytec Presentation1
Raytec Presentation1
 

Similaire à The design evolution of replacement motorway bridge approach embankments

new resume stephen hobbs
new resume  stephen hobbsnew resume  stephen hobbs
new resume stephen hobbsLiptrap Lawns
 
Saravanan CV 2015.1
Saravanan CV 2015.1Saravanan CV 2015.1
Saravanan CV 2015.1Bob Vanan
 
Work based project KNE520_John Ghaly visual audio presentation
Work based project KNE520_John Ghaly visual audio presentationWork based project KNE520_John Ghaly visual audio presentation
Work based project KNE520_John Ghaly visual audio presentationJohn Ghaly , MIEAust
 
161115 FDTB - from pile group to piled raft_Benoit Latapie
161115 FDTB - from pile group to piled raft_Benoit Latapie161115 FDTB - from pile group to piled raft_Benoit Latapie
161115 FDTB - from pile group to piled raft_Benoit LatapieBenoit Latapie
 
Overview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _VhoraOverview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _VhoraProSIM R & D Pvt. Ltd.
 
Presentation - Tosca Goldberg
Presentation - Tosca GoldbergPresentation - Tosca Goldberg
Presentation - Tosca GoldbergTosca Goldberg
 
25 herold 20160830 retrieval final
25 herold 20160830 retrieval final25 herold 20160830 retrieval final
25 herold 20160830 retrieval finalleann_mays
 
Culvert Box Construction.pptx
Culvert Box Construction.pptxCulvert Box Construction.pptx
Culvert Box Construction.pptxabdullah951033
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_AkhtarJavad Akhtar
 
Access Engineering PLC - Training Presentation
Access Engineering PLC - Training PresentationAccess Engineering PLC - Training Presentation
Access Engineering PLC - Training PresentationGihan Anuradha Bombuwala
 
GE Presentation 6th October 2010
GE Presentation 6th October 2010GE Presentation 6th October 2010
GE Presentation 6th October 2010Tonyamis
 
Chapter 01_2019_04_19.pptx
Chapter 01_2019_04_19.pptxChapter 01_2019_04_19.pptx
Chapter 01_2019_04_19.pptxssuserc0bf9b
 
Proper Maintenance for the Long Life of Concrete Pavements
Proper Maintenance for the Long Life of Concrete PavementsProper Maintenance for the Long Life of Concrete Pavements
Proper Maintenance for the Long Life of Concrete PavementsJill Reeves
 
Final Report
Final Report Final Report
Final Report Jack Ng
 
Remediation of contaminated sediments.ppt
Remediation of contaminated sediments.pptRemediation of contaminated sediments.ppt
Remediation of contaminated sediments.pptAhmdSbhy
 
D1 (A3) Ulla Kytölä - Restraint moment tests on precast prestressed beams mad...
D1 (A3) Ulla Kytölä - Restraint moment tests on precast prestressed beams mad...D1 (A3) Ulla Kytölä - Restraint moment tests on precast prestressed beams mad...
D1 (A3) Ulla Kytölä - Restraint moment tests on precast prestressed beams mad...Svenska Betongföreningen
 
JAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE NavyJAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE NavyMike Bisland
 
Case study on pile foundation review
Case study on pile foundation reviewCase study on pile foundation review
Case study on pile foundation reviewRajankumar416
 
Precast Bridges slides
Precast Bridges slidesPrecast Bridges slides
Precast Bridges slidesWaqas Javaid
 

Similaire à The design evolution of replacement motorway bridge approach embankments (20)

new resume stephen hobbs
new resume  stephen hobbsnew resume  stephen hobbs
new resume stephen hobbs
 
Saravanan CV 2015.1
Saravanan CV 2015.1Saravanan CV 2015.1
Saravanan CV 2015.1
 
Work based project KNE520_John Ghaly visual audio presentation
Work based project KNE520_John Ghaly visual audio presentationWork based project KNE520_John Ghaly visual audio presentation
Work based project KNE520_John Ghaly visual audio presentation
 
