SlideShare une entreprise Scribd logo
1  sur  35
Télécharger pour lire hors ligne
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
1 | P a g e
EDITORS COMMENTS
The annual London conference takes place on
the 19 August 2021 and will be an online
conference with a physical networking and
drinks event in London in the evening at the
Middle Temple. Panel members will have
received an email with the links.
I am also pleased to confirm that the ‘rookie
adjudicator’ has provided an article for this
newsletter which newer adjudicators will find
of interest.
Please do forward articles, events and worthy
news for inclusion in forthcoming newsletters.
If you would like to take part in the conference
as a speaker or sponsor, please do let me now.
Our charity partner for the event is the Free
Representation Unit and we are looking for
donations of raffle prizes to assist them with
fundraising at the evening event.
Sean Gibbs LLB(Hons) LLM MICE FCIOB FRICS
FCIARB, is the Chief Executive Officer of
Hanscomb Intercontinental and is available to
sit as an arbitrator, adjudicator, mediator,
quantum expert and dispute board member.
sean.gibbs@hanscombintercontinental.co.uk
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
2 | P a g e
IS IT TIME TO ‘DEFAULT’ FROM
DEFAULT PAYMENT NOTICES?
Not long after my last piece regarding
‘technical’ defences to payment claims was
included in the Adjudication Society’s Autumn
Newsletter, a judgement was handed down in
the TCC which caught my eye. The judgement
was in the case RGB Plastering Limited v Tawe
Drylining and Plastering Limited [2020] EWHC
3028 (TCC), and it surrounded issues
connected to those discussed in my last piece.
Whilst I won’t go into any great detail as to the
facts of the RGB case, for the purposes of this
piece I will set out a very brief background to
the dispute.
Tawe submitted an application for payment to
RGB. RGB did not respond to the application
with a payment notice or pay less notice, nor
did RGB pay Tawe the sum set out in Tawe’s
application. Tawe referred the payment
dispute to adjudication, seeking full payment
of the sum claimed in its application for
payment on the basis that RGB had not served
a valid payment notice or pay less notice in
response to the application therefore its
application had become a payee notice in
default/default payment notice. The
adjudicator agreed with Tawe and awarded it
the sum claimed in its application for payment.
Subsequently, RGB referred the matter to the
Court seeking a declaration that Tawe’s
application for payment was invalid because it
did not comply strictly with the requirements
of sub-contract in relation to the submission of
applications for payment (precisely the kind of
‘technical’ defence to payment which I
discussed in my last piece). The Court agreed
with RGB and granted it the declaration it had
sought.
This case is yet another example of the
situation we, as an industry, seem to have
gotten ourselves into since the floodgates
were opened by ISG Construction Ltd v Seevic
College [2014] EWHC 4007 (TCC). There have
been many reported cases since ISG, and
undoubtedly hundreds, if not thousands, more
which have been settled without coming
before the courts. The costs involved are
probably eye watering.
This, then, leads me to the following questions:
i) what benefit does the
construction industry actually
receive, in reality, from the default
payment provisions of the Housing
Grants Construction and
Regeneration Act 1996 (as
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
3 | P a g e
amended by the Local Democracy
Economic Development and
Construction Act 2009); and,
ii) does that benefit (if any) outweigh
the cost?
As a Trainee Quantity Surveyor with Mowlem
in the mid-late 1990s, and then as an Assistant
Quantity Surveyor with Wates in the late
1990s, I was taught that a payee should always
provide full substantiation in support of all
sums claimed in each application for payment
which it submits to a payer. This substantiation
included things like marked-up drawings,
marked-up specifications, photographs, copies
of instructions, copies of meeting minutes,
‘take-offs’, build-ups to ‘star rates’, cross
references to BOQ rates, and suchlike; all of
which were to be provided with each
application for payment with the sole intention
being to support the payee’s right to payment
of the sum claimed in the application. If a
payee had properly substantiated each of its
applications for payment as aforesaid then, if
the payer failed or refused to pay the sum
claimed in any such application, the payee was
in a position to pretty much immediately refer
a dispute to adjudication without further delay
because it had already prepared all of the
documents/substantiation necessary to
demonstrate the ‘true value’ of the work which
it had completed and which it had claimed in
the application.
Then along came the Local Democracy
Economic Development and Construction Act
2009, and with it some new payment
provisions designed to give the previous
payment provisions of the Housing Grants
Construction and Regeneration Act 1996 some
‘teeth’. It was not until 2015 that this amended
legislation really showed its teeth, with the
judgement in ISG v Seevic. In essence,
following ISG v Seevic a payee could now
obtain full payment of the sum claimed in its
application for payment without having to
actually do any of the detailed work necessary
to properly substantiate the sum claimed
therein (provided, of course, that the payer
had failed to respond to the application for
payment with a payment notice or pay less
notice). This, in my experience, has
encouraged payees to take short cuts when
preparing applications for payment; such
applications being prepared to a very basic
standard and often in the hope that the payer
fails to respond with the requisite notices.
So, turning to the first question I set out above.
Whilst the Construction Act (as amended) may
be well intentioned in its aim of facilitating
cashflow, does it really achieve this in reality?
If a payee submits an application for payment
along with full substantiation in support of the
sum claimed therein, then what does it matter
whether or not the payer serves a payment
notice or pay less notice? Surely all that is
needed is a mechanism for ascertaining an
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
4 | P a g e
application date and a final date for payment?
If the payer does not pay, by the final date for
payment, the sum claimed in an application for
payment then, having already prepared and
submitted a fully substantiated application for
payment, the payee is already in a position to
pretty much immediately refer the dispute to
adjudication so to have the ‘true value’ of the
work declared and paid. The payee could
obtain the declaration and payment in
adjudication proceedings in similar timescales
(if not the same timescales) as it would in what
has become commonly termed ‘smash and
grab’ adjudication proceedings. In view of the
foregoing, what benefit is actually really
achieved by the default payment notice
provisions of the Construction Act (as
amended)? Some may perhaps suggest that
the benefits are, in reality, fairly limited.
Turning to the second question I set out above.
If some were indeed correct to say that the
benefits of the default payment provisions of
Construction Act (as amended) are, in reality,
fairly limited, then at what cost do those
benefits come? The now widespread (in my
experience) practice of taking short cuts to
prepare applications for payment is
undoubtedly a fertile breeding ground for
conflict. With that conflict often comes an
irretrievable deterioration in relationships and
significant financial consequences. Is this
really what the amended legislation intended?
In view of the above, is it time to give serious
consideration to repealing the default
payment provisions of the Construction Act (as
amended)? Would this not encourage payees
to set out their claims with fully substantiated
clarity and thereby reduce both the
opportunity for conflict to arise and the
likelihood of conflict actually arising (or, at the
very least, reduce the likelihood of conflict
subsequently becoming adversarial in nature)?
The final date for payment and other relevant
provisions (other than the default payment
provisions) of the Construction Act could (and,
I suggest, should) remain; thereby maintaining
the right for a payee who is not paid by the final
date for payment to immediately refer the
dispute to adjudication on a ‘true value’ basis
(having already prepared and submitted with
its application for payment the necessary
substantiation in support of the sum claimed
therein) and have it decided in similar
timescales (if not the same timescales), from
the date the dispute crystallised, as it would in
a ‘smash and grab’ adjudication.
Some may say a repealing of the default
payment provisions of the Construction Act (as
amended) would lead to a reduction in the use
of adjudication as a means of resolving conflict
in the industry. However, should we, as an
industry, not be taking steps to avoid conflict
rather than encourage it? Further, would it not
mean that adjudicators could actually get on
with deciding disputes of substance, rather
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
5 | P a g e
than technical disputes of little substance at
all?
Dean Sayers is a Director with Sayers
Commercial Ltd, and is available to sit as an
adjudicator and arbitrator
E: dean@sayerscommercial.co.uk
T: 07710 422671
MY FIRST APPOINTMENT – PART 1
BY THE ROOKIE ADJUDICATOR
It was the summer of 2019 and I received an
email from the Serving Nominator. Like all
those who receive such an email, I carried out
a quick assessment of the Notice of
Adjudication and undertook a conflict check. I
was good to go, so I sent my response to the
Serving Nominator. The next day I received the
email, which confirmed that I had been
appointed.
This was great news. This is what I had been
working towards. This was my first
appointment.
I had completed my CIArb Diploma in
Adjudication in May 2015 and I had gained
valuable adjudication experience working as a
Party Rep since 2013. But there is something
different being appointed as an adjudicator, it
all became rather serious.
Following confirmation of my Nomination, I
carefully prepared my opening communication
to the parties, which set out that I had been
nominated by UK Adjudicators as the
adjudicator, I gave some initial directions such
as, I was happy for communications to be
exchanged using email and that I only intended
to communicate with the persons /
organisations set out this letter and then, such
as my surprise to be appointed and mainly
because I hadn’t quite got round to doing
them, I realised that I needed a set of terms of
appointment to accompany my first
communication.
I considered several pieces of information and
pulled together a robust set of terms, which I
was happy with. Whilst creating these terms, I
had to deal with the matter of the hourly rate I
should charge to conduct the adjudication and
produce a decision for the dispute. What was
too much? What was too little? Looking back
through the charges received from
adjudicators when I had been acting as a party
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
6 | P a g e
representative, I made a decision, which I felt
reflected my standing in the league of
adjudicators. For those wondering, the rate
was sub £180.00 per hour.
So having now completed the first
communication and the terms of appointment,
I sent the communication to the parties via
email using the email addresses stated in the
Notice of Adjudication and the UKA
Adjudicator application form. Shortly after, I
received an acknowledgement from the
Referring Party, I now just wanted the
acknowledgement from the Responding Party.
I waited and waited, and nothing came
through (I am talking hours rather than days).
As a user of Apple’s Mac Mail I did not have the
benefits of Microsoft Outlook and thus no
delivery or read receipt facility, so there was no
100% guarantee that the email had been
received by the Responding Party; although I
was certain it had been, having not received an
‘undeliverable receipt’ from my email domain.
Nevertheless, the last thing I wanted, with this
being my first appointment, was there to be
any issues with claims of breaches of natural
justice and allegations only communicating
with one party. So I did what most other
adjudicators would do (I hope), I printed off
two copies of the covering email, my first letter
and my terms of appointment (one set for the
Referring Party and one set for the Responding
Party) with the intention of posting them using
royal mail’s track and trace delivery facility.
Just as I was about to insert the copies into the
envelopes I had a negative thought, “What if
the Responding Party had been advised to
make my life hard work? What if they were
being advised by someone who told them to
not play ball and this is the reason why they did
not respond to my email after my first
communication, which had now prompted me
sending the document by post? Negative
thoughts I know, but I had seen the way other
adjudicators had been treated by party
representatives of the responding parties,
when I had been the Party Representative of
the Referring Party and I wanted to lock all
doors, which might be opened by someone
looking to cause trouble. To counter the
negative thought I decided to not send the
communications in envelopes branded with
my business logo, but rather in unmarked
envelopes only stating the name and address
of the parties and the contact names provided
to me. Was I being over cautious? A phrase
often said to us all by our friends, peers and
seniors came to mind, so I adopted the “better
safe than sorry” principle and I believe I made
the right decision. It certainly did give me
peace of mind.
Having now enclosed, sealed and addressed
the envelopes, I walked to my local Post Office
and sent the envelopes tracked for next day
delivery, with signature for proof of delivery.
The next day, after checking the Royal Mail
Track and Trace website, I had confirmation in
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
7 | P a g e
writing that both parties had received a hard
copy of my first communication and my mind
was at ease.
Now all that I awaited was the Referral. Was it
going to come in or had the parties managed
to reach a deal and stop the adjudication in its
tracks?
THE ROOKIE ADJUDICATOR
BUILDERS LIEN UPDATE - RED TAPE
REDUCTION IMPLANTATION ACT
(BILL 62)
Background
The name of the Alberta Builders’ Lien Act has
changed to the Prompt Payment and
Construction Lien Act (the PPCLA), and
contains new rules and adjudication
procedures that will have a transformative
impact on the construction industry in Alberta.
The PPCLA is anticipated to come into force on
July 21, 2021, although the regulations have
not yet been released.
Bill 37, the Builders’ Lien (Prompt Payment)
Amendment Act, 2020 and its proposed
amendments to the Alberta Builders’ Lien
Act (the Prompt Payment Amendment) have
been discussed in BLG’s articles on October 23,
2020 and November 4, 2020.
On April 8, 2021, Bill 62, the Red Tape
Reduction Implantation Act (Bill 62) received
its first reading in the Alberta legislature. Bill 62
contains important information and guidance
on the adjudication provisions in the Prompt
Payment Amendment, a key feature of the
PPCLA. Most critically, Bill 62:
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
8 | P a g e
Outlines the application and scope of the
PPCLA; and
Provides further definition to the adjudication
provisions in the PPCLA.
Scope of the PPCLA
Bill 62 excludes construction projects involving
the provincial government from the PPCLA,
including projects involving crown
corporations. Bill 62 also references other
entities and agreements to be excluded from
the PPCLA’s scope. While Bill 62 states that the
PPCLA will apply to “a prescribed class of
professionals acting in a consultative capacity”,
the Government of Alberta has not yet
published guidance or regulations about which
professions would fall within this “prescribed
class”.
Adjudication
More importantly, Bill 62 makes significant
changes to the adjudication provisions in the
PPCLA (the Adjudication Process). Bill 62
stipulates that parties cannot use the
Adjudication Process where a court action has
been commenced or where the contract is
complete. As such, the Adjudication Process
appears to be exclusively intended for disputes
occurring during the execution of a project.
Completed projects
While these changes highlight the primary goal
of the adjudication provisions of the PPCLA
(the faster resolution of disputes during a
construction project), they also create
uncertainty, potential for delay and
inconsistent results. When a project is
“complete” is often a point of contention
between parties in a construction dispute.
Uncertainty stemming from whether a project
is complete may result in more court
applications, which could result in fewer
disputes being subject to the Adjudication
Process and create further delays. Notably, as
drafted, warranty or remedial work that is
usually completed close to or after project
completion, may be excluded from the
Adjudication Process altogether.
Court actions
Carving out construction disputes that are the
subject of a court action may generate
unintended consequences. For example,
parties may be incentivized to commence
court actions to avoid the Adjudication Process
altogether in an attempt to ensure they are
able to select the forum for the dispute.
Further, there could be instances where a
broad court action involves the subject matter
and potentially the same parties involved in an
Adjudication Process. This raises the possibility
of inconsistent results. Without more guidance
from the Government of Alberta, the incentive
to race to the courthouse and the potential for
inconsistent results between courts and
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
9 | P a g e
adjunction panels adds to the uncertainty that
the adjudication provisions of the PPCLA will
create.
Adjudication orders and judicial review
Prior to Bill 62, the PPCLA attempted to make
adjudication decisions final by making judicial
review the only way to challenge a
adjudicator’s decision. To further reinforce the
PPCLA’s adjudication provisions against delays
associated with court involvement, the PPCLA
made adjudication decisions enforceable
despite the filing of a judicial review
application. Bill 62 walks back the limits on the
court’s ability to become involved in a dispute
that is subject to the Adjudication Process.
Specifically, the order of an adjudicator
stemming from a dispute will not be binding
where:
The Court makes an order in respect of the
dispute;
An application for judicial review of the
determination is made by one of the parties;
The parties proceed to arbitration by entering
into a written agreement; or
The parties settle the dispute by written
agreement.
The “Exemptions”
In addition to raising serious questions about
the strength of any order stemming from an
Adjudication Process, the Exemptions also act
as a bar to the registration (and enforcement)
of an adjudication order. The Exemptions
create significant uncertainty about how
arbitration/meditation clauses, commonly
found in construction contracts, will apply to
the Adjudication Process. If a party
commences an arbitration, are they barred
from using the adjudication provisions? If
during the course of an Adjudication Process,
one party seeks to activate the arbitration
clause of their agreement, does this trigger one
of the Exemptions? Moreover, do the
Exemptions mean that, at any time, a party can
make an application to the court in respect of
a dispute? As drafted, the Exemptions may
provide parties an avenue to engage the court
even if they have failed to win the race to the
courthouse.
Procedural guidance
Finally, Bill 62 includes mechanical and
procedural provisions required to enforce an
order stemming from the Adjudication
Process. A party must register an adjudicator’s
order with the Clerk of the Court of Queen’s
Bench of Alberta (the Clerk of the Court) and
provide a written notice to the other party
within 10 days from the date that the Clerk of
the Court registers the adjudicator’s order.
Once the Clerk of the Court registers the
adjudicator’s order it has the same effect as a
court order. Bill 62 also includes two important
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
10 | P a g e
limitations dates that stipulate that an
adjudicator’s order cannot be registered:
Two years after the order is issued; or
Two years after the court has rendered a
decision on an application for judicial review.
Conclusion
Bill 62 raises further uncertainty about the
applicability of the PPCLA. As a result, we
expect additional changes in the form of
further amendments or publication of draft
regulations will be required to better frame the
purpose and scope of the PPCLA.
We will continue to monitor the progress of Bill
37 and Bill 62 as both pieces of legislation
receive further consideration by the Alberta
legislature and provide updates as they
become available. It remains clear that
construction industry players, of all sizes, will
need to take proactive steps to prepare for and
mitigate against the uncertainty and new risks
created by these reforms to the
Alberta Builders’ Lien Act.
CONFACT CORE CONSTRUCTION CC
V JLK CONSTRUCTION (PTY) LTD
The Western Cape High Court handed down
judgement in the matter of Confact Core
Construction CC v JLK Construction (Pty) Ltd on
25 November 2020. Confact had applied for an
order giving effect to an adjudication award.
JLK alleged that the referral to adjudication
was not competent. Failing such a finding, JLK
counter applied for an order suspending the
implementation of the adjudication award on
the grounds that it would suffer substantial
injustice should the award be given effect.
The agreement between Confact and JLK was
governed by the JBCC Edition 5.0 N/S
subcontract agreement. If a disagreement
arises, Clause 40 thereof requires the
aggrieved party to give notice to the other to
resolve the disagreement. If the disagreement
is not resolved within 10 working days of this
notice it is deemed to be a dispute and the
aggrieved party has the option to refer it to
either adjudication or arbitration. The
adjudication is governed by the JBCC
Adjudication Rules which stipulate that the
parties must appoint the adjudicator by mutual
agreement within 5 days of the disagreement
being deemed a dispute. Where an
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
11 | P a g e
appointment is not made in that period, either
party may request the nominating body to
appoint an adjudicator. The adjudicator’s
decision is binding on the parties who must
give effect to it without delay unless and until
it is subsequently revised by an arbitrator.
The Principal Building Agreement between the
Employer and JLK was terminated in December
2018, which resulted in the termination of the
subcontract agreement between JLK and
Confact. In January 2020 Confact demanded
payment of sums due in respect of work done
and the return of retention. JLK did not
respond and Confact gave notice to JLK to
resolve the disagreement in February 2020.
The disagreement was not resolved within 10
working days, was deemed to be a dispute and
Confact elected to refer it to adjudication. JLK
and Confact were not able to agree on an
adjudicator and Confab requested the
nominating body to appoint an adjudicator in
March 2020. Confact made submissions to the
adjudicator in May 2020, but JLK failed to
respond. The adjudicator delivered a decision
in favour of Confact in June 2020. Despite
demand, JLK failed to make payment in terms
of this award.
The dispute arose in 2018 when Confact
requested (and JLK refused to make) payment
on termination of the agreement. JLK argued
that the dispute should have been referred to
adjudication in 2018 and that as it was not, an
adjudicator had not been appointed within the
5 days stipulated in the Adjudication Rules, and
arbitration was the only competent option left
available to Confact. The court rejected this
argument on the following grounds:
It flies in the face of the stipulation in Clause 40
of the agreement that a disagreement is
deemed to be a dispute only once a notice to
resolve disagreement has been given, and such
disagreement hasn’t been resolved within 10
working days thereof. It would also mean that
every time a subcontractor made application
for payment, the date of this application would
determine the date of a dispute even as the
subcontractor remained unaware whether or
not the contractor intended to make payment.
The court concluded that it is absurd to
contend that an application for payment would
have the same effect as a notice.
Clause 40 also clearly provides for an election
