12. reporting metrics
Little’s Law:
average WIP = average LT x average TP
http://www.cs.bilkent.edu.tr/~tugrul/CS518/Papers/little.pdf
http://web.mit.edu/sgraves/www/papers/Little's%20Law-Published.pdf
13. Conditions/assumptions:
● Items of similar size
● Conservation of flow: departure rate =
average arrival rate
● All work items that enter the system will
eventually be completed and will exit the
system
14. How do we apply it?
Time to complete = N/aTP
Or
Time to complete = N* (aLT/aWIP)