161115 FDTB - from pile group to piled raft_Benoit Latapie
161115 FDTB - from pile group to piled raft_Benoit Latapie161115 FDTB - from pile group to piled raft_Benoit Latapie
161115 FDTB - from pile group to piled raft_Benoit Latapie
 
Overview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _VhoraOverview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _Vhora
 
Presentation - Tosca Goldberg
Presentation - Tosca GoldbergPresentation - Tosca Goldberg
Presentation - Tosca Goldberg
 
25 herold 20160830 retrieval final
25 herold 20160830 retrieval final25 herold 20160830 retrieval final
25 herold 20160830 retrieval final
 
Culvert Box Construction.pptx
Culvert Box Construction.pptxCulvert Box Construction.pptx
Culvert Box Construction.pptx
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar
 
Access Engineering PLC - Training Presentation
Access Engineering PLC - Training PresentationAccess Engineering PLC - Training Presentation
Access Engineering PLC - Training Presentation
 
GE Presentation 6th October 2010
GE Presentation 6th October 2010GE Presentation 6th October 2010
GE Presentation 6th October 2010
 
Chapter 01_2019_04_19.pptx
Chapter 01_2019_04_19.pptxChapter 01_2019_04_19.pptx
Chapter 01_2019_04_19.pptx
 
Proper Maintenance for the Long Life of Concrete Pavements
Proper Maintenance for the Long Life of Concrete PavementsProper Maintenance for the Long Life of Concrete Pavements
Proper Maintenance for the Long Life of Concrete Pavements
 
Shib
ShibShib
Shib
 
Final Report
Final Report Final Report
Final Report
 
Remediation of contaminated sediments.ppt
Remediation of contaminated sediments.pptRemediation of contaminated sediments.ppt
Remediation of contaminated sediments.ppt
 
D1 (A3) Ulla Kytölä - Restraint moment tests on precast prestressed beams mad...
D1 (A3) Ulla Kytölä - Restraint moment tests on precast prestressed beams mad...D1 (A3) Ulla Kytölä - Restraint moment tests on precast prestressed beams mad...
D1 (A3) Ulla Kytölä - Restraint moment tests on precast prestressed beams mad...
 
JAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE NavyJAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE Navy
 
Case study on pile foundation review
Case study on pile foundation reviewCase study on pile foundation review
Case study on pile foundation review
 
Precast Bridges slides
Precast Bridges slidesPrecast Bridges slides
Precast Bridges slides
 

Plus de Chris Bridges

Long-term geotechnical impacts of climate change on project
 Long-term geotechnical impacts of climate change on project Long-term geotechnical impacts of climate change on project
Long-term geotechnical impacts of climate change on projectChris Bridges
 
Geotechnical risk on large scale infrastructure projects
Geotechnical risk on large scale infrastructure projectsGeotechnical risk on large scale infrastructure projects
Geotechnical risk on large scale infrastructure projectsChris Bridges
 
The identification, treatment and use of expansive soils in railway construction
The identification, treatment and use of expansive soils in railway constructionThe identification, treatment and use of expansive soils in railway construction
The identification, treatment and use of expansive soils in railway constructionChris Bridges
 
The management of geotechnical risk on major infrastructure projects
The management of geotechnical risk on major infrastructure projectsThe management of geotechnical risk on major infrastructure projects
The management of geotechnical risk on major infrastructure projectsChris Bridges
 
Design of earth-retaining structures - Lecture 8
Design of earth-retaining structures - Lecture 8Design of earth-retaining structures - Lecture 8
Design of earth-retaining structures - Lecture 8Chris Bridges
 
Design of earth-retaining structures - Lecture 7
Design of earth-retaining structures - Lecture 7Design of earth-retaining structures - Lecture 7
Design of earth-retaining structures - Lecture 7Chris Bridges
 
Design of earth-retaining structures - Lecture 6
Design of earth-retaining structures - Lecture 6Design of earth-retaining structures - Lecture 6
Design of earth-retaining structures - Lecture 6Chris Bridges
 