between adjudication and arbitration and on a
plain and straightforward reading of this
provision, JLK’s contention was misplaced.
Adjudication is a specific process which caters
for specific time frames, the aim and purpose
for which is quick and immediate resolution
whilst the agreement still endures. If the
agreement is terminated then the parties
should use arbitration and they will effectively
be barred from adjudication. In support of this
argument JLK relied upon obiter in the matter
of Radon Projects (Pty) Ltd v NV Properties
(Pty) Ltd and Another. As the court rightly
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
12 | P a g e
pointed out, however, the underlying
agreement in Radon was different to the
agreement between Confact and JLK. In Radon,
the agreement specifically stipulated that prior
to practical completion disputes were to be
referred to adjudication and after practical
completion disputes were to be referred to
arbitration. This didn’t have any application to
the agreement between Confact and JLK
because their agreement did not include such
a provision.
JLK also argued against the implementation of
the award on the grounds that it still had the
right to refer the dispute to arbitration and
had, in fact, done so. The court rejected this
argument on the grounds that there are
numerous authorities that support the
proposition that a party to a construction
contract is obliged to give effect to the terms
of an adjudication award, including payment,
until it is set aside (See Esor Africa (Pty)
Ltd/Franki Africa (Pty) Ltd joint Venture v
Bombela Civils Joint Venture, Case 2012/7442,
para13; Tubular Holding (Pty) Ltd v DBT
Technologies (Pty) Ltd 2014 (1) SA 244 (GSJ)
para 40; Basil Read (Pty) Ltd v Regent Devco
(Pty) Ltd [2011] JOL 27946 (GSJ)). Regardless of
whether JLK exercises its contractual right to
refer the dispute to arbitration, it is bound by
the adjudicator’s decision and must give effect
to it without delay, unless and until the
adjudicator’s decision is set aside by an
arbitrator.
In its counter application JLK argued that the
implementation of the adjudicator’s award
should be suspended pending the outcome of
the arbitration process because the
adjudication process was unnecessary, JLK did
not have an opportunity to challenge Confact’s
claim, and JLK had been indicating since June
2020 that it intended to refer the adjudication
award to arbitration. For these reasons JLK
alleged that it would suffer substantial
prejudice if the suspension was not granted
and that it was in the interests of justice to
suspend the implementation of the
adjudicator’s award. The court found that it
was Confact who would suffer real and
substantial prejudice should the adjudicator’s
award not be implemented. The court has a
discretion to grant a suspension of an order
where real and substantial injustice will
otherwise be done, but JLK had wilfully refused
to pay Confact for some 18 months, refused to
agree on an adjudicator and refused to
participate in the adjudication process. It was
not, therefore, open for it to complain that it
had not been afforded the opportunity to
challenge Confact’s claim. The court also
pointed out that despite JLK’s assertion that it
required the dispute to be ventilated by
arbitration, there was no evidence before the
court that JLK had referred the matter to an
arbitrator. JLK had, therefore, dismally failed to
reach the threshold of exceptional
circumstances required to satisfy the granting
of a suspension order.
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
13 | P a g e
AMALGAMATED CONSTRUCTION
CONTRACTS - GRASP THE NETTLE
AND ENFORCE (OR NOT)?
Pursuant to the Housing Grants, Construction
and Regeneration Act 1996 (as amended) a
party to a construction contract is permitted to
refer a dispute arising under the contract to
adjudication.i
It is noteworthy that ‘dispute’ is
referred to in the singular. Consequently,
should a dispute between parties be spread
over more than one contract it is likely that
more than one dispute exists, thus, leaving an
adjudicator devoid of jurisdiction. On occasion
parties may have entered more than one
construction contract with each other on the
same project but administer and treat those
contracts as one. For example, a contractor
may enter a contract with a sub-contractor for
a particular works package and later enter a
contract with that same sub-contractor for
another works package but administer
payments for both of those contracts in an
amalgamated way. Similarly, a local authority
may enter a framework agreement with a
contractor and place separate Orders
thereunder but amalgamate payments for
those Orders. Should a party refer a dispute to
adjudication under such arrangements
jurisdictional challenges may arise on the
grounds that there is more than one dispute as
the issues relate to more than one contract.
Such an issue arose in the recent case of Delta
Fabrications & Glazing Ltd v Watkin Jones &
Sons Ltd.ii
The claimant had entered two sub-
contracts with the defendant for the provision
of work packages and contended that the
parties had subsequently agreed by their
conduct to vary the contracts so that they were
amalgamated into one, particularly, as
payments for both contracts were dealt with in
one application. A dispute arose between that
parties, which the claimant successfully
referred to adjudication. The adjudicator
concluded that there was one amalgamated
contract. The claimant applied for summary
judgment to enforce the adjudicator’s award.
The defendant resisted on the grounds that the
adjudicator did not have jurisdiction because
the claimant referred a dispute under two
separate contracts in the same adjudication.
The defendant contended that there was an
extensive course of dealings between the
parties relating to various projects and the
parties had entered separate sub-contracts for
works packages on those projects. The parties
had adopted a practice of having one payment
notice for all the claimant’s sub-contracts
under each project without amalgamating the
sub-contracts into one.
Watson J considered that if the court were to
find that the two contracts were varied and
amalgamated by conduct, the court must be
satisfied that the parties’ conduct was
‘unequivocal and consistent’ so that a single
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
14 | P a g e
contract came into existence. If that were the
case, the defence had no real prospect of
success and the court should, as Watson J put
it, ‘grasp the nettle’ by giving summary
judgment. In considering whether a defence
has a real prospect of success, consideration
must be given to the background of the policy
underlying adjudication enforcement, which is
that of maintaining cashflow and of
maintaining the principle of pay now and argue
later.iii
In dismissing the application for summary
judgment, Watson J held that the documents
relied on by the claimant as constituting the
agreement to vary the contracts were not
unequivocal. Indeed, far from satisfying this
requirement the conduct of the parties, both
before and after the alleged agreement to
amalgamate, indicated that the parties did not
intend that the contracts would be
amalgamated or that only one contract
existed. A factual analysis supporting this
conclusion showed that:
Although the defendant’s payment notice
contained an amalgamated figure for payment
due under both contracts, the supporting
documents dealt with both contracts
separately. It did not follow that including the
total of the sums due under both contracts in
one payment notice amounts to an offer to
amalgamate the contracts so that they cease
to exist as separate contracts and become one
contract;
Similarly, although the claimant’s payment
application contained a single combined figure
for both contracts, the supporting documents
consisted of separately prepared, detailed
calculations of the sums due under the two
contracts;
Variations agreed between the parties were
readily identifiable as relating to distinctive
contracts;
The correspondence between the parties was
inconsistent referring to ‘contract’ in the
singular and ‘contracts’ in the plural; and
Rather than referencing the alleged variation
to amalgamate the contracts by conduct, the
Referral Notice contended that the separation
of the contracts ended upon the
commencement of the works. This was
inconsistent with the claimant’s stance at
enforcement.
In conclusion Watson J held that:
42 … the Defendant has not only a real, but a
strong, prospect of successfully defending the
claim on the ground that the adjudicator
lacked jurisdiction, because the Claimant
referred disputes under two separate
contracts to the adjudicator in one referral.’
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
15 | P a g e
Although, not referred to in Delta Fabrications
it is interesting to consider the judgment of
Amec Group Ltd v Thames Water Utilities Ltd.iv
In Amec Group a similar jurisdictional
challenged was raised, namely, that Orders
placed under a framework agreement
constituted separate contracts. Consequently,
the payment dispute dealt with by the
adjudicator related to more than one dispute
as the differences between the parties arose
across multiple contracts. On the wording of
the contract Coulson J held that the dispute
arose under the framework agreement and not
the Orders placed thereunder, thus, the
adjudicator had jurisdiction to deal with the
dispute. However, Coulson J noted that had
the dispute(s) arose under a series of Orders,
the multiple dispute point ‘would probably
have been successful’v
meaning that the
validity of any aggregated applications for
payment could not be dealt with in a single
adjudication. Consequently, such dispute(s)
would lead to:
’… hundreds of separate adjudications, each
for a trifling sum, each arising under an
individual works contract. It seems … that was
not what the parties agreed … and it would not
give rise to a solution that could be described
as commercially sensible.’vi
Delta Fabrications and Amec Group highlights
the commercial practicalities that parties
should have in mind when considering
adjudication provisions in the context of
multiple contracts between the parties on the
same project. Without proper consideration
disputes between the parties may be
prevented from any sort of meaningful
adjudication as aggregate claims arising across
multiple contracts would have to be dissected
and separated into potentially trifling sums.
This may not be commercially viable. If not
properly considered at the outset subsequent
arguments about the amalgamation of
contracts by way of conduct, as advanced in
Delta Fabrications, may be difficult to support.
Showing that conduct was ‘unequivocal and
consistent’ with the amalgamation of the
contracts is an onerous proposition to put
forward.
Paul Hughes
phughes@sharpepritchard.co.uk 1
s108(1).
[2021] EWHC 1034 (TCC).
Ex Novo Ltd v MPS Housing Ltd [2020] EWHC 3804
(TCC), para 4.
[2010] EWHC 419 (TCC).
Amec Group Ltd v Thames Water Utilities Ltd [2010]
EWHC 419 (TCC), para 37.
Amec Group Ltd v Thames Water Utilities Ltd [2010]
EWHC 419 (TCC), para 33.
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
16 | P a g e
SINGAPORE: HIGH COURT CLARIFIES
DIFFERENT DEFINITIONS OF "DAY"
UNDER THE SOP ACT AND
CONSTRUCTION CONTRACTS
In brief
Under the Building and Construction Industry
Security of Payment Act (Cap 30B) ("SOP Act"),
the definition of “day” under Section 2
excludes “a public holiday within the meaning
of the Holidays Act (Cap. 126).” In Tay Choon
Huat, deceased v Soon Kiat Construction &
Maintenance Pte Ltd [2021] 3 SLR 1005 (“Tay
Choon Huat”), the Singapore High Court
(SGHC) considered whether this statutory
definition of "day" would apply to the Articles
and Conditions of Building Contract of the
Singapore Institute of Architects (Lump Sum
Contract, 9th Ed) (“SIA Conditions”).
After reviewing existing authorities, the SGHC
held that parties may contractually agree on a
more stringent deadline for the provision of a
payment response under the SOP Act. Where
the SIA Conditions is applicable, the more
inclusive definition of "day," which includes
public holidays, will apply notwithstanding the
statutory definition provided for under the
SOP Act. The case is a reminder to parties
entering into construction contracts to
expressly define terms used in their contract,
particularly as they may relate to the
calculation of time in relation to the statutory
adjudication process under the SOP Act.
Summary
The employer, Tay Choon Huat (“TCH”),
entered into a construction contract
(“Contract”) with the contractor, Soon Kiat
Construction & Maintenance Pte Ltd (“SK”),
which incorporated the SIA Conditions. Under
Clause 31(15)(a) of the SIA Conditions, TCH was
to respond to an interim payment claim by SK
by providing a payment response "within 21
days" after the interim payment claim had
been served on the employer.
In this case, the payment claim was served on
TCH on 20 April 2020. TCH in turn provided its
payment response on 15 May 2020. The
Adjudication Application (AA) was lodged on
28 May 2020. During this period, there were
multiple public holidays and the parties were
in dispute as to whether the word "day" in
Clause 31(15)(a) of the SIA Conditions included
or excluded public holidays. It was not in
dispute between TCH and SK that the public
holidays on 24 May and 25 May 2020 were to
be excluded from the seven‑day period for the
lodgement of the AA. However, the parties
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
17 | P a g e
were in disagreement as to whether the two
public holidays on 1 May and 7 May 2020
ought to be excluded from the 21‑day period
under the SIA Conditions for TCH to file its
payment response:
On TCH's case, as the word "day" includes
public holidays, the payment response was due
on 11 May 2020 (i.e., 21 calendar days from the
service of the payment claim on 20 April 2020)
and the AA had to be lodged by 27 May 2020.
In contrast, SK argued that as the word "day"
did not include public holidays, the payment
response was only due on 13 May 2020 (i.e., 23
calendar days from the service of the payment
claim on 20 April 2020) and the AA was to be
lodged by 29 May 2020.
The SGHC held that the word "day" included
public holidays on two grounds:
First, the SIA Conditions did not expressly
adopt the definition of "day" as provided for in
the SOP Act. In contrast, the drafters of the SIA
Conditions incorporated the definitions of
"payment claim" and "payment response"
from the SOP Act.
Second, the court considered the use of the
word "day" in other parts of the Contract,
which supported the interpretation of "day" as
including public holidays. For example, the
liquidated damages clause expressly provided
that the Contract period would include
Sundays, public holidays and rest days.
Key takeaways
This case confirms that the definition of “day”
under the SOP Act is not applicable to the SIA
Conditions. The SGHC also confirmed that
parties may contractually agree on a more
stringent deadline for the provision of a
payment response under the SOP Act.
The SGHC also cautioned that "[u]ltimately, the
particular contract in each case stands to be
construed" and whether statutory definitions
are incorporated would depend on how the
contract is to be construed. Parties should
therefore be careful when drafting their
construction contracts to ensure that they
expressly specify definitions for periods of time
and whether such periods are inclusive or
exclusive of public holidays.
Given how seriously the statutory timelines
under the SOP Act are typically adhered to,
parties should pay particular attention to the
definitions of time periods and the calculation
of timelines in their contracts. Where there
may be ambiguity as to these matters, parties
should err on the side of caution and seek
advice to avoid falling foul of the SOP Act.
Baker McKenzie - Nandakumar Ponniya,
Wong Tjen Wee, Daniel Ho and Daryl Yang
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
18 | P a g e
ONE YEAR IN REVIEW: A FIRST-
HAND LOOK AT AN ADJUDICATION
UNDER THE ONTARIO
CONSTRUCTION ACT
Introduction
In June 2020, Glaholt Bowles LLP completed
one of the first adjudications under the
new Construction Act, R.S.O. 1990, c. C.30 (the
“Act”).
The adjudication provisions under Part II.1 of
the Act came into force on October 1, 2019
and were developed to ensure continuity of
work on jobsites and cash flow through the
construction pyramid.
Adjudication is available where both the
procurement process (if any) is started, and
the contract is executed, after October 1, 2019.
It is unavailable in situations where the con-
tract may have been executed after October 1,
2019 but the procurement process was
commenced prior to that date. In other
words, both the procurement process (if any)
must have commenced and the contract must
be formalized after October 1, 2019 for
adjudication to be an option.
This article discusses a first-hand experience of
legal advocacy in an adjudication and provides
insight into whether this new form of dispute
resolution serves to meet the legislative goal of
efficient resolution of contract disputes on
construction sites.
The Decision to Adjudicate
The decision to pursue adjudication on behalf
of a subcontractor client (the “Claimant”) was
based on several factors including availability
of adjudication, the nature of the dispute and
client cost considerations.
Our firm saw an opportunity to explore a quick
form of resolution which had the potential to
meet the needs of our client. The claim
centered on a residential project dispute
between two private individuals and involved
no procurement process. Section 87.3 (4) of
the Act, the transition provision, makes it clear
that in determining the availability of
adjudication, the contract governs.
Here, the contract between the contractor and
owner of the residence had been formalized
after October 1, 2019. The subcontractor’s
agreement was also formalized after October
1, 2019. It is important to note that had the
contract been effective prior to October 1,
2019, it would not have mattered that the
Claimant, as subcontractor, entered into the
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
19 | P a g e
agreement after that date. Adjudication would
not have been available in those
circumstances.
We grappled with a few anomalies in deciding
whether to pursue adjudication. First, there
was no written agreement but only an oral
agreement along with payment records and
various communications (emails, texts) related
to the subcontract. Second, section 13.5(3) of
the Act explicitly states that adjudication is not
available when a contract or subcontract is
complete, unless the parties agree otherwise.
In our case, if section 13.5(3) had been raised,
we were prepared to take the position that the
“completion” of a contact was not the same as
an effective termination of the contract (as in
our case) and therefore the adjudication
period had not expired for the Claimant. To
reiterate, adjudication is meant to be a “real
time” resolution vehicle for active projects
which is why it is unavailable in contracts that
are completed.
The types of disputes that may be referred for
adjudication are listed under section 13.5(1) of
the Act. We determined, based on the facts,
that the Claimant’s dispute fell into the cat-
egory of “payment under the contract”.
We continued our analysis of whether to
pursue adjudication by taking stock of the
scope of the claim. The claim was relatively
small (less than $100,000) and the issue fairly
discrete and straightforward (non-payment).
Section 13.5(4) of the Act explicitly states that
unless the parties agree otherwise, ad-
judication should only address a single matter.
We were confident that the facts of the claim
met this requirement.
Finally, we were conscious of the Claimant’s
costs and business needs. As the operator of a
sole proprietorship, the Claimant’s priority was
to recoup funds as quickly as possible.
Adjudications can be completed in writing and
written materials have strict page limits and
submission deadlines. Importantly, a
determination must be made by the
adjudicator within 30 days (s.13.13(1)) unless
an extension of time is approved with written
consent of the parties (s.13.13(2)). An
attractive feature of adjudication is the ability
to avoid expansive hearings and protracted
pleadings, which are typical of traditional lien
actions.
Following our review of the Claimant’s dispute,
we decided adjudication was appropriate in
the circumstances. We issued a Notice of
Adjudication to opposing counsel as required
under section 13.7(1) of the Act.
Ontario Dispute Adjudication For
Construction Contracts (ODACC)
On July 18, 2019, the Province of Ontario
announced the appointment of ADR Chambers
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
20 | P a g e
as the Authorized Nominating Authority under
section 13.2(1) of the Act.[1]
ADR Chambers, for the purposes of carrying
out its mandate, operates under the title
Ontario Dispute Adjudication for Construction
Contracts (“ODACC”). ODACC oversees the
appointment of adjudicators and each
adjudication proceeding.
ODACC’s website is a critical tool in the
adjudication process. It acts as both a source of
information and, if so desired, the
administrative centerpoint of the proceeding
via the online portal.
In our case, we used the online portal and
found it user-friendly. After registering an
account, we were able to create a file online
for the new claim. We completed and
electronically submitted the online form for
the Notice of Arbitration.
Each party (or their counsel) must register for
an ODACC account to use the online portal. The
online portal can be used to send and receive
all materials pertaining to the claim. The
adjudicator and the parties can also use it for
direct communication. All conversation
histories are saved to the system. When a
message is sent or received, it is viewed by all
parties along with an ODACC administrative
coordinator.
Using the online portal is more efficient than
email or hardcopy correspondence. The portal
keeps the adjudication organized, with all
information and required next steps clearly
displayed on the user “dashboard”. The portal
is truly a “one-stop shop” for carrying out an
adjudication proceeding under the Act.
Notifications are sent to the user’s email
whenever materials are uploaded to the online
portal or a new message is available. We
experienced some technical glitches where
notifications were significantly delayed, but
ODACC quickly resolved that issue and has
since made instant notification a reliable
feature for users.
It is not required that parties register and use
the online portal as part of the adjudication.
Given that adjudications will likely be in writing
in most cases, the option remains to circulate
documents and other correspondence via
email, fax or mail. However, the online portal
is recommended based on our experience.
Even if a party does decide to use the online
portal, the regulations under the Act still
require that any documents (including the
Notice of Adjudication) be “given” to the op-
posing side under the rules of court (s.13.7(1)).
In other words, despite using the online portal
to submit all documents, we still formally
served the materials on opposing counsel.[2]
The Adjudication Process
Notice of Adjudication
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
21 | P a g e
The Notice of Adjudication is an important
document for the Claimant because it must
concisely describe the dispute in 250 words or
less. In addition, it must include: (1) the
Claimant’s suggested adjudicator; and (2) the
suggested procedure for conducting the
adjudication.
I. Selecting an Adjudicator
In selecting a proposed adjudicator, we had
two options. The first option was to review the
ODACC registry of adjudicators and select from
the extensive list of certified adjudicators. The
registry provides background details of each
adjudicator including their profession, years of
experience, professional memberships,
languages spoken and fee range. The second
option is choosing a certified adjudicator based
on recommendations from colleagues or other
networks. In our case, our proposed
adjudicator was based on a short list of
recommendations from other practicing
construction lawyers.
It is not required that an individual be a
licensed lawyer in Ontario to be certified as an
adjudicator. Many are accountants, project
managers, architects, quantity surveyors or
engineers. Depending on the nature of the
dispute, some parties may not want a lawyer
as an adjudicator. Instead, the parties may
decide that an adjudicator with training and
depth of experience in a highly technical
profession (e.g. structural engineering) is
better suited to make a determination.
Still, any adjudicator has the ability to request
the participation of an independent “assistant”