Design of earth-retaining structures - Lecture 5
Design of earth-retaining structures - Lecture 5Design of earth-retaining structures - Lecture 5
Design of earth-retaining structures - Lecture 5Chris Bridges
 
The design of earth retaining structures - Lecture 4
The design of earth retaining structures - Lecture 4The design of earth retaining structures - Lecture 4
The design of earth retaining structures - Lecture 4Chris Bridges
 
The design of earth retaining structures - Lecture 3
The design of earth retaining structures - Lecture 3The design of earth retaining structures - Lecture 3
The design of earth retaining structures - Lecture 3Chris Bridges
 
The design of earth-retaining structures - Lecture 2
The design of earth-retaining structures - Lecture 2The design of earth-retaining structures - Lecture 2
The design of earth-retaining structures - Lecture 2Chris Bridges
 
The design of earth-retaining structures - Lecture 1
The design of earth-retaining structures - Lecture 1The design of earth-retaining structures - Lecture 1
The design of earth-retaining structures - Lecture 1Chris Bridges
 

Plus de Chris Bridges (12)

Long-term geotechnical impacts of climate change on project
 Long-term geotechnical impacts of climate change on project Long-term geotechnical impacts of climate change on project
Long-term geotechnical impacts of climate change on project
 
Geotechnical risk on large scale infrastructure projects
Geotechnical risk on large scale infrastructure projectsGeotechnical risk on large scale infrastructure projects
Geotechnical risk on large scale infrastructure projects
 
The identification, treatment and use of expansive soils in railway construction
The identification, treatment and use of expansive soils in railway constructionThe identification, treatment and use of expansive soils in railway construction
The identification, treatment and use of expansive soils in railway construction
 
The management of geotechnical risk on major infrastructure projects
The management of geotechnical risk on major infrastructure projectsThe management of geotechnical risk on major infrastructure projects
The management of geotechnical risk on major infrastructure projects
 
Design of earth-retaining structures - Lecture 8
Design of earth-retaining structures - Lecture 8Design of earth-retaining structures - Lecture 8
Design of earth-retaining structures - Lecture 8
 
Design of earth-retaining structures - Lecture 7
Design of earth-retaining structures - Lecture 7Design of earth-retaining structures - Lecture 7
Design of earth-retaining structures - Lecture 7
 
Design of earth-retaining structures - Lecture 6
Design of earth-retaining structures - Lecture 6Design of earth-retaining structures - Lecture 6
Design of earth-retaining structures - Lecture 6
 
Design of earth-retaining structures - Lecture 5
Design of earth-retaining structures - Lecture 5Design of earth-retaining structures - Lecture 5
Design of earth-retaining structures - Lecture 5
 
The design of earth retaining structures - Lecture 4
The design of earth retaining structures - Lecture 4The design of earth retaining structures - Lecture 4
The design of earth retaining structures - Lecture 4
 
The design of earth retaining structures - Lecture 3
The design of earth retaining structures - Lecture 3The design of earth retaining structures - Lecture 3
The design of earth retaining structures - Lecture 3
 
The design of earth-retaining structures - Lecture 2
The design of earth-retaining structures - Lecture 2The design of earth-retaining structures - Lecture 2
The design of earth-retaining structures - Lecture 2
 
The design of earth-retaining structures - Lecture 1
The design of earth-retaining structures - Lecture 1The design of earth-retaining structures - Lecture 1
The design of earth-retaining structures - Lecture 1
 

Dernier

Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 

Dernier (20)

Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 

The design evolution of replacement motorway bridge approach embankments

  • 1. 13th Australia New Zealand Conference on Geomechanics 2019 The design evolution of replacement motorway bridge approach embankments N. Campbell and C. Bridges
  • 2. 13th Australia New Zealand Conference on Geomechanics 2019 Brisbane Airport Gateway Motorway Gateway Upgrade North N
  • 4. 13th Australia New Zealand Conference on Geomechanics 2019 May 2018
  • 5. 13th Australia New Zealand Conference on Geomechanics 2019 October 2017
  • 6. 13th Australia New Zealand Conference on Geomechanics 2019
  • 7. Design Inputs • Loading History • Previous construction details • Performance criteria • Ground Model (Site investigation) 13th Australia New Zealand Conference on Geomechanics 2019 June 2017
  • 8. Design Inputs • Loading History • Previous construction details • Performance criteria • Ground Model (Site investigation) 13th Australia New Zealand Conference on Geomechanics 2019 Time Activity 1m/week Construct existing embankment 24 years Current embankment 1 week Infill Median (Nov 2016) Pause 1m/week Commence Widening (April 2017) Hold at piling platform (RL +7) Abutment A: 3 weeks Abutment B: 3 weeks Preloading NB widening, install piles (A then B) 4 weeks Continue widening, raise to Abutment soffit (RL +8.1) 3 days Install end spans of structure 1m/week Widen and raise to Final Surface Level (FSL) 1 month Preload at final level 1 week Apply final pavement load (Set as PCS Reference) 40 years Measure Post Construction Settlement (PCS)
  • 9. Design Inputs • Loading History • Previous construction details • Performance criteria • Ground Model (Site investigation) 13th Australia New Zealand Conference on Geomechanics 2019
  • 10. Design Inputs • Loading History • Previous construction details • Performance criteria • Ground Model (Site investigation) 13th Australia New Zealand Conference on Geomechanics 2019 Slope Stability Short term factor of safety ≥ 1.3 Long term factor of safety ≥ 1.5 Settlement Post construction settlement (PCS) < 50mm over 40 years Differential settlement limited to 0.5% over any 5m length
  • 11. Design Inputs • Loading History • Previous construction details • Performance criteria • Ground Model (Site investigation) 13th Australia New Zealand Conference on Geomechanics 2019 Year Investigation Type No. of Test Points 1984 CPT 1 1985 Boreholes 11 1985 CPT 5 2011 Borehole 1 2016 Borehole 8 2016 CPT 4 2017 Test Pits 2 2017 Test Pits during construction 3
  • 12. Design Inputs • Loading History • Previous construction details • Performance criteria • Ground Model (Site investigation) 13th Australia New Zealand Conference on Geomechanics 2019 Abutment A Abutment B Abutment A Abutment B
  • 14. 13th Australia New Zealand Conference on Geomechanics 2019 Additional SI Load Transfer Platform Expanded Polystyrene Pulverised Fly Ash Preolading Update Ground Model Calibrate Model Updated Contractor Input Preolading Construction Verification Monitoring Tender Design Detailed Design Construction
  • 15. 13th Australia New Zealand Conference on Geomechanics 2019
  • 16. 13th Australia New Zealand Conference on Geomechanics 2019 Criteria Outcome Durability No structural elements  Aesthetics Temporary: no screens required Permanent: Unchanged  - Whole of Life Improvement to rideability, no hard to soft pavement interface between piled vs non piled section  Sustainability No emissions intensive elements (reinforced concrete, transportation, heavy plant and machinery). Use of existing ground’s load carrying potential  Design Life Unchanged - Safety Eliminated heavy plant operations to handle, pitch and drive piles. Eliminate constructability issued with piling under existing high voltage power lines  Functional Performance No closely spaced piles which would have limited or constrained future works or installations (eg. Poles, gantries, light fittings)  Program Less time required for earthworks compared to load transfer platform / piling installation. Adjacent works could continue during preloading period  Cost Decreased cost in materials, time and equipment  Comparison between concept and current design
  • 17. Lessons Learnt • Confirm the design assumptions at the outset (i.e. following the Tender Phase) • Seek input from construction team early in the design process • Undertake additional ground investigation to fill in the gaps • It is useful to have new investigation positions adjacent to historic locations, to calibrate settlement models • Update the analysis with ‘as encountered’ conditions during construction • There is great value in regular monitoring, enabling back analysis and greater confidence in forward predictions. 13th Australia New Zealand Conference on Geomechanics 2019