under section 13.12(5) of the Act.
If the parties cannot agree to an adjudicator,
one will be assigned by ODACC.
II. Selecting an Adjudication Procedure
ODACC’s website provides four (4) “pre-
designed” options for conducting an
adjudication. The first three options are strictly
in writing, where the parties exchange written
materials of varying lengths. The fourth option
involves a 30-minute oral presentation by each
party.
If none of the four pre-designed procedures fit
the needs of the parties, a fifth option is for the
parties, with input from the adjudicator, to
develop a customized process. A customized
process may involve, for instance, a site visit or
the appointment of an assistant. An assistant is
an experienced professional such as an
architect, engineer, or actuary who carries out
the role of an expert in helping the adjudicator
determine facts in question prior to reaching a
determination.
Each type of procedure has its own cost
implications. Adjudicator fees can range from a
flat fee of $800 all the way to hourly rates of
$750 per hour depending on both the amount
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
22 | P a g e
of money in dispute and the complexity of the
issue. In our case, the adjudicator’s fee was
due 10 days after the adjudicator agreed to
hear the matter.
The Claimant and Respondent each pay 50% of
the adjudicator’s fee and are expected to cover
their own legal costs unless the adjudicator
determines otherwise.
In our case, we initially selected the pre-
designed process #1, which allows for a
maximum of 2 pages of written submissions
from both parties. However, based on the
adjudicator’s recommendation, all parties
agreed to pre-designed process #2, which
allows the Claimant a total of 5 pages of sub-
missions and a one-page reply. The
Respondent is also allowed a total of 5 pages.
The adjudicator must approve the selected
procedure for conducting the adjudication. It
was helpful to have the adjudicator’s input in
selecting the procedure because we had
initially underestimated the length of written
submissions we would need to effectively
advocate our client’s position.
A more difficult decision is determining
whether written submissions will suffice or if
your client would benefit from the
comparatively more costly and time-
consuming options of oral submissions or site
visits. The need to ensure your client is
positioned for the best possible outcome is
paramount and that may mean that the
truncated pre-design procedures are not suit-
able given the substantive issue in dispute.
Supporting Documents
After we submitted our notice of adjudication
and received confirmation of the adjudicator’s
approval to hear the matter, we had five (5)
days to submit our supporting documents.
Akin to a statement of claim, our supporting
documents consisted of a 4-page, written
advocacy piece of the issue and why the
Claimant was entitled to recovery. The
Respondent was given 7 days to submit a 5-
page response. The Claimant was then given 3
days to issue a 1-page reply.
Attached documents such as contracts and
invoices are not counted in the page limit.
However, it is good practice to clarify what
limits, if any, might be placed on the number of
attachments allowed in the adjudication. In
some cases, the need for additional documents
(emails, text, etc.) may be necessary to
establish key facts. Communication between
parties and with the adjudicator is essential to
setting the parameters of what is acceptable.
Section 13.12(1) gives the adjudicator
significant flexibility in overseeing the conduct
of the adjudication.
Determination
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
23 | P a g e
The adjudicator is required to render a
determination within 30 days of receiving all
documents (s. 13.13(1)). In our case, we
received a determination in 13 days.
We were satisfied with the quick turnaround
but recognize that this may not occur in other
cases. External factors that impact scheduling
may arise or the complexity of the issues may
require a longer period of analysis and review
of materials by the adjudicator.
ODACC uploaded the final determination with
written reasons to the online portal. Seven (7)
days later, a certified copy of the
determination was also uploaded to the online
portal.
As soon as we received the certified copy of the
determination, we filed it with the court per
section 13.20 of the Act, thus making it
enforceable as any other court order. In
accordance with section 13.20(3), we
contacted opposing counsel and provided
notice that the determination had been filed
with the court.
Parallel Proceedings
Notwithstanding the decision to pursue
adjudication, an important practice tip is to
ensure that any claim for lien is properly
preserved and perfected under the Act.
In our case, the Claimant pursued both the
adjudication and a standard lien claim. During
the adjudication period, we continued to serve
pleadings and communicate with opposing
counsel concerning the lien action. It is prudent
to protect a client’s lien rights in the event the
lien remains the only viable method of
enforcement.
The determination of an adjudicator is the
equivalent of an interim order. Per Section
13.15, it is binding on the parties until a later
determination by a court or arbitrator or until
the parties enter into a written agreement re-
specting the adjudicator’s decision.
If the parties accept the determination and
thereafter forgo the lien action, another key
practice tip is to seek an order on a without
costs basis when discontinuing the lien action.
If this is not done, there remains an opportun-
ity for the defendant to make a motion within
30 days of the discontinuance to seek such
costs under Rule 23.05(1) of the Rules of Civil
Procedure, R.R.O. 1990, Reg. 194.
Secondly, parties should strongly consider
executing a mutual “full and final” release to
avoid the resurgence of future claims related
to the matter already addressed in the
adjudication.
If a party disagrees with the adjudicator’s
determination, the option remains for them to
seek the court’s final disposition in the lien
action. However, under section 13.15(2), the
court or an arbitrator may consider the merits
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
24 | P a g e
of a matter decided by the adjudicator. In
other words, seeking a final determination in a
separate forum will not necessarily lead to a
different result from the adjudication.
A party that disagrees with the outcome of an
adjudication has the option of seeking judicial
review of the decision, with leave of the
Divisional Court, as prescribed in section
13.18(1) of the Act.
The lien action was discontinued in our case
and judicial review was not sought by any of
the parties. Still, anyone participating in an
adjudication should be attuned to the reality of
parallel proceedings, especially those involving
lien actions and should be prepared to protect
their client’s interests.
Conclusion
As one of the first completed adjudications in
Ontario, our experience confirms what the
legislators hoped would be the impact of
adjudication. We found the process to be quick
and relatively inexpensive as compared to a
lien action or other legal proceeding which can
seriously hamper the progress of a
construction project.
We were impressed by the thoroughness of
the analysis and extensive written reasons of
the adjudicator. There were no concerns that
the adjudicator was engaging in what some
have suggested may be a form of “quick and
dirty” or “rough” justice. On the contrary, the
adjudicator was actively involved in the
process and provided direction to ensure the
proceedings ran smoothly and all parties
would have a fair opportunity to present their
case.
Administratively, the ease of use of ODACC’s
online portal, along with the pre-designed
forms of adjudication made participation
seamless. In our case, the fast turnaround in
receiving a determination removed any doubt
that adjudication can be the “real time”
dispute resolution tool that it is intended to be.
If adjudication is going to have the long-term
impact of maintaining continuity of work on
construction projects and cashflow, then
industry stakeholders and their counsel will
need to utilize adjudicationwhere appropriate.
An interesting study would be the short and
long-term effects of these new provisions in
the Act. However, such a study cannot take
place until there is a sufficient number of
adjudications.
Adjudication has the potential to save costs
and maintain the focus on bringing projects to
completion. With these priorities in mind, we
are hopeful that adjudication can serve the
construction industry well in this expanded era
of alternative dispute resolution.
[1] https://adrchambers.com/wp-content/
uploads/2019/07/announcement.pdf
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
25 | P a g e
[2] Section 16.1(1), O. Reg. 306/18:
Adjudications under Part II.1 of the Act.
Patricia Joseph
Associate
T:(416) 368-8280
Direct Line: (647) 699-5431
PatriciaJoseph@glaholt.com
FALLING INTO JURISDICTIONAL
ERROR UNDER SECURITY OF
PAYMENT LEGISLATION
The process of adjudication under the security
of payment legislation requires adjudicators to
reconcile difficult requirements, namely, to
determine often complex legal issues within a
short time frame, and to observe the strict
requirements of the legislation. If the right
balance isn't struck, adjudicators may fall into
jurisdictional error. This is what occurred in the
recent case of Total Lifestyle Windows Pty Ltd
v Aniko Constructions Pty Ltd & Anor [2021]
QSC 92.
Total made a payment claim against Aniko
under a construction contract and Aniko
denied liability in its payment schedule. Total
proceeded to make an adjudication application
under the Building Industry Fairness (Security
of Payment) Act 2017 (Qld) and the
adjudicator found in favour of Aniko. In issue in
this case was whether the determination was
invalidated by jurisdictional error because the
adjudicator:
considered reasons included in Aniko's
adjudication response that had not been
included in its payment schedule; and
failed to consider a relevant document that
had been submitted by Total.
The Court agreed that the adjudicator erred in
each instance, and declared the resultant
determination void. In reaching this
conclusion, the Court considered the operation
of certain provisions of the Act, relevantly:
section 88 – in deciding an application, an
adjudicator may only consider matters
prescribed in subsection (2), which includes
the provisions of the construction contract in
issue, the payment claim and the payment
schedule and, in respect of each, "all
submissions, including relevant documents,
that have been properly made" in support of
the claim or schedule respectively;
section 88(3) – an adjudicator must not
consider "a reason" included in an adjudication
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
26 | P a g e
response to an adjudication application where
section 82 prohibits the inclusion of the
reason; and
section 82 – an adjudication response "must
not include any reasons (new reasons) for
withholding payment that were not included in
the payment schedule".
The Court considered, and rejected, various
arguments advanced by Aniko regarding the
provisions of the Act dealing with "new
reasons". With respect to one of Total's claims,
Aniko's adjudication response relied on – and
the adjudicator applied – a clause of the
contract (clause 18) that was not raised in
Aniko's payment schedule. Aniko contended
that:
reference to clause 18 was not made in the
payment schedule because the clause had not
been referred to in Total's payment claim. The
Court noted in response that "s 69(c) of the Act
requires a respondent to include all of its
reasons for withholding payment in its
payment schedule and not just those that are
specifically raised or prompted by the payment
claim";
section 82(3)(c) of the Act (which states an
adjudication response may include
"submissions relevant to the response")
allowed it to raise the operation of clause 18.
The Court disagreed, stating that this provision
"must be read subject to section 82(4) which
provides that an adjudication response must
not include any reasons for withholding
payment that were not included in the
payment schedule"; and
the operation of clause 18 was within the
adjudicator's jurisdiction because section
88(2)(b) permits consideration of the relevant
construction contract. Dispensing with that
argument, the Court held that section 88 "must
be read as a whole", and that while an
"adjudicator might consider the provisions of
the construction contract, the adjudicator may
not consider a reason associated with a
particular provision if it is a reason which falls
within section 88(3)."
The Court also noted that the prohibition
imposed by section 88(3)(b) "is a very wide
restriction", that it is immaterial whether a
proscribed reason forms part of an
adjudicator's decision. Rather, once such a
reason is considered by an adjudicator, "then
section 88(3)(b) has been breached, whether
or not the consideration leads to a particular
decision."
On the matter of the adjudicator's failure to
consider a relevant document submitted by
Total, Aniko pointed to the fact the
adjudicator, in his determination, stated "he
had had regard to 'the payment claim to which
the Application relates, together with all
submissions, including relevant
documentation'”. While conceding that
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
27 | P a g e
adjudicators are subject to "extraordinary
pressure" when dealing with applications, and
that "[i]nfelicity of expression is not a ground
for finding that there has been an omission to
comply with the Act", nevertheless, the Court
held that the document in issue was of such
import to Total's case, squarely contradicting
the case advanced by Aniko (that was accepted
by the adjudicator), that reference to it should
have been made:
"Merely saying that one has had regard to all
relevant documentation is not conclusive on
that issue. The omission to refer to a document
of considerable importance … allows the
inference to be drawn that regard was not had
to it."
The case not only demonstrates the strictness
with which requirements of the Act relating to
adjudication applications are applied, but also
the importance of considering, and including in
payment schedules, all of the arguments on
which a respondent may wish to rely.
CIPAA: ADJUDICATORS' POWERS TO
ORDER REMEDIES AND INTEREST
WHEN PAYMENT CLAUSE IS
UNENFORCEABLE
Introduction
Section 25 of the Construction Industry
Payment and Adjudication Act (CIPAA) 2012
lists adjudicators' extensive powers in
adjudication proceedings, including the power
to award financing costs and interest. The
recent high court decision in First Commerce
Sdn Bhd v Titan Vista Sdn Bhd and another
case(1) examined the extent of an
adjudicator's powers to determine remedies
and interest in unique circumstances where a
payment clause was void and the default
statutory implied payment provision in the
CIPAA was pleaded.
Facts
First Commerce Sdn Bhd was appointed as the
main contractor by the employer of a project
to build and complete the super structure of
the project. Upon being notified by the
employer, the architect directed First
Commerce to appoint Titan Vista Sdn Bhd as its
nominated subcontractor to perform part of
the project. Accordingly, First Commerce
issued a letter of award to Titan Vista for such
work. The letter stated that the terms and
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
28 | P a g e
conditions of the Malaysian Institute of
Architects (PAM) Nominated Subcontract 2006
were incorporated into the contract between
the parties. Further, Clause 9 of the letter of
award provided that the payment for the
certified amounts had to be paid in the form of
cheques from the employer within 45 days
from the date of the architect's certificates.
In the course of executing the contracted work,
Titan Vista commenced an adjudication against
First Commerce pursuant to the CIPAA to
recover payment for four unpaid interim
certificates. Specifically, Titan Vista claimed an
outstanding sum of approximately RM2.37
million and late payment interest. Titan Vista's
adjudication reply also stated that its claims
were based on Clause 9 of the letter of award
and pleaded that the default payment
provisions in Section 36 of the CIPAA would
apply if Clause 9 of the letter of award was
found to be a conditional payment prohibited
by Section 35 of the CIPAA.
After hearing both parties, the adjudicator
decided in favour of Titan Vista. The
adjudicator found that Clause 9 of the letter of
award was unenforceable as it was a
conditional payment provision prohibited by
Section 35 of the CIPAA. The adjudicator
referred to the "Period of Honouring
Certificates" found in Clause 30 of the
Appendix to the PAM Nominated Subcontract
2006, instead of Section 36 of the CIPAA as had
been pleaded; he ordered First Commerce to
pay the amounts certified and claimed by Titan
Vista within 21 days from the date of each
interim certificate.
Dissatisfied with the adjudication decision,
First Commerce relied on Sections 15(1)(b),
15(1)(c) and 15(1)(d) of the CIPAA to set aside
the adjudication decision at the high court.
Titan Vista, on the other hand, filed an
originating summons pursuant to Section 28 of
the CIPAA at the high court to enforce the
adjudication decision as a judgment when First
Commerce failed to pay in accordance with the
adjudication decision. Both applications were
heard on the same day before the same court.
Issue
At the high court, First Commerce's main
contention was that the adjudicator had erred
in ordering it to pay the amounts certified and
claimed by Titan Vista based on the due dates
which he had set (ie, within 21 days of the date
of the interim certificates) as opposed to the
due dates pleaded by Titan Vista (ie, within 45
days of the date of the interim certificates
pursuant to Clause 9 of the letter of award).
This, in turn, had resulted in excessive interest
being awarded to Titan Vista.
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
29 | P a g e
Decision
Justice Lim Chong Fong found that Titan Vista
had not specifically confined its claims to
Clause 9 of the letter of award as it had
requested payment of the interim certificates
to be based on either:
Clause 9 of the letter of award; or
Section 36 of the CIPAA if Clause 9 of the letter
of award was void in contravention of Section
35 of the CIPAA.
Hence, the adjudicator had acted within his
jurisdiction based on the disputes referred to
him. The judge also held that adjudicators are
not bound by the disputes referred to them in
the exact way as pleaded by the parties,
especially with regard to the remedies sought.
In the present case, the judge ruled that the
adjudicator, having decided that Clause 9 of
the letter of award was void and
unenforceable, need not decide on the issue of
interest based on Section 36 of the CIPAA as
pleaded by Titan Vista because Section 25(o) of
the CIPAA authorises adjudicators to decide on
issues of interest, including the date of accrual,
as they see fit. It was therefore justified for the
adjudicator to adopt the express provision
found in PAM Nominated Subcontract 2006
which binds both parties in lieu of Section 36 of
the CIPAA.
Comment
The high court decision is a welcome judgment
for the construction industry, especially unpaid
parties as they are not strictly bound by their
pleaded case, particularly with regard to the
remedies sought. However, this decision
should not be used as a general principle for
unpaid parties to broaden their claim against
non-paying parties, bearing in mind the
application of Section 27(1) of the CIPAA.
An appeal against this decision is pending
before the Court of Appeal.
Endnotes
(1) [2021] MLJU 376.
Gan Partnership - Min Lee Tan, Yuen
Wah Foo
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
30 | P a g e
UK ADJUDICATORS EDINBURGH
ADJUDICATION & ARBITRATION
CONFERENCE – 5 MARCH 2021
The UKA 2021 Edinburgh Adjudication &
Arbitration Conference took place online on
the 5 March 2021 and had over 900
registrations for the free conference. Many
thanks to all of the speakers and supporting
organisations.
The conference video can be viewed at:
https://www.ukadjudicators.co.uk/resources
TCC COURT JUDGEMENTS
April
• Beattie Passive Norse Ltd & Anor v
Canham Consulting Ltd [2021] EWHC
1116 (TCC) (30 April 2021)
• Boxwood Leisure Ltd v Gleeson
Construction Services Ltd &
Anor [2021] EWHC 947 (TCC) (19 April
2021)
• Celtic Bioenergy Ltd v Knowles
Ltd [2021] EWHC 1352 (TCC) (19 April
2021)
• Dana UK Axle Ltd v Freudenberg FST
GmbH [2021] EWHC 1027 (TCC) (23
April 2021)
• Delta Fabrication & Glazing Ltd v
Watkin Jones & Son Ltd [2021] EWHC
1034 (TCC) (30 April 2021)
• Good Law Project Ltd & Anor v
Secretary of State for Health and Social
Care [2021] EWHC 1223 (TCC) (22 April
2021)
• Good Law Project Ltd v Minister for the
Cabinet Office [2012] EWHC 1083
(TCC) (16 April 2021)
• Good Law Project Ltd v Secretary of
State for Health And Social Care [2021]
EWHC 1237 (TCC) (29 April 2021)
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
31 | P a g e
• Kang & Anor v Pattar [2021] EWHC
1101 (TCC) (28 April 2021)
• Prater Ltd v John Sisk & Son (Holdings)
Ltd [2021] EWHC 1113 (TCC) (30 April
2021)
May
• Beattie Passive Norse Ltd & Anor v
Canham Consulting Ltd (No. 2
Costs) [2021] EWHC 1414 (TCC) (28
May 2021)
• Dana UK AXLE Ltd v Freudenberg FST
GmbH [2021] EWHC 1413 (TCC) (26
May 2021)
• Davies & Davies Associates Ltd v Steve
Ward Services (UK) Ltd [2021] EWHC
1337 (TCC) (19 May 2021)
DRBF’S 20TH ANNUAL
INTERNATIONAL CONFERENCE AND
WORKSHOP
30 JUNE - 2 JULY 2021 LISBON,
PORTUGAL
https://www.drb.org/2021-06-lisbon-home-
page
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
32 | P a g e
FORTHCOMING EVENTS
Tuesday, June 8, 2021 - 6:30 PM
Causation in English Construction Law: time
for a re-statement?
Online
Chair: Professor Anthony Lavers
Speaker(s): David Sawtell, 39 Essex Chambers
For more info
Tuesday, June 15, 2021 - 9:00 AM
An Introduction to Delay Claims: Part 2
Chair: Rebecca Shorter (Partner, White &
Case)
Speaker(s): Valia Dousiou (Blackrock)
For more info
Thursday, June 24, 2021 - 5:00 PM
Making best use of the RIAI suite of contracts
Online
Moderator: Paul Darling QC
Speaker(s): Arran Dowling-Hussey, James
O'Donoghue, Chartered Architect, Bluett &
O'Donoghue, Dublin & Kilkenny & Niall
Meagher, Interactive Project Managers
(Dublin)
Venue: Online
For more info
Tuesday, June 29, 2021 - 9:00 AM
An Introduction to Quantum: Part 1
Speaker(s): Patrick Clarke (Atkin Chambers)
For more info
Monday, July 5, 2021 - 9:00 AM
BIM in 2021: a look at current and future
trends
Online
Moderator: Rory Kirrane SC, Mason Hayes &
Curran LLP
Speaker(s): May Winfield, Buro Happold;
Ralph Montague, Arcdox & David-John Gibbs,
Gammon Construction
Venue: Online
For more info
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
33 | P a g e
Tuesday, July 6, 2021 - 6:30 PM
Factual witness evidence: who needs it? (NLC)
London
Chair: Rowan Planterose, SCA President
Speaker(s): Roger Ter Haar QC and Kim
Franklin QC, Crown Office Chambers
Venue: National Liberal Club, 1 Whitehall Pl,
Westminster, London SW1A 2HE
For more info
Tuesday, July 6, 2021 - 6:30 PM
Factual witness evidence: who needs it?
(Online)
Online
Chair: Rowan Planterose, SCA President
Speaker(s): Roger Ter Haar QC and Kim
Franklin QC, Crown Office Chambers
Venue: Online
For more info
Tuesday, July 13, 2021 - 9:00 AM
An Introduction to Quantum: Part 2
Speaker(s): James Morris (Partner, Mayer
Brown) & Sue Kim (Director, HKA)
For more info
Wednesday, July 28, 2021 - 6:00 PM
EU litigation after Brexit
Chair: Alison Garrett, Mills & Reeve LLP
Speaker(s): Jennifer Jones of Atkin Chambers,
Mathias Cheung and Caroline Greenfield
For more info
Thursday, August 5, 2021 - 5:00 PM
SCL Networking Evening
London
Venue: The Yacht London, Upper Deck, Temple
Pier, Victoria Embankment, London WC2R 2PN
Full details in this flyer
For more info
Tuesday, September 7, 2021 - 9:00 AM
An Introduction to Disruption Claims
Speaker(s): David Coyne (Associate Director,
Blackrock) & Tom Andrews (Senior Associate,
Osborne Clarke)
For more info
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
34 | P a g e
SCL INTERNATIONAL CONFERENCE
2021
The Society of Construction Law 9th
International Conference has been postponed
till November 2021. The Right Honourable Lord
Justice Coulson will be a keynote speaker at the
Conference.
http://www.constructionlaw2021.com/scl21
WWW.UKADJUDICATORS.CO.UK
JUNE 2021 NEWSLETTER
35 | P a g e
SCL INTERNATIONAL CONFERENCE
2021
The Society of Construction Law 9th
International Conference has been postponed
till November 2021.e Right Honourable Lord
Justice Coulson will be a keynote speaker at the
Conference.
http://www.constructionlaw2021.com/scl21

Contenu connexe

Tendances

UK Adjudicators October 2021 Newsletter
UK Adjudicators October 2021 NewsletterUK Adjudicators October 2021 Newsletter
UK Adjudicators October 2021 NewsletterSeanGibbs12
 
Module 3 law of contracts
Module 3  law of contractsModule 3  law of contracts
Module 3 law of contractsGichelle Amon
 
Chapter 16: Genuine Assent and Contractual Capacity
Chapter 16: Genuine Assent and Contractual Capacity Chapter 16: Genuine Assent and Contractual Capacity
Chapter 16: Genuine Assent and Contractual Capacity Tara Kissel, M.Ed
 
Chapter 14: Agreement: Offer and Acceptance
Chapter 14: Agreement: Offer and Acceptance Chapter 14: Agreement: Offer and Acceptance
Chapter 14: Agreement: Offer and Acceptance Tara Kissel, M.Ed
 
It Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction ContractsIt Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction ContractsFrancis Ho
 
Chapter 13: Nature of Contracts and Contract Remedies
Chapter 13: Nature of Contracts and Contract Remedies Chapter 13: Nature of Contracts and Contract Remedies
Chapter 13: Nature of Contracts and Contract Remedies Tara Kissel, M.Ed
 

Tendances (8)

UK Adjudicators October 2021 Newsletter
UK Adjudicators October 2021 NewsletterUK Adjudicators October 2021 Newsletter
UK Adjudicators October 2021 Newsletter
 
Chapter 15: Consideration
Chapter 15: ConsiderationChapter 15: Consideration
Chapter 15: Consideration
 
UK Adjudicators October 2019 newsletter
UK Adjudicators October 2019 newsletterUK Adjudicators October 2019 newsletter
UK Adjudicators October 2019 newsletter
 
Module 3 law of contracts
Module 3  law of contractsModule 3  law of contracts
Module 3 law of contracts
 
Chapter 16: Genuine Assent and Contractual Capacity
Chapter 16: Genuine Assent and Contractual Capacity Chapter 16: Genuine Assent and Contractual Capacity
Chapter 16: Genuine Assent and Contractual Capacity
 
Chapter 14: Agreement: Offer and Acceptance
Chapter 14: Agreement: Offer and Acceptance Chapter 14: Agreement: Offer and Acceptance
Chapter 14: Agreement: Offer and Acceptance
 
It Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction ContractsIt Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction Contracts
 
Chapter 13: Nature of Contracts and Contract Remedies
Chapter 13: Nature of Contracts and Contract Remedies Chapter 13: Nature of Contracts and Contract Remedies
Chapter 13: Nature of Contracts and Contract Remedies
 

Similaire à UK Adjudicators Newsletter June 2021

Slides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claimsSlides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claimsRobert MacDonald
 
Construction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 aConstruction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 aColin Tomlinson
 
Commercial and Construction Law Update Q2 2015
Commercial and Construction Law Update Q2 2015Commercial and Construction Law Update Q2 2015
Commercial and Construction Law Update Q2 2015Colin Tomlinson
 
Commericial Management and Construction law update 2015 Q2
Commericial Management and Construction law update 2015 Q2Commericial Management and Construction law update 2015 Q2
Commericial Management and Construction law update 2015 Q2Colin Tomlinson
 
Payment in construction contracts: how to get paid
Payment in construction contracts: how to get paidPayment in construction contracts: how to get paid
Payment in construction contracts: how to get paidBarry Hembling
 
Systech insights edition-Mark Woodward Smith
Systech insights edition-Mark Woodward Smith Systech insights edition-Mark Woodward Smith
Systech insights edition-Mark Woodward Smith mark woodward-smith
 
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....Pierrette Khoury BComm/B Laws, GDLP
 
Striking The Balance
Striking The BalanceStriking The Balance
Striking The Balanceproverbs6_31
 
Understanding the Legal Weapons Landlords and Tenants have in Enforcing/Termi...
Understanding the Legal Weapons Landlords and Tenants have in Enforcing/Termi...Understanding the Legal Weapons Landlords and Tenants have in Enforcing/Termi...
Understanding the Legal Weapons Landlords and Tenants have in Enforcing/Termi...Adam Leitman Bailey, P.C.
 
MWWPR Group Sued - Lawsuit Against MWW PR Vs. Byte Dept. Inc.
MWWPR Group Sued - Lawsuit Against MWW PR Vs. Byte Dept. Inc.MWWPR Group Sued - Lawsuit Against MWW PR Vs. Byte Dept. Inc.
MWWPR Group Sued - Lawsuit Against MWW PR Vs. Byte Dept. Inc.EverythingPR
 
Student Project There is no extension of the due date for t.docx
Student  Project   There is no extension of the due date for t.docxStudent  Project   There is no extension of the due date for t.docx
Student Project There is no extension of the due date for t.docxjohniemcm5zt
 
M32089 Construction Contracts And Dispute Resolution.docx
M32089 Construction Contracts And Dispute Resolution.docxM32089 Construction Contracts And Dispute Resolution.docx
M32089 Construction Contracts And Dispute Resolution.docxstirlingvwriters
 

Similaire à UK Adjudicators Newsletter June 2021 (19)

Slides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claimsSlides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claims
 
Construction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 aConstruction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 a
 
Commercial and Construction Law Update Q2 2015
Commercial and Construction Law Update Q2 2015Commercial and Construction Law Update Q2 2015
Commercial and Construction Law Update Q2 2015
 
Commericial Management and Construction law update 2015 Q2
Commericial Management and Construction law update 2015 Q2Commericial Management and Construction law update 2015 Q2
Commericial Management and Construction law update 2015 Q2
 
UK Adjudicators August 2020 newsletter
UK Adjudicators August 2020 newsletterUK Adjudicators August 2020 newsletter
UK Adjudicators August 2020 newsletter
 
Construction Claims
Construction ClaimsConstruction Claims
Construction Claims
 
Payment in construction contracts: how to get paid
Payment in construction contracts: how to get paidPayment in construction contracts: how to get paid
Payment in construction contracts: how to get paid
 
UK Adjudicators September 2019 newsletter
UK Adjudicators September 2019 newsletterUK Adjudicators September 2019 newsletter
UK Adjudicators September 2019 newsletter
 
UK Adjudicators December 2019 Newsletter
UK Adjudicators December 2019 NewsletterUK Adjudicators December 2019 Newsletter
UK Adjudicators December 2019 Newsletter
 
UK Adjdudiators Newsletter June 2019
UK Adjdudiators Newsletter June 2019UK Adjdudiators Newsletter June 2019
UK Adjdudiators Newsletter June 2019
 
Systech insights edition-Mark Woodward Smith
Systech insights edition-Mark Woodward Smith Systech insights edition-Mark Woodward Smith
Systech insights edition-Mark Woodward Smith
 
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
 
Striking The Balance
Striking The BalanceStriking The Balance
Striking The Balance
 
Understanding the Legal Weapons Landlords and Tenants have in Enforcing/Termi...
Understanding the Legal Weapons Landlords and Tenants have in Enforcing/Termi...Understanding the Legal Weapons Landlords and Tenants have in Enforcing/Termi...
Understanding the Legal Weapons Landlords and Tenants have in Enforcing/Termi...
 
Against all odds
Against all odds Against all odds
Against all odds
 
MWWPR Group Sued - Lawsuit Against MWW PR Vs. Byte Dept. Inc.
MWWPR Group Sued - Lawsuit Against MWW PR Vs. Byte Dept. Inc.MWWPR Group Sued - Lawsuit Against MWW PR Vs. Byte Dept. Inc.
MWWPR Group Sued - Lawsuit Against MWW PR Vs. Byte Dept. Inc.
 
Student Project There is no extension of the due date for t.docx
Student  Project   There is no extension of the due date for t.docxStudent  Project   There is no extension of the due date for t.docx
Student Project There is no extension of the due date for t.docx
 
M32089 Construction Contracts And Dispute Resolution.docx
M32089 Construction Contracts And Dispute Resolution.docxM32089 Construction Contracts And Dispute Resolution.docx
M32089 Construction Contracts And Dispute Resolution.docx
 
Public Matters November 2015
Public Matters November 2015Public Matters November 2015
Public Matters November 2015
 

Plus de Sean Gibbs DipArb, FCIARB, FCIOB, FRICS, MICE

Plus de Sean Gibbs DipArb, FCIARB, FCIOB, FRICS, MICE (20)

UKA Newsletter May 2022.pdf
UKA Newsletter May 2022.pdfUKA Newsletter May 2022.pdf
UKA Newsletter May 2022.pdf
 
UK Adjudicators September 2021 Newsletter
UK Adjudicators  September 2021 Newsletter UK Adjudicators  September 2021 Newsletter
UK Adjudicators September 2021 Newsletter
 
UK Adjudicators 2021 London Adjudication & Arbitration Conference pack
UK Adjudicators 2021 London Adjudication & Arbitration Conference packUK Adjudicators 2021 London Adjudication & Arbitration Conference pack
UK Adjudicators 2021 London Adjudication & Arbitration Conference pack
 
UK Adjudicators 2021 London Conference pack
UK Adjudicators 2021 London Conference packUK Adjudicators 2021 London Conference pack
UK Adjudicators 2021 London Conference pack
 
UK Adjudicators London 2021 Conference pack
UK Adjudicators London 2021 Conference packUK Adjudicators London 2021 Conference pack
UK Adjudicators London 2021 Conference pack
 
UK Adjudicators Newsletter August 2021
UK Adjudicators Newsletter August 2021UK Adjudicators Newsletter August 2021
UK Adjudicators Newsletter August 2021
 
Glos CE - material shortages & fluctuations in standard forms of contr5act
Glos CE - material shortages & fluctuations in standard forms of contr5actGlos CE - material shortages & fluctuations in standard forms of contr5act
Glos CE - material shortages & fluctuations in standard forms of contr5act
 
UK Adjudicators Newsletter July 2021
UK Adjudicators Newsletter July 2021UK Adjudicators Newsletter July 2021
UK Adjudicators Newsletter July 2021
 
UK Adjudicators London 2021 Adjudication & Arbitration Conference
UK Adjudicators  London 2021 Adjudication & Arbitration ConferenceUK Adjudicators  London 2021 Adjudication & Arbitration Conference
UK Adjudicators London 2021 Adjudication & Arbitration Conference
 
The need for dispute boards on international waste to energy projects
The need for dispute boards on international waste to energy projectsThe need for dispute boards on international waste to energy projects
The need for dispute boards on international waste to energy projects
 
JCT Dispute Adjudication Board 20221
JCT Dispute Adjudication  Board 20221JCT Dispute Adjudication  Board 20221
JCT Dispute Adjudication Board 20221
 
UK Adjudicators newsletter May 2021
UK Adjudicators newsletter May 2021UK Adjudicators newsletter May 2021
UK Adjudicators newsletter May 2021
 
UK Adjudicators April 2021 newsletter
UK Adjudicators April 2021 newsletterUK Adjudicators April 2021 newsletter
UK Adjudicators April 2021 newsletter
 
UK Adjudicators panel members 14 March 2021
UK Adjudicators panel members 14 March 2021UK Adjudicators panel members 14 March 2021
UK Adjudicators panel members 14 March 2021
 
Vis East Moot Programme 2021
Vis East Moot Programme 2021Vis East Moot Programme 2021
Vis East Moot Programme 2021
 
UK Adjudicators Panel Members
UK Adjudicators Panel MembersUK Adjudicators Panel Members
UK Adjudicators Panel Members
 
Hanscomb Intercontinental brochure expert advisory & expert witness services
Hanscomb Intercontinental brochure expert advisory & expert witness servicesHanscomb Intercontinental brochure expert advisory & expert witness services
Hanscomb Intercontinental brochure expert advisory & expert witness services
 
UK Adjudicators October 2020 Newsletter
UK Adjudicators  October 2020 NewsletterUK Adjudicators  October 2020 Newsletter
UK Adjudicators October 2020 Newsletter
 
Hanscomb Intercontinental expert advisory & expert witness services
Hanscomb Intercontinental expert advisory & expert witness servicesHanscomb Intercontinental expert advisory & expert witness services
Hanscomb Intercontinental expert advisory & expert witness services
 
UK Adjudicators panel members 7 August 2020
UK Adjudicators panel members 7 August 2020UK Adjudicators panel members 7 August 2020
UK Adjudicators panel members 7 August 2020
 

Dernier

A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURYA SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURYJulian Scutts
 
一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理Airst S
 
Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...
Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...
Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...SUHANI PANDEY
 
Relationship Between International Law and Municipal Law MIR.pdf
Relationship Between International Law and Municipal Law MIR.pdfRelationship Between International Law and Municipal Law MIR.pdf
Relationship Between International Law and Municipal Law MIR.pdfKelechi48
 
589308994-interpretation-of-statutes-notes-law-college.pdf
589308994-interpretation-of-statutes-notes-law-college.pdf589308994-interpretation-of-statutes-notes-law-college.pdf
589308994-interpretation-of-statutes-notes-law-college.pdfSUSHMITAPOTHAL
 
一比一原版(UM毕业证书)美国密歇根大学安娜堡分校毕业证如何办理
一比一原版(UM毕业证书)美国密歇根大学安娜堡分校毕业证如何办理一比一原版(UM毕业证书)美国密歇根大学安娜堡分校毕业证如何办理
一比一原版(UM毕业证书)美国密歇根大学安娜堡分校毕业证如何办理A AA
 
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理Airst S
 
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理e9733fc35af6
 
一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理
一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理
一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理Airst S
 
一比一原版赫尔大学毕业证如何办理
一比一原版赫尔大学毕业证如何办理一比一原版赫尔大学毕业证如何办理
一比一原版赫尔大学毕业证如何办理Airst S
 
Code_Ethics of_Mechanical_Engineering.ppt
Code_Ethics of_Mechanical_Engineering.pptCode_Ethics of_Mechanical_Engineering.ppt
Code_Ethics of_Mechanical_Engineering.pptJosephCanama
 
Navigating Employment Law - Term Project.pptx
Navigating Employment Law - Term Project.pptxNavigating Employment Law - Term Project.pptx
Navigating Employment Law - Term Project.pptxelysemiller87
 
Navigating the Legal and Ethical Landscape of Blockchain Investigation.pdf
Navigating the Legal and Ethical Landscape of Blockchain Investigation.pdfNavigating the Legal and Ethical Landscape of Blockchain Investigation.pdf
Navigating the Legal and Ethical Landscape of Blockchain Investigation.pdfMilind Agarwal
 
一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理
一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理
一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理A AA
 
Clarifying Land Donation Issues Memo for
Clarifying Land Donation Issues Memo forClarifying Land Donation Issues Memo for
Clarifying Land Donation Issues Memo forRoger Valdez
 
PPT- Voluntary Liquidation (Under section 59).pptx
PPT- Voluntary Liquidation (Under section 59).pptxPPT- Voluntary Liquidation (Under section 59).pptx
PPT- Voluntary Liquidation (Under section 59).pptxRRR Chambers
 
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxxAudience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxxMollyBrown86
 
Cyber Laws : National and International Perspective.
Cyber Laws : National and International Perspective.Cyber Laws : National and International Perspective.
Cyber Laws : National and International Perspective.Nilendra Kumar
 
ARTICLE 370 PDF about the indian constitution.
ARTICLE 370 PDF about the  indian constitution.ARTICLE 370 PDF about the  indian constitution.
ARTICLE 370 PDF about the indian constitution.tanughoshal0
 
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...Finlaw Associates
 

Dernier (20)

A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURYA SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
 
一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理
 
Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...
Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...
Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...
 
Relationship Between International Law and Municipal Law MIR.pdf
Relationship Between International Law and Municipal Law MIR.pdfRelationship Between International Law and Municipal Law MIR.pdf
Relationship Between International Law and Municipal Law MIR.pdf
 
589308994-interpretation-of-statutes-notes-law-college.pdf
589308994-interpretation-of-statutes-notes-law-college.pdf589308994-interpretation-of-statutes-notes-law-college.pdf
589308994-interpretation-of-statutes-notes-law-college.pdf
 
一比一原版(UM毕业证书)美国密歇根大学安娜堡分校毕业证如何办理
一比一原版(UM毕业证书)美国密歇根大学安娜堡分校毕业证如何办理一比一原版(UM毕业证书)美国密歇根大学安娜堡分校毕业证如何办理
一比一原版(UM毕业证书)美国密歇根大学安娜堡分校毕业证如何办理
 
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
 
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
 
一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理
一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理
一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理
 
一比一原版赫尔大学毕业证如何办理
一比一原版赫尔大学毕业证如何办理一比一原版赫尔大学毕业证如何办理
一比一原版赫尔大学毕业证如何办理
 
Code_Ethics of_Mechanical_Engineering.ppt
Code_Ethics of_Mechanical_Engineering.pptCode_Ethics of_Mechanical_Engineering.ppt
Code_Ethics of_Mechanical_Engineering.ppt
 
Navigating Employment Law - Term Project.pptx
Navigating Employment Law - Term Project.pptxNavigating Employment Law - Term Project.pptx
Navigating Employment Law - Term Project.pptx
 
Navigating the Legal and Ethical Landscape of Blockchain Investigation.pdf
Navigating the Legal and Ethical Landscape of Blockchain Investigation.pdfNavigating the Legal and Ethical Landscape of Blockchain Investigation.pdf
Navigating the Legal and Ethical Landscape of Blockchain Investigation.pdf
 
一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理
一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理
一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理
 
Clarifying Land Donation Issues Memo for
Clarifying Land Donation Issues Memo forClarifying Land Donation Issues Memo for
Clarifying Land Donation Issues Memo for
 
PPT- Voluntary Liquidation (Under section 59).pptx
PPT- Voluntary Liquidation (Under section 59).pptxPPT- Voluntary Liquidation (Under section 59).pptx
PPT- Voluntary Liquidation (Under section 59).pptx
 
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxxAudience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
 
Cyber Laws : National and International Perspective.
Cyber Laws : National and International Perspective.Cyber Laws : National and International Perspective.
Cyber Laws : National and International Perspective.
 
ARTICLE 370 PDF about the indian constitution.
ARTICLE 370 PDF about the  indian constitution.ARTICLE 370 PDF about the  indian constitution.
ARTICLE 370 PDF about the indian constitution.
 
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
 

UK Adjudicators Newsletter June 2021

  • 1. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 1 | P a g e EDITORS COMMENTS The annual London conference takes place on the 19 August 2021 and will be an online conference with a physical networking and drinks event in London in the evening at the Middle Temple. Panel members will have received an email with the links. I am also pleased to confirm that the ‘rookie adjudicator’ has provided an article for this newsletter which newer adjudicators will find of interest. Please do forward articles, events and worthy news for inclusion in forthcoming newsletters. If you would like to take part in the conference as a speaker or sponsor, please do let me now. Our charity partner for the event is the Free Representation Unit and we are looking for donations of raffle prizes to assist them with fundraising at the evening event. Sean Gibbs LLB(Hons) LLM MICE FCIOB FRICS FCIARB, is the Chief Executive Officer of Hanscomb Intercontinental and is available to sit as an arbitrator, adjudicator, mediator, quantum expert and dispute board member. sean.gibbs@hanscombintercontinental.co.uk
  • 2. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 2 | P a g e IS IT TIME TO ‘DEFAULT’ FROM DEFAULT PAYMENT NOTICES? Not long after my last piece regarding ‘technical’ defences to payment claims was included in the Adjudication Society’s Autumn Newsletter, a judgement was handed down in the TCC which caught my eye. The judgement was in the case RGB Plastering Limited v Tawe Drylining and Plastering Limited [2020] EWHC 3028 (TCC), and it surrounded issues connected to those discussed in my last piece. Whilst I won’t go into any great detail as to the facts of the RGB case, for the purposes of this piece I will set out a very brief background to the dispute. Tawe submitted an application for payment to RGB. RGB did not respond to the application with a payment notice or pay less notice, nor did RGB pay Tawe the sum set out in Tawe’s application. Tawe referred the payment dispute to adjudication, seeking full payment of the sum claimed in its application for payment on the basis that RGB had not served a valid payment notice or pay less notice in response to the application therefore its application had become a payee notice in default/default payment notice. The adjudicator agreed with Tawe and awarded it the sum claimed in its application for payment. Subsequently, RGB referred the matter to the Court seeking a declaration that Tawe’s application for payment was invalid because it did not comply strictly with the requirements of sub-contract in relation to the submission of applications for payment (precisely the kind of ‘technical’ defence to payment which I discussed in my last piece). The Court agreed with RGB and granted it the declaration it had sought. This case is yet another example of the situation we, as an industry, seem to have gotten ourselves into since the floodgates were opened by ISG Construction Ltd v Seevic College [2014] EWHC 4007 (TCC). There have been many reported cases since ISG, and undoubtedly hundreds, if not thousands, more which have been settled without coming before the courts. The costs involved are probably eye watering. This, then, leads me to the following questions: i) what benefit does the construction industry actually receive, in reality, from the default payment provisions of the Housing Grants Construction and Regeneration Act 1996 (as
  • 3. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 3 | P a g e amended by the Local Democracy Economic Development and Construction Act 2009); and, ii) does that benefit (if any) outweigh the cost? As a Trainee Quantity Surveyor with Mowlem in the mid-late 1990s, and then as an Assistant Quantity Surveyor with Wates in the late 1990s, I was taught that a payee should always provide full substantiation in support of all sums claimed in each application for payment which it submits to a payer. This substantiation included things like marked-up drawings, marked-up specifications, photographs, copies of instructions, copies of meeting minutes, ‘take-offs’, build-ups to ‘star rates’, cross references to BOQ rates, and suchlike; all of which were to be provided with each application for payment with the sole intention being to support the payee’s right to payment of the sum claimed in the application. If a payee had properly substantiated each of its applications for payment as aforesaid then, if the payer failed or refused to pay the sum claimed in any such application, the payee was in a position to pretty much immediately refer a dispute to adjudication without further delay because it had already prepared all of the documents/substantiation necessary to demonstrate the ‘true value’ of the work which it had completed and which it had claimed in the application. Then along came the Local Democracy Economic Development and Construction Act 2009, and with it some new payment provisions designed to give the previous payment provisions of the Housing Grants Construction and Regeneration Act 1996 some ‘teeth’. It was not until 2015 that this amended legislation really showed its teeth, with the judgement in ISG v Seevic. In essence, following ISG v Seevic a payee could now obtain full payment of the sum claimed in its application for payment without having to actually do any of the detailed work necessary to properly substantiate the sum claimed therein (provided, of course, that the payer had failed to respond to the application for payment with a payment notice or pay less notice). This, in my experience, has encouraged payees to take short cuts when preparing applications for payment; such applications being prepared to a very basic standard and often in the hope that the payer fails to respond with the requisite notices. So, turning to the first question I set out above. Whilst the Construction Act (as amended) may be well intentioned in its aim of facilitating cashflow, does it really achieve this in reality? If a payee submits an application for payment along with full substantiation in support of the sum claimed therein, then what does it matter whether or not the payer serves a payment notice or pay less notice? Surely all that is needed is a mechanism for ascertaining an
  • 4. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 4 | P a g e application date and a final date for payment? If the payer does not pay, by the final date for payment, the sum claimed in an application for payment then, having already prepared and submitted a fully substantiated application for payment, the payee is already in a position to pretty much immediately refer the dispute to adjudication so to have the ‘true value’ of the work declared and paid. The payee could obtain the declaration and payment in adjudication proceedings in similar timescales (if not the same timescales) as it would in what has become commonly termed ‘smash and grab’ adjudication proceedings. In view of the foregoing, what benefit is actually really achieved by the default payment notice provisions of the Construction Act (as amended)? Some may perhaps suggest that the benefits are, in reality, fairly limited. Turning to the second question I set out above. If some were indeed correct to say that the benefits of the default payment provisions of Construction Act (as amended) are, in reality, fairly limited, then at what cost do those benefits come? The now widespread (in my experience) practice of taking short cuts to prepare applications for payment is undoubtedly a fertile breeding ground for conflict. With that conflict often comes an irretrievable deterioration in relationships and significant financial consequences. Is this really what the amended legislation intended? In view of the above, is it time to give serious consideration to repealing the default payment provisions of the Construction Act (as amended)? Would this not encourage payees to set out their claims with fully substantiated clarity and thereby reduce both the opportunity for conflict to arise and the likelihood of conflict actually arising (or, at the very least, reduce the likelihood of conflict subsequently becoming adversarial in nature)? The final date for payment and other relevant provisions (other than the default payment provisions) of the Construction Act could (and, I suggest, should) remain; thereby maintaining the right for a payee who is not paid by the final date for payment to immediately refer the dispute to adjudication on a ‘true value’ basis (having already prepared and submitted with its application for payment the necessary substantiation in support of the sum claimed therein) and have it decided in similar timescales (if not the same timescales), from the date the dispute crystallised, as it would in a ‘smash and grab’ adjudication. Some may say a repealing of the default payment provisions of the Construction Act (as amended) would lead to a reduction in the use of adjudication as a means of resolving conflict in the industry. However, should we, as an industry, not be taking steps to avoid conflict rather than encourage it? Further, would it not mean that adjudicators could actually get on with deciding disputes of substance, rather
  • 5. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 5 | P a g e than technical disputes of little substance at all? Dean Sayers is a Director with Sayers Commercial Ltd, and is available to sit as an adjudicator and arbitrator E: dean@sayerscommercial.co.uk T: 07710 422671 MY FIRST APPOINTMENT – PART 1 BY THE ROOKIE ADJUDICATOR It was the summer of 2019 and I received an email from the Serving Nominator. Like all those who receive such an email, I carried out a quick assessment of the Notice of Adjudication and undertook a conflict check. I was good to go, so I sent my response to the Serving Nominator. The next day I received the email, which confirmed that I had been appointed. This was great news. This is what I had been working towards. This was my first appointment. I had completed my CIArb Diploma in Adjudication in May 2015 and I had gained valuable adjudication experience working as a Party Rep since 2013. But there is something different being appointed as an adjudicator, it all became rather serious. Following confirmation of my Nomination, I carefully prepared my opening communication to the parties, which set out that I had been nominated by UK Adjudicators as the adjudicator, I gave some initial directions such as, I was happy for communications to be exchanged using email and that I only intended to communicate with the persons / organisations set out this letter and then, such as my surprise to be appointed and mainly because I hadn’t quite got round to doing them, I realised that I needed a set of terms of appointment to accompany my first communication. I considered several pieces of information and pulled together a robust set of terms, which I was happy with. Whilst creating these terms, I had to deal with the matter of the hourly rate I should charge to conduct the adjudication and produce a decision for the dispute. What was too much? What was too little? Looking back through the charges received from adjudicators when I had been acting as a party
  • 6. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 6 | P a g e representative, I made a decision, which I felt reflected my standing in the league of adjudicators. For those wondering, the rate was sub £180.00 per hour. So having now completed the first communication and the terms of appointment, I sent the communication to the parties via email using the email addresses stated in the Notice of Adjudication and the UKA Adjudicator application form. Shortly after, I received an acknowledgement from the Referring Party, I now just wanted the acknowledgement from the Responding Party. I waited and waited, and nothing came through (I am talking hours rather than days). As a user of Apple’s Mac Mail I did not have the benefits of Microsoft Outlook and thus no delivery or read receipt facility, so there was no 100% guarantee that the email had been received by the Responding Party; although I was certain it had been, having not received an ‘undeliverable receipt’ from my email domain. Nevertheless, the last thing I wanted, with this being my first appointment, was there to be any issues with claims of breaches of natural justice and allegations only communicating with one party. So I did what most other adjudicators would do (I hope), I printed off two copies of the covering email, my first letter and my terms of appointment (one set for the Referring Party and one set for the Responding Party) with the intention of posting them using royal mail’s track and trace delivery facility. Just as I was about to insert the copies into the envelopes I had a negative thought, “What if the Responding Party had been advised to make my life hard work? What if they were being advised by someone who told them to not play ball and this is the reason why they did not respond to my email after my first communication, which had now prompted me sending the document by post? Negative thoughts I know, but I had seen the way other adjudicators had been treated by party representatives of the responding parties, when I had been the Party Representative of the Referring Party and I wanted to lock all doors, which might be opened by someone looking to cause trouble. To counter the negative thought I decided to not send the communications in envelopes branded with my business logo, but rather in unmarked envelopes only stating the name and address of the parties and the contact names provided to me. Was I being over cautious? A phrase often said to us all by our friends, peers and seniors came to mind, so I adopted the “better safe than sorry” principle and I believe I made the right decision. It certainly did give me peace of mind. Having now enclosed, sealed and addressed the envelopes, I walked to my local Post Office and sent the envelopes tracked for next day delivery, with signature for proof of delivery. The next day, after checking the Royal Mail Track and Trace website, I had confirmation in
  • 7. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 7 | P a g e writing that both parties had received a hard copy of my first communication and my mind was at ease. Now all that I awaited was the Referral. Was it going to come in or had the parties managed to reach a deal and stop the adjudication in its tracks? THE ROOKIE ADJUDICATOR BUILDERS LIEN UPDATE - RED TAPE REDUCTION IMPLANTATION ACT (BILL 62) Background The name of the Alberta Builders’ Lien Act has changed to the Prompt Payment and Construction Lien Act (the PPCLA), and contains new rules and adjudication procedures that will have a transformative impact on the construction industry in Alberta. The PPCLA is anticipated to come into force on July 21, 2021, although the regulations have not yet been released. Bill 37, the Builders’ Lien (Prompt Payment) Amendment Act, 2020 and its proposed amendments to the Alberta Builders’ Lien Act (the Prompt Payment Amendment) have been discussed in BLG’s articles on October 23, 2020 and November 4, 2020. On April 8, 2021, Bill 62, the Red Tape Reduction Implantation Act (Bill 62) received its first reading in the Alberta legislature. Bill 62 contains important information and guidance on the adjudication provisions in the Prompt Payment Amendment, a key feature of the PPCLA. Most critically, Bill 62:
  • 8. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 8 | P a g e Outlines the application and scope of the PPCLA; and Provides further definition to the adjudication provisions in the PPCLA. Scope of the PPCLA Bill 62 excludes construction projects involving the provincial government from the PPCLA, including projects involving crown corporations. Bill 62 also references other entities and agreements to be excluded from the PPCLA’s scope. While Bill 62 states that the PPCLA will apply to “a prescribed class of professionals acting in a consultative capacity”, the Government of Alberta has not yet published guidance or regulations about which professions would fall within this “prescribed class”. Adjudication More importantly, Bill 62 makes significant changes to the adjudication provisions in the PPCLA (the Adjudication Process). Bill 62 stipulates that parties cannot use the Adjudication Process where a court action has been commenced or where the contract is complete. As such, the Adjudication Process appears to be exclusively intended for disputes occurring during the execution of a project. Completed projects While these changes highlight the primary goal of the adjudication provisions of the PPCLA (the faster resolution of disputes during a construction project), they also create uncertainty, potential for delay and inconsistent results. When a project is “complete” is often a point of contention between parties in a construction dispute. Uncertainty stemming from whether a project is complete may result in more court applications, which could result in fewer disputes being subject to the Adjudication Process and create further delays. Notably, as drafted, warranty or remedial work that is usually completed close to or after project completion, may be excluded from the Adjudication Process altogether. Court actions Carving out construction disputes that are the subject of a court action may generate unintended consequences. For example, parties may be incentivized to commence court actions to avoid the Adjudication Process altogether in an attempt to ensure they are able to select the forum for the dispute. Further, there could be instances where a broad court action involves the subject matter and potentially the same parties involved in an Adjudication Process. This raises the possibility of inconsistent results. Without more guidance from the Government of Alberta, the incentive to race to the courthouse and the potential for inconsistent results between courts and
  • 9. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 9 | P a g e adjunction panels adds to the uncertainty that the adjudication provisions of the PPCLA will create. Adjudication orders and judicial review Prior to Bill 62, the PPCLA attempted to make adjudication decisions final by making judicial review the only way to challenge a adjudicator’s decision. To further reinforce the PPCLA’s adjudication provisions against delays associated with court involvement, the PPCLA made adjudication decisions enforceable despite the filing of a judicial review application. Bill 62 walks back the limits on the court’s ability to become involved in a dispute that is subject to the Adjudication Process. Specifically, the order of an adjudicator stemming from a dispute will not be binding where: The Court makes an order in respect of the dispute; An application for judicial review of the determination is made by one of the parties; The parties proceed to arbitration by entering into a written agreement; or The parties settle the dispute by written agreement. The “Exemptions” In addition to raising serious questions about the strength of any order stemming from an Adjudication Process, the Exemptions also act as a bar to the registration (and enforcement) of an adjudication order. The Exemptions create significant uncertainty about how arbitration/meditation clauses, commonly found in construction contracts, will apply to the Adjudication Process. If a party commences an arbitration, are they barred from using the adjudication provisions? If during the course of an Adjudication Process, one party seeks to activate the arbitration clause of their agreement, does this trigger one of the Exemptions? Moreover, do the Exemptions mean that, at any time, a party can make an application to the court in respect of a dispute? As drafted, the Exemptions may provide parties an avenue to engage the court even if they have failed to win the race to the courthouse. Procedural guidance Finally, Bill 62 includes mechanical and procedural provisions required to enforce an order stemming from the Adjudication Process. A party must register an adjudicator’s order with the Clerk of the Court of Queen’s Bench of Alberta (the Clerk of the Court) and provide a written notice to the other party within 10 days from the date that the Clerk of the Court registers the adjudicator’s order. Once the Clerk of the Court registers the adjudicator’s order it has the same effect as a court order. Bill 62 also includes two important
  • 10. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 10 | P a g e limitations dates that stipulate that an adjudicator’s order cannot be registered: Two years after the order is issued; or Two years after the court has rendered a decision on an application for judicial review. Conclusion Bill 62 raises further uncertainty about the applicability of the PPCLA. As a result, we expect additional changes in the form of further amendments or publication of draft regulations will be required to better frame the purpose and scope of the PPCLA. We will continue to monitor the progress of Bill 37 and Bill 62 as both pieces of legislation receive further consideration by the Alberta legislature and provide updates as they become available. It remains clear that construction industry players, of all sizes, will need to take proactive steps to prepare for and mitigate against the uncertainty and new risks created by these reforms to the Alberta Builders’ Lien Act. CONFACT CORE CONSTRUCTION CC V JLK CONSTRUCTION (PTY) LTD The Western Cape High Court handed down judgement in the matter of Confact Core Construction CC v JLK Construction (Pty) Ltd on 25 November 2020. Confact had applied for an order giving effect to an adjudication award. JLK alleged that the referral to adjudication was not competent. Failing such a finding, JLK counter applied for an order suspending the implementation of the adjudication award on the grounds that it would suffer substantial injustice should the award be given effect. The agreement between Confact and JLK was governed by the JBCC Edition 5.0 N/S subcontract agreement. If a disagreement arises, Clause 40 thereof requires the aggrieved party to give notice to the other to resolve the disagreement. If the disagreement is not resolved within 10 working days of this notice it is deemed to be a dispute and the aggrieved party has the option to refer it to either adjudication or arbitration. The adjudication is governed by the JBCC Adjudication Rules which stipulate that the parties must appoint the adjudicator by mutual agreement within 5 days of the disagreement being deemed a dispute. Where an
  • 11. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 11 | P a g e appointment is not made in that period, either party may request the nominating body to appoint an adjudicator. The adjudicator’s decision is binding on the parties who must give effect to it without delay unless and until it is subsequently revised by an arbitrator. The Principal Building Agreement between the Employer and JLK was terminated in December 2018, which resulted in the termination of the subcontract agreement between JLK and Confact. In January 2020 Confact demanded payment of sums due in respect of work done and the return of retention. JLK did not respond and Confact gave notice to JLK to resolve the disagreement in February 2020. The disagreement was not resolved within 10 working days, was deemed to be a dispute and Confact elected to refer it to adjudication. JLK and Confact were not able to agree on an adjudicator and Confab requested the nominating body to appoint an adjudicator in March 2020. Confact made submissions to the adjudicator in May 2020, but JLK failed to respond. The adjudicator delivered a decision in favour of Confact in June 2020. Despite demand, JLK failed to make payment in terms of this award. The dispute arose in 2018 when Confact requested (and JLK refused to make) payment on termination of the agreement. JLK argued that the dispute should have been referred to adjudication in 2018 and that as it was not, an adjudicator had not been appointed within the 5 days stipulated in the Adjudication Rules, and arbitration was the only competent option left available to Confact. The court rejected this argument on the following grounds: It flies in the face of the stipulation in Clause 40 of the agreement that a disagreement is deemed to be a dispute only once a notice to resolve disagreement has been given, and such disagreement hasn’t been resolved within 10 working days thereof. It would also mean that every time a subcontractor made application for payment, the date of this application would determine the date of a dispute even as the subcontractor remained unaware whether or not the contractor intended to make payment. The court concluded that it is absurd to contend that an application for payment would have the same effect as a notice. Clause 40 also clearly provides for an election between adjudication and arbitration and on a plain and straightforward reading of this provision, JLK’s contention was misplaced. Adjudication is a specific process which caters for specific time frames, the aim and purpose for which is quick and immediate resolution whilst the agreement still endures. If the agreement is terminated then the parties should use arbitration and they will effectively be barred from adjudication. In support of this argument JLK relied upon obiter in the matter of Radon Projects (Pty) Ltd v NV Properties (Pty) Ltd and Another. As the court rightly
  • 12. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 12 | P a g e pointed out, however, the underlying agreement in Radon was different to the agreement between Confact and JLK. In Radon, the agreement specifically stipulated that prior to practical completion disputes were to be referred to adjudication and after practical completion disputes were to be referred to arbitration. This didn’t have any application to the agreement between Confact and JLK because their agreement did not include such a provision. JLK also argued against the implementation of the award on the grounds that it still had the right to refer the dispute to arbitration and had, in fact, done so. The court rejected this argument on the grounds that there are numerous authorities that support the proposition that a party to a construction contract is obliged to give effect to the terms of an adjudication award, including payment, until it is set aside (See Esor Africa (Pty) Ltd/Franki Africa (Pty) Ltd joint Venture v Bombela Civils Joint Venture, Case 2012/7442, para13; Tubular Holding (Pty) Ltd v DBT Technologies (Pty) Ltd 2014 (1) SA 244 (GSJ) para 40; Basil Read (Pty) Ltd v Regent Devco (Pty) Ltd [2011] JOL 27946 (GSJ)). Regardless of whether JLK exercises its contractual right to refer the dispute to arbitration, it is bound by the adjudicator’s decision and must give effect to it without delay, unless and until the adjudicator’s decision is set aside by an arbitrator. In its counter application JLK argued that the implementation of the adjudicator’s award should be suspended pending the outcome of the arbitration process because the adjudication process was unnecessary, JLK did not have an opportunity to challenge Confact’s claim, and JLK had been indicating since June 2020 that it intended to refer the adjudication award to arbitration. For these reasons JLK alleged that it would suffer substantial prejudice if the suspension was not granted and that it was in the interests of justice to suspend the implementation of the adjudicator’s award. The court found that it was Confact who would suffer real and substantial prejudice should the adjudicator’s award not be implemented. The court has a discretion to grant a suspension of an order where real and substantial injustice will otherwise be done, but JLK had wilfully refused to pay Confact for some 18 months, refused to agree on an adjudicator and refused to participate in the adjudication process. It was not, therefore, open for it to complain that it had not been afforded the opportunity to challenge Confact’s claim. The court also pointed out that despite JLK’s assertion that it required the dispute to be ventilated by arbitration, there was no evidence before the court that JLK had referred the matter to an arbitrator. JLK had, therefore, dismally failed to reach the threshold of exceptional circumstances required to satisfy the granting of a suspension order.
  • 13. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 13 | P a g e AMALGAMATED CONSTRUCTION CONTRACTS - GRASP THE NETTLE AND ENFORCE (OR NOT)? Pursuant to the Housing Grants, Construction and Regeneration Act 1996 (as amended) a party to a construction contract is permitted to refer a dispute arising under the contract to adjudication.i It is noteworthy that ‘dispute’ is referred to in the singular. Consequently, should a dispute between parties be spread over more than one contract it is likely that more than one dispute exists, thus, leaving an adjudicator devoid of jurisdiction. On occasion parties may have entered more than one construction contract with each other on the same project but administer and treat those contracts as one. For example, a contractor may enter a contract with a sub-contractor for a particular works package and later enter a contract with that same sub-contractor for another works package but administer payments for both of those contracts in an amalgamated way. Similarly, a local authority may enter a framework agreement with a contractor and place separate Orders thereunder but amalgamate payments for those Orders. Should a party refer a dispute to adjudication under such arrangements jurisdictional challenges may arise on the grounds that there is more than one dispute as the issues relate to more than one contract. Such an issue arose in the recent case of Delta Fabrications & Glazing Ltd v Watkin Jones & Sons Ltd.ii The claimant had entered two sub- contracts with the defendant for the provision of work packages and contended that the parties had subsequently agreed by their conduct to vary the contracts so that they were amalgamated into one, particularly, as payments for both contracts were dealt with in one application. A dispute arose between that parties, which the claimant successfully referred to adjudication. The adjudicator concluded that there was one amalgamated contract. The claimant applied for summary judgment to enforce the adjudicator’s award. The defendant resisted on the grounds that the adjudicator did not have jurisdiction because the claimant referred a dispute under two separate contracts in the same adjudication. The defendant contended that there was an extensive course of dealings between the parties relating to various projects and the parties had entered separate sub-contracts for works packages on those projects. The parties had adopted a practice of having one payment notice for all the claimant’s sub-contracts under each project without amalgamating the sub-contracts into one. Watson J considered that if the court were to find that the two contracts were varied and amalgamated by conduct, the court must be satisfied that the parties’ conduct was ‘unequivocal and consistent’ so that a single
  • 14. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 14 | P a g e contract came into existence. If that were the case, the defence had no real prospect of success and the court should, as Watson J put it, ‘grasp the nettle’ by giving summary judgment. In considering whether a defence has a real prospect of success, consideration must be given to the background of the policy underlying adjudication enforcement, which is that of maintaining cashflow and of maintaining the principle of pay now and argue later.iii In dismissing the application for summary judgment, Watson J held that the documents relied on by the claimant as constituting the agreement to vary the contracts were not unequivocal. Indeed, far from satisfying this requirement the conduct of the parties, both before and after the alleged agreement to amalgamate, indicated that the parties did not intend that the contracts would be amalgamated or that only one contract existed. A factual analysis supporting this conclusion showed that: Although the defendant’s payment notice contained an amalgamated figure for payment due under both contracts, the supporting documents dealt with both contracts separately. It did not follow that including the total of the sums due under both contracts in one payment notice amounts to an offer to amalgamate the contracts so that they cease to exist as separate contracts and become one contract; Similarly, although the claimant’s payment application contained a single combined figure for both contracts, the supporting documents consisted of separately prepared, detailed calculations of the sums due under the two contracts; Variations agreed between the parties were readily identifiable as relating to distinctive contracts; The correspondence between the parties was inconsistent referring to ‘contract’ in the singular and ‘contracts’ in the plural; and Rather than referencing the alleged variation to amalgamate the contracts by conduct, the Referral Notice contended that the separation of the contracts ended upon the commencement of the works. This was inconsistent with the claimant’s stance at enforcement. In conclusion Watson J held that: 42 … the Defendant has not only a real, but a strong, prospect of successfully defending the claim on the ground that the adjudicator lacked jurisdiction, because the Claimant referred disputes under two separate contracts to the adjudicator in one referral.’
  • 15. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 15 | P a g e Although, not referred to in Delta Fabrications it is interesting to consider the judgment of Amec Group Ltd v Thames Water Utilities Ltd.iv In Amec Group a similar jurisdictional challenged was raised, namely, that Orders placed under a framework agreement constituted separate contracts. Consequently, the payment dispute dealt with by the adjudicator related to more than one dispute as the differences between the parties arose across multiple contracts. On the wording of the contract Coulson J held that the dispute arose under the framework agreement and not the Orders placed thereunder, thus, the adjudicator had jurisdiction to deal with the dispute. However, Coulson J noted that had the dispute(s) arose under a series of Orders, the multiple dispute point ‘would probably have been successful’v meaning that the validity of any aggregated applications for payment could not be dealt with in a single adjudication. Consequently, such dispute(s) would lead to: ’… hundreds of separate adjudications, each for a trifling sum, each arising under an individual works contract. It seems … that was not what the parties agreed … and it would not give rise to a solution that could be described as commercially sensible.’vi Delta Fabrications and Amec Group highlights the commercial practicalities that parties should have in mind when considering adjudication provisions in the context of multiple contracts between the parties on the same project. Without proper consideration disputes between the parties may be prevented from any sort of meaningful adjudication as aggregate claims arising across multiple contracts would have to be dissected and separated into potentially trifling sums. This may not be commercially viable. If not properly considered at the outset subsequent arguments about the amalgamation of contracts by way of conduct, as advanced in Delta Fabrications, may be difficult to support. Showing that conduct was ‘unequivocal and consistent’ with the amalgamation of the contracts is an onerous proposition to put forward. Paul Hughes phughes@sharpepritchard.co.uk 1 s108(1). [2021] EWHC 1034 (TCC). Ex Novo Ltd v MPS Housing Ltd [2020] EWHC 3804 (TCC), para 4. [2010] EWHC 419 (TCC). Amec Group Ltd v Thames Water Utilities Ltd [2010] EWHC 419 (TCC), para 37. Amec Group Ltd v Thames Water Utilities Ltd [2010] EWHC 419 (TCC), para 33.
  • 16. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 16 | P a g e SINGAPORE: HIGH COURT CLARIFIES DIFFERENT DEFINITIONS OF "DAY" UNDER THE SOP ACT AND CONSTRUCTION CONTRACTS In brief Under the Building and Construction Industry Security of Payment Act (Cap 30B) ("SOP Act"), the definition of “day” under Section 2 excludes “a public holiday within the meaning of the Holidays Act (Cap. 126).” In Tay Choon Huat, deceased v Soon Kiat Construction & Maintenance Pte Ltd [2021] 3 SLR 1005 (“Tay Choon Huat”), the Singapore High Court (SGHC) considered whether this statutory definition of "day" would apply to the Articles and Conditions of Building Contract of the Singapore Institute of Architects (Lump Sum Contract, 9th Ed) (“SIA Conditions”). After reviewing existing authorities, the SGHC held that parties may contractually agree on a more stringent deadline for the provision of a payment response under the SOP Act. Where the SIA Conditions is applicable, the more inclusive definition of "day," which includes public holidays, will apply notwithstanding the statutory definition provided for under the SOP Act. The case is a reminder to parties entering into construction contracts to expressly define terms used in their contract, particularly as they may relate to the calculation of time in relation to the statutory adjudication process under the SOP Act. Summary The employer, Tay Choon Huat (“TCH”), entered into a construction contract (“Contract”) with the contractor, Soon Kiat Construction & Maintenance Pte Ltd (“SK”), which incorporated the SIA Conditions. Under Clause 31(15)(a) of the SIA Conditions, TCH was to respond to an interim payment claim by SK by providing a payment response "within 21 days" after the interim payment claim had been served on the employer. In this case, the payment claim was served on TCH on 20 April 2020. TCH in turn provided its payment response on 15 May 2020. The Adjudication Application (AA) was lodged on 28 May 2020. During this period, there were multiple public holidays and the parties were in dispute as to whether the word "day" in Clause 31(15)(a) of the SIA Conditions included or excluded public holidays. It was not in dispute between TCH and SK that the public holidays on 24 May and 25 May 2020 were to be excluded from the seven‑day period for the lodgement of the AA. However, the parties
  • 17. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 17 | P a g e were in disagreement as to whether the two public holidays on 1 May and 7 May 2020 ought to be excluded from the 21‑day period under the SIA Conditions for TCH to file its payment response: On TCH's case, as the word "day" includes public holidays, the payment response was due on 11 May 2020 (i.e., 21 calendar days from the service of the payment claim on 20 April 2020) and the AA had to be lodged by 27 May 2020. In contrast, SK argued that as the word "day" did not include public holidays, the payment response was only due on 13 May 2020 (i.e., 23 calendar days from the service of the payment claim on 20 April 2020) and the AA was to be lodged by 29 May 2020. The SGHC held that the word "day" included public holidays on two grounds: First, the SIA Conditions did not expressly adopt the definition of "day" as provided for in the SOP Act. In contrast, the drafters of the SIA Conditions incorporated the definitions of "payment claim" and "payment response" from the SOP Act. Second, the court considered the use of the word "day" in other parts of the Contract, which supported the interpretation of "day" as including public holidays. For example, the liquidated damages clause expressly provided that the Contract period would include Sundays, public holidays and rest days. Key takeaways This case confirms that the definition of “day” under the SOP Act is not applicable to the SIA Conditions. The SGHC also confirmed that parties may contractually agree on a more stringent deadline for the provision of a payment response under the SOP Act. The SGHC also cautioned that "[u]ltimately, the particular contract in each case stands to be construed" and whether statutory definitions are incorporated would depend on how the contract is to be construed. Parties should therefore be careful when drafting their construction contracts to ensure that they expressly specify definitions for periods of time and whether such periods are inclusive or exclusive of public holidays. Given how seriously the statutory timelines under the SOP Act are typically adhered to, parties should pay particular attention to the definitions of time periods and the calculation of timelines in their contracts. Where there may be ambiguity as to these matters, parties should err on the side of caution and seek advice to avoid falling foul of the SOP Act. Baker McKenzie - Nandakumar Ponniya, Wong Tjen Wee, Daniel Ho and Daryl Yang
  • 18. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 18 | P a g e ONE YEAR IN REVIEW: A FIRST- HAND LOOK AT AN ADJUDICATION UNDER THE ONTARIO CONSTRUCTION ACT Introduction In June 2020, Glaholt Bowles LLP completed one of the first adjudications under the new Construction Act, R.S.O. 1990, c. C.30 (the “Act”). The adjudication provisions under Part II.1 of the Act came into force on October 1, 2019 and were developed to ensure continuity of work on jobsites and cash flow through the construction pyramid. Adjudication is available where both the procurement process (if any) is started, and the contract is executed, after October 1, 2019. It is unavailable in situations where the con- tract may have been executed after October 1, 2019 but the procurement process was commenced prior to that date. In other words, both the procurement process (if any) must have commenced and the contract must be formalized after October 1, 2019 for adjudication to be an option. This article discusses a first-hand experience of legal advocacy in an adjudication and provides insight into whether this new form of dispute resolution serves to meet the legislative goal of efficient resolution of contract disputes on construction sites. The Decision to Adjudicate The decision to pursue adjudication on behalf of a subcontractor client (the “Claimant”) was based on several factors including availability of adjudication, the nature of the dispute and client cost considerations. Our firm saw an opportunity to explore a quick form of resolution which had the potential to meet the needs of our client. The claim centered on a residential project dispute between two private individuals and involved no procurement process. Section 87.3 (4) of the Act, the transition provision, makes it clear that in determining the availability of adjudication, the contract governs. Here, the contract between the contractor and owner of the residence had been formalized after October 1, 2019. The subcontractor’s agreement was also formalized after October 1, 2019. It is important to note that had the contract been effective prior to October 1, 2019, it would not have mattered that the Claimant, as subcontractor, entered into the
  • 19. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 19 | P a g e agreement after that date. Adjudication would not have been available in those circumstances. We grappled with a few anomalies in deciding whether to pursue adjudication. First, there was no written agreement but only an oral agreement along with payment records and various communications (emails, texts) related to the subcontract. Second, section 13.5(3) of the Act explicitly states that adjudication is not available when a contract or subcontract is complete, unless the parties agree otherwise. In our case, if section 13.5(3) had been raised, we were prepared to take the position that the “completion” of a contact was not the same as an effective termination of the contract (as in our case) and therefore the adjudication period had not expired for the Claimant. To reiterate, adjudication is meant to be a “real time” resolution vehicle for active projects which is why it is unavailable in contracts that are completed. The types of disputes that may be referred for adjudication are listed under section 13.5(1) of the Act. We determined, based on the facts, that the Claimant’s dispute fell into the cat- egory of “payment under the contract”. We continued our analysis of whether to pursue adjudication by taking stock of the scope of the claim. The claim was relatively small (less than $100,000) and the issue fairly discrete and straightforward (non-payment). Section 13.5(4) of the Act explicitly states that unless the parties agree otherwise, ad- judication should only address a single matter. We were confident that the facts of the claim met this requirement. Finally, we were conscious of the Claimant’s costs and business needs. As the operator of a sole proprietorship, the Claimant’s priority was to recoup funds as quickly as possible. Adjudications can be completed in writing and written materials have strict page limits and submission deadlines. Importantly, a determination must be made by the adjudicator within 30 days (s.13.13(1)) unless an extension of time is approved with written consent of the parties (s.13.13(2)). An attractive feature of adjudication is the ability to avoid expansive hearings and protracted pleadings, which are typical of traditional lien actions. Following our review of the Claimant’s dispute, we decided adjudication was appropriate in the circumstances. We issued a Notice of Adjudication to opposing counsel as required under section 13.7(1) of the Act. Ontario Dispute Adjudication For Construction Contracts (ODACC) On July 18, 2019, the Province of Ontario announced the appointment of ADR Chambers
  • 20. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 20 | P a g e as the Authorized Nominating Authority under section 13.2(1) of the Act.[1] ADR Chambers, for the purposes of carrying out its mandate, operates under the title Ontario Dispute Adjudication for Construction Contracts (“ODACC”). ODACC oversees the appointment of adjudicators and each adjudication proceeding. ODACC’s website is a critical tool in the adjudication process. It acts as both a source of information and, if so desired, the administrative centerpoint of the proceeding via the online portal. In our case, we used the online portal and found it user-friendly. After registering an account, we were able to create a file online for the new claim. We completed and electronically submitted the online form for the Notice of Arbitration. Each party (or their counsel) must register for an ODACC account to use the online portal. The online portal can be used to send and receive all materials pertaining to the claim. The adjudicator and the parties can also use it for direct communication. All conversation histories are saved to the system. When a message is sent or received, it is viewed by all parties along with an ODACC administrative coordinator. Using the online portal is more efficient than email or hardcopy correspondence. The portal keeps the adjudication organized, with all information and required next steps clearly displayed on the user “dashboard”. The portal is truly a “one-stop shop” for carrying out an adjudication proceeding under the Act. Notifications are sent to the user’s email whenever materials are uploaded to the online portal or a new message is available. We experienced some technical glitches where notifications were significantly delayed, but ODACC quickly resolved that issue and has since made instant notification a reliable feature for users. It is not required that parties register and use the online portal as part of the adjudication. Given that adjudications will likely be in writing in most cases, the option remains to circulate documents and other correspondence via email, fax or mail. However, the online portal is recommended based on our experience. Even if a party does decide to use the online portal, the regulations under the Act still require that any documents (including the Notice of Adjudication) be “given” to the op- posing side under the rules of court (s.13.7(1)). In other words, despite using the online portal to submit all documents, we still formally served the materials on opposing counsel.[2] The Adjudication Process Notice of Adjudication
  • 21. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 21 | P a g e The Notice of Adjudication is an important document for the Claimant because it must concisely describe the dispute in 250 words or less. In addition, it must include: (1) the Claimant’s suggested adjudicator; and (2) the suggested procedure for conducting the adjudication. I. Selecting an Adjudicator In selecting a proposed adjudicator, we had two options. The first option was to review the ODACC registry of adjudicators and select from the extensive list of certified adjudicators. The registry provides background details of each adjudicator including their profession, years of experience, professional memberships, languages spoken and fee range. The second option is choosing a certified adjudicator based on recommendations from colleagues or other networks. In our case, our proposed adjudicator was based on a short list of recommendations from other practicing construction lawyers. It is not required that an individual be a licensed lawyer in Ontario to be certified as an adjudicator. Many are accountants, project managers, architects, quantity surveyors or engineers. Depending on the nature of the dispute, some parties may not want a lawyer as an adjudicator. Instead, the parties may decide that an adjudicator with training and depth of experience in a highly technical profession (e.g. structural engineering) is better suited to make a determination. Still, any adjudicator has the ability to request the participation of an independent “assistant” under section 13.12(5) of the Act. If the parties cannot agree to an adjudicator, one will be assigned by ODACC. II. Selecting an Adjudication Procedure ODACC’s website provides four (4) “pre- designed” options for conducting an adjudication. The first three options are strictly in writing, where the parties exchange written materials of varying lengths. The fourth option involves a 30-minute oral presentation by each party. If none of the four pre-designed procedures fit the needs of the parties, a fifth option is for the parties, with input from the adjudicator, to develop a customized process. A customized process may involve, for instance, a site visit or the appointment of an assistant. An assistant is an experienced professional such as an architect, engineer, or actuary who carries out the role of an expert in helping the adjudicator determine facts in question prior to reaching a determination. Each type of procedure has its own cost implications. Adjudicator fees can range from a flat fee of $800 all the way to hourly rates of $750 per hour depending on both the amount
  • 22. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 22 | P a g e of money in dispute and the complexity of the issue. In our case, the adjudicator’s fee was due 10 days after the adjudicator agreed to hear the matter. The Claimant and Respondent each pay 50% of the adjudicator’s fee and are expected to cover their own legal costs unless the adjudicator determines otherwise. In our case, we initially selected the pre- designed process #1, which allows for a maximum of 2 pages of written submissions from both parties. However, based on the adjudicator’s recommendation, all parties agreed to pre-designed process #2, which allows the Claimant a total of 5 pages of sub- missions and a one-page reply. The Respondent is also allowed a total of 5 pages. The adjudicator must approve the selected procedure for conducting the adjudication. It was helpful to have the adjudicator’s input in selecting the procedure because we had initially underestimated the length of written submissions we would need to effectively advocate our client’s position. A more difficult decision is determining whether written submissions will suffice or if your client would benefit from the comparatively more costly and time- consuming options of oral submissions or site visits. The need to ensure your client is positioned for the best possible outcome is paramount and that may mean that the truncated pre-design procedures are not suit- able given the substantive issue in dispute. Supporting Documents After we submitted our notice of adjudication and received confirmation of the adjudicator’s approval to hear the matter, we had five (5) days to submit our supporting documents. Akin to a statement of claim, our supporting documents consisted of a 4-page, written advocacy piece of the issue and why the Claimant was entitled to recovery. The Respondent was given 7 days to submit a 5- page response. The Claimant was then given 3 days to issue a 1-page reply. Attached documents such as contracts and invoices are not counted in the page limit. However, it is good practice to clarify what limits, if any, might be placed on the number of attachments allowed in the adjudication. In some cases, the need for additional documents (emails, text, etc.) may be necessary to establish key facts. Communication between parties and with the adjudicator is essential to setting the parameters of what is acceptable. Section 13.12(1) gives the adjudicator significant flexibility in overseeing the conduct of the adjudication. Determination
  • 23. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 23 | P a g e The adjudicator is required to render a determination within 30 days of receiving all documents (s. 13.13(1)). In our case, we received a determination in 13 days. We were satisfied with the quick turnaround but recognize that this may not occur in other cases. External factors that impact scheduling may arise or the complexity of the issues may require a longer period of analysis and review of materials by the adjudicator. ODACC uploaded the final determination with written reasons to the online portal. Seven (7) days later, a certified copy of the determination was also uploaded to the online portal. As soon as we received the certified copy of the determination, we filed it with the court per section 13.20 of the Act, thus making it enforceable as any other court order. In accordance with section 13.20(3), we contacted opposing counsel and provided notice that the determination had been filed with the court. Parallel Proceedings Notwithstanding the decision to pursue adjudication, an important practice tip is to ensure that any claim for lien is properly preserved and perfected under the Act. In our case, the Claimant pursued both the adjudication and a standard lien claim. During the adjudication period, we continued to serve pleadings and communicate with opposing counsel concerning the lien action. It is prudent to protect a client’s lien rights in the event the lien remains the only viable method of enforcement. The determination of an adjudicator is the equivalent of an interim order. Per Section 13.15, it is binding on the parties until a later determination by a court or arbitrator or until the parties enter into a written agreement re- specting the adjudicator’s decision. If the parties accept the determination and thereafter forgo the lien action, another key practice tip is to seek an order on a without costs basis when discontinuing the lien action. If this is not done, there remains an opportun- ity for the defendant to make a motion within 30 days of the discontinuance to seek such costs under Rule 23.05(1) of the Rules of Civil Procedure, R.R.O. 1990, Reg. 194. Secondly, parties should strongly consider executing a mutual “full and final” release to avoid the resurgence of future claims related to the matter already addressed in the adjudication. If a party disagrees with the adjudicator’s determination, the option remains for them to seek the court’s final disposition in the lien action. However, under section 13.15(2), the court or an arbitrator may consider the merits
  • 24. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 24 | P a g e of a matter decided by the adjudicator. In other words, seeking a final determination in a separate forum will not necessarily lead to a different result from the adjudication. A party that disagrees with the outcome of an adjudication has the option of seeking judicial review of the decision, with leave of the Divisional Court, as prescribed in section 13.18(1) of the Act. The lien action was discontinued in our case and judicial review was not sought by any of the parties. Still, anyone participating in an adjudication should be attuned to the reality of parallel proceedings, especially those involving lien actions and should be prepared to protect their client’s interests. Conclusion As one of the first completed adjudications in Ontario, our experience confirms what the legislators hoped would be the impact of adjudication. We found the process to be quick and relatively inexpensive as compared to a lien action or other legal proceeding which can seriously hamper the progress of a construction project. We were impressed by the thoroughness of the analysis and extensive written reasons of the adjudicator. There were no concerns that the adjudicator was engaging in what some have suggested may be a form of “quick and dirty” or “rough” justice. On the contrary, the adjudicator was actively involved in the process and provided direction to ensure the proceedings ran smoothly and all parties would have a fair opportunity to present their case. Administratively, the ease of use of ODACC’s online portal, along with the pre-designed forms of adjudication made participation seamless. In our case, the fast turnaround in receiving a determination removed any doubt that adjudication can be the “real time” dispute resolution tool that it is intended to be. If adjudication is going to have the long-term impact of maintaining continuity of work on construction projects and cashflow, then industry stakeholders and their counsel will need to utilize adjudicationwhere appropriate. An interesting study would be the short and long-term effects of these new provisions in the Act. However, such a study cannot take place until there is a sufficient number of adjudications. Adjudication has the potential to save costs and maintain the focus on bringing projects to completion. With these priorities in mind, we are hopeful that adjudication can serve the construction industry well in this expanded era of alternative dispute resolution. [1] https://adrchambers.com/wp-content/ uploads/2019/07/announcement.pdf
  • 25. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 25 | P a g e [2] Section 16.1(1), O. Reg. 306/18: Adjudications under Part II.1 of the Act. Patricia Joseph Associate T:(416) 368-8280 Direct Line: (647) 699-5431 PatriciaJoseph@glaholt.com FALLING INTO JURISDICTIONAL ERROR UNDER SECURITY OF PAYMENT LEGISLATION The process of adjudication under the security of payment legislation requires adjudicators to reconcile difficult requirements, namely, to determine often complex legal issues within a short time frame, and to observe the strict requirements of the legislation. If the right balance isn't struck, adjudicators may fall into jurisdictional error. This is what occurred in the recent case of Total Lifestyle Windows Pty Ltd v Aniko Constructions Pty Ltd & Anor [2021] QSC 92. Total made a payment claim against Aniko under a construction contract and Aniko denied liability in its payment schedule. Total proceeded to make an adjudication application under the Building Industry Fairness (Security of Payment) Act 2017 (Qld) and the adjudicator found in favour of Aniko. In issue in this case was whether the determination was invalidated by jurisdictional error because the adjudicator: considered reasons included in Aniko's adjudication response that had not been included in its payment schedule; and failed to consider a relevant document that had been submitted by Total. The Court agreed that the adjudicator erred in each instance, and declared the resultant determination void. In reaching this conclusion, the Court considered the operation of certain provisions of the Act, relevantly: section 88 – in deciding an application, an adjudicator may only consider matters prescribed in subsection (2), which includes the provisions of the construction contract in issue, the payment claim and the payment schedule and, in respect of each, "all submissions, including relevant documents, that have been properly made" in support of the claim or schedule respectively; section 88(3) – an adjudicator must not consider "a reason" included in an adjudication
  • 26. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 26 | P a g e response to an adjudication application where section 82 prohibits the inclusion of the reason; and section 82 – an adjudication response "must not include any reasons (new reasons) for withholding payment that were not included in the payment schedule". The Court considered, and rejected, various arguments advanced by Aniko regarding the provisions of the Act dealing with "new reasons". With respect to one of Total's claims, Aniko's adjudication response relied on – and the adjudicator applied – a clause of the contract (clause 18) that was not raised in Aniko's payment schedule. Aniko contended that: reference to clause 18 was not made in the payment schedule because the clause had not been referred to in Total's payment claim. The Court noted in response that "s 69(c) of the Act requires a respondent to include all of its reasons for withholding payment in its payment schedule and not just those that are specifically raised or prompted by the payment claim"; section 82(3)(c) of the Act (which states an adjudication response may include "submissions relevant to the response") allowed it to raise the operation of clause 18. The Court disagreed, stating that this provision "must be read subject to section 82(4) which provides that an adjudication response must not include any reasons for withholding payment that were not included in the payment schedule"; and the operation of clause 18 was within the adjudicator's jurisdiction because section 88(2)(b) permits consideration of the relevant construction contract. Dispensing with that argument, the Court held that section 88 "must be read as a whole", and that while an "adjudicator might consider the provisions of the construction contract, the adjudicator may not consider a reason associated with a particular provision if it is a reason which falls within section 88(3)." The Court also noted that the prohibition imposed by section 88(3)(b) "is a very wide restriction", that it is immaterial whether a proscribed reason forms part of an adjudicator's decision. Rather, once such a reason is considered by an adjudicator, "then section 88(3)(b) has been breached, whether or not the consideration leads to a particular decision." On the matter of the adjudicator's failure to consider a relevant document submitted by Total, Aniko pointed to the fact the adjudicator, in his determination, stated "he had had regard to 'the payment claim to which the Application relates, together with all submissions, including relevant documentation'”. While conceding that
  • 27. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 27 | P a g e adjudicators are subject to "extraordinary pressure" when dealing with applications, and that "[i]nfelicity of expression is not a ground for finding that there has been an omission to comply with the Act", nevertheless, the Court held that the document in issue was of such import to Total's case, squarely contradicting the case advanced by Aniko (that was accepted by the adjudicator), that reference to it should have been made: "Merely saying that one has had regard to all relevant documentation is not conclusive on that issue. The omission to refer to a document of considerable importance … allows the inference to be drawn that regard was not had to it." The case not only demonstrates the strictness with which requirements of the Act relating to adjudication applications are applied, but also the importance of considering, and including in payment schedules, all of the arguments on which a respondent may wish to rely. CIPAA: ADJUDICATORS' POWERS TO ORDER REMEDIES AND INTEREST WHEN PAYMENT CLAUSE IS UNENFORCEABLE Introduction Section 25 of the Construction Industry Payment and Adjudication Act (CIPAA) 2012 lists adjudicators' extensive powers in adjudication proceedings, including the power to award financing costs and interest. The recent high court decision in First Commerce Sdn Bhd v Titan Vista Sdn Bhd and another case(1) examined the extent of an adjudicator's powers to determine remedies and interest in unique circumstances where a payment clause was void and the default statutory implied payment provision in the CIPAA was pleaded. Facts First Commerce Sdn Bhd was appointed as the main contractor by the employer of a project to build and complete the super structure of the project. Upon being notified by the employer, the architect directed First Commerce to appoint Titan Vista Sdn Bhd as its nominated subcontractor to perform part of the project. Accordingly, First Commerce issued a letter of award to Titan Vista for such work. The letter stated that the terms and
  • 28. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 28 | P a g e conditions of the Malaysian Institute of Architects (PAM) Nominated Subcontract 2006 were incorporated into the contract between the parties. Further, Clause 9 of the letter of award provided that the payment for the certified amounts had to be paid in the form of cheques from the employer within 45 days from the date of the architect's certificates. In the course of executing the contracted work, Titan Vista commenced an adjudication against First Commerce pursuant to the CIPAA to recover payment for four unpaid interim certificates. Specifically, Titan Vista claimed an outstanding sum of approximately RM2.37 million and late payment interest. Titan Vista's adjudication reply also stated that its claims were based on Clause 9 of the letter of award and pleaded that the default payment provisions in Section 36 of the CIPAA would apply if Clause 9 of the letter of award was found to be a conditional payment prohibited by Section 35 of the CIPAA. After hearing both parties, the adjudicator decided in favour of Titan Vista. The adjudicator found that Clause 9 of the letter of award was unenforceable as it was a conditional payment provision prohibited by Section 35 of the CIPAA. The adjudicator referred to the "Period of Honouring Certificates" found in Clause 30 of the Appendix to the PAM Nominated Subcontract 2006, instead of Section 36 of the CIPAA as had been pleaded; he ordered First Commerce to pay the amounts certified and claimed by Titan Vista within 21 days from the date of each interim certificate. Dissatisfied with the adjudication decision, First Commerce relied on Sections 15(1)(b), 15(1)(c) and 15(1)(d) of the CIPAA to set aside the adjudication decision at the high court. Titan Vista, on the other hand, filed an originating summons pursuant to Section 28 of the CIPAA at the high court to enforce the adjudication decision as a judgment when First Commerce failed to pay in accordance with the adjudication decision. Both applications were heard on the same day before the same court. Issue At the high court, First Commerce's main contention was that the adjudicator had erred in ordering it to pay the amounts certified and claimed by Titan Vista based on the due dates which he had set (ie, within 21 days of the date of the interim certificates) as opposed to the due dates pleaded by Titan Vista (ie, within 45 days of the date of the interim certificates pursuant to Clause 9 of the letter of award). This, in turn, had resulted in excessive interest being awarded to Titan Vista.
  • 29. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 29 | P a g e Decision Justice Lim Chong Fong found that Titan Vista had not specifically confined its claims to Clause 9 of the letter of award as it had requested payment of the interim certificates to be based on either: Clause 9 of the letter of award; or Section 36 of the CIPAA if Clause 9 of the letter of award was void in contravention of Section 35 of the CIPAA. Hence, the adjudicator had acted within his jurisdiction based on the disputes referred to him. The judge also held that adjudicators are not bound by the disputes referred to them in the exact way as pleaded by the parties, especially with regard to the remedies sought. In the present case, the judge ruled that the adjudicator, having decided that Clause 9 of the letter of award was void and unenforceable, need not decide on the issue of interest based on Section 36 of the CIPAA as pleaded by Titan Vista because Section 25(o) of the CIPAA authorises adjudicators to decide on issues of interest, including the date of accrual, as they see fit. It was therefore justified for the adjudicator to adopt the express provision found in PAM Nominated Subcontract 2006 which binds both parties in lieu of Section 36 of the CIPAA. Comment The high court decision is a welcome judgment for the construction industry, especially unpaid parties as they are not strictly bound by their pleaded case, particularly with regard to the remedies sought. However, this decision should not be used as a general principle for unpaid parties to broaden their claim against non-paying parties, bearing in mind the application of Section 27(1) of the CIPAA. An appeal against this decision is pending before the Court of Appeal. Endnotes (1) [2021] MLJU 376. Gan Partnership - Min Lee Tan, Yuen Wah Foo
  • 30. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 30 | P a g e UK ADJUDICATORS EDINBURGH ADJUDICATION & ARBITRATION CONFERENCE – 5 MARCH 2021 The UKA 2021 Edinburgh Adjudication & Arbitration Conference took place online on the 5 March 2021 and had over 900 registrations for the free conference. Many thanks to all of the speakers and supporting organisations. The conference video can be viewed at: https://www.ukadjudicators.co.uk/resources TCC COURT JUDGEMENTS April • Beattie Passive Norse Ltd & Anor v Canham Consulting Ltd [2021] EWHC 1116 (TCC) (30 April 2021) • Boxwood Leisure Ltd v Gleeson Construction Services Ltd & Anor [2021] EWHC 947 (TCC) (19 April 2021) • Celtic Bioenergy Ltd v Knowles Ltd [2021] EWHC 1352 (TCC) (19 April 2021) • Dana UK Axle Ltd v Freudenberg FST GmbH [2021] EWHC 1027 (TCC) (23 April 2021) • Delta Fabrication & Glazing Ltd v Watkin Jones & Son Ltd [2021] EWHC 1034 (TCC) (30 April 2021) • Good Law Project Ltd & Anor v Secretary of State for Health and Social Care [2021] EWHC 1223 (TCC) (22 April 2021) • Good Law Project Ltd v Minister for the Cabinet Office [2012] EWHC 1083 (TCC) (16 April 2021) • Good Law Project Ltd v Secretary of State for Health And Social Care [2021] EWHC 1237 (TCC) (29 April 2021)
  • 31. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 31 | P a g e • Kang & Anor v Pattar [2021] EWHC 1101 (TCC) (28 April 2021) • Prater Ltd v John Sisk & Son (Holdings) Ltd [2021] EWHC 1113 (TCC) (30 April 2021) May • Beattie Passive Norse Ltd & Anor v Canham Consulting Ltd (No. 2 Costs) [2021] EWHC 1414 (TCC) (28 May 2021) • Dana UK AXLE Ltd v Freudenberg FST GmbH [2021] EWHC 1413 (TCC) (26 May 2021) • Davies & Davies Associates Ltd v Steve Ward Services (UK) Ltd [2021] EWHC 1337 (TCC) (19 May 2021) DRBF’S 20TH ANNUAL INTERNATIONAL CONFERENCE AND WORKSHOP 30 JUNE - 2 JULY 2021 LISBON, PORTUGAL https://www.drb.org/2021-06-lisbon-home- page
  • 32. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 32 | P a g e FORTHCOMING EVENTS Tuesday, June 8, 2021 - 6:30 PM Causation in English Construction Law: time for a re-statement? Online Chair: Professor Anthony Lavers Speaker(s): David Sawtell, 39 Essex Chambers For more info Tuesday, June 15, 2021 - 9:00 AM An Introduction to Delay Claims: Part 2 Chair: Rebecca Shorter (Partner, White & Case) Speaker(s): Valia Dousiou (Blackrock) For more info Thursday, June 24, 2021 - 5:00 PM Making best use of the RIAI suite of contracts Online Moderator: Paul Darling QC Speaker(s): Arran Dowling-Hussey, James O'Donoghue, Chartered Architect, Bluett & O'Donoghue, Dublin & Kilkenny & Niall Meagher, Interactive Project Managers (Dublin) Venue: Online For more info Tuesday, June 29, 2021 - 9:00 AM An Introduction to Quantum: Part 1 Speaker(s): Patrick Clarke (Atkin Chambers) For more info Monday, July 5, 2021 - 9:00 AM BIM in 2021: a look at current and future trends Online Moderator: Rory Kirrane SC, Mason Hayes & Curran LLP Speaker(s): May Winfield, Buro Happold; Ralph Montague, Arcdox & David-John Gibbs, Gammon Construction Venue: Online For more info
  • 33. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 33 | P a g e Tuesday, July 6, 2021 - 6:30 PM Factual witness evidence: who needs it? (NLC) London Chair: Rowan Planterose, SCA President Speaker(s): Roger Ter Haar QC and Kim Franklin QC, Crown Office Chambers Venue: National Liberal Club, 1 Whitehall Pl, Westminster, London SW1A 2HE For more info Tuesday, July 6, 2021 - 6:30 PM Factual witness evidence: who needs it? (Online) Online Chair: Rowan Planterose, SCA President Speaker(s): Roger Ter Haar QC and Kim Franklin QC, Crown Office Chambers Venue: Online For more info Tuesday, July 13, 2021 - 9:00 AM An Introduction to Quantum: Part 2 Speaker(s): James Morris (Partner, Mayer Brown) & Sue Kim (Director, HKA) For more info Wednesday, July 28, 2021 - 6:00 PM EU litigation after Brexit Chair: Alison Garrett, Mills & Reeve LLP Speaker(s): Jennifer Jones of Atkin Chambers, Mathias Cheung and Caroline Greenfield For more info Thursday, August 5, 2021 - 5:00 PM SCL Networking Evening London Venue: The Yacht London, Upper Deck, Temple Pier, Victoria Embankment, London WC2R 2PN Full details in this flyer For more info Tuesday, September 7, 2021 - 9:00 AM An Introduction to Disruption Claims Speaker(s): David Coyne (Associate Director, Blackrock) & Tom Andrews (Senior Associate, Osborne Clarke) For more info
  • 34. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 34 | P a g e SCL INTERNATIONAL CONFERENCE 2021 The Society of Construction Law 9th International Conference has been postponed till November 2021. The Right Honourable Lord Justice Coulson will be a keynote speaker at the Conference. http://www.constructionlaw2021.com/scl21
  • 35. WWW.UKADJUDICATORS.CO.UK JUNE 2021 NEWSLETTER 35 | P a g e SCL INTERNATIONAL CONFERENCE 2021 The Society of Construction Law 9th International Conference has been postponed till November 2021.e Right Honourable Lord Justice Coulson will be a keynote speaker at the Conference. http://www.constructionlaw2021.com/scl21