What is formwork?
• Formwork is a mould including all supporting structures, used
to shape and support the concrete until it attains sufficient
strength to carry its own weight.
• It should be capable of carrying all imposed dead and live
loads apart from its own weight.
Requirements good formwork
1. It should be strong enough to withstand all types of dead and live loads.
2. It should be rigidly constructed and efficiently propped and braced both
horizontally and vertically, so as to retain its shape.
3. The joints in the formwork should be tight against leakage of cement grout.
4. Construction of formwork should permit removal of various parts in desired
sequences without damage to the concrete.
5. The material of the formwork should be cheap, easily available and should
be suitable for reuse.
6. The formwork should be set accurately to the desired line and levels should
have plane surface.
7. It should be as light as possible.
8. The material of the formwork should not warp or get distorted when
exposed to the elements.
9. It should rest on firm base.
Economy in formwork
• The cost of formwork may range between 30 to 40% of the cost of
concrete work.
• Special structure like bridge ,tall chimneys, dams etc; the cost of formwork
may range between 50 to 100%.
• The building should be planned in such a way that there are minimum
number of various in the size rooms, floor area etc. so as to permit reuse
of the formwork moulds repeatedly.
• Formwork shall be made of low cost materials, energy and labor if
possible.
• Formwork care and maintenance should be done according to
specifications.
Types of formwork
• Timber formwork
• Steel formwork
• Plywood formwork
• Aluminum formwork
• Plastics formwork
Timber formwork
• It should be well seasoned.
• It should be light weight.
• It should be easily workable
with nail without splitting.
• It should be free from knots.
Advantage of timber formwork
• Easy handling because it is light weight.
• Easy to disassemble.
• Damaged parts can be replaced with new one.
• Very flexible.
• Easy to produce.
• Easily available.
Disadvantage of timber formwork
• Limited size of shape.
• Excessive loss of heat.
• A very smooth surface will be produced which would give
problems for finishing process.
• Limited fixing.
STEEL FORMWORK
• This consists of panels fabricated out of the thin steel plates
stiffened along the edges by small steel angles.
• The panel units can be held together through the use of
suitable clamps or bolts and nuts.
• The panels can be fabricated in large number in any desired
modular shape or size.
• Steel forms are largely used in large projects or in situation
where large number reuses of the shuttering is possible.
• This type of shuttering is considered most suitable for circular
or curved structures.
Advantages of steel formwork
• It can be used for a no. of times.
• It is non absorbent.
• Smooth finish surface obtained.
• No shrinkage of formwork occurs.
• Easy to use.
• Its volume is less.
• Its strength is more.
Disadvantage of steel formwork
• Limited size or shape.
• Excessive loss of heat.
• A very smooth surface will be produced which would give
problems for finishing process.
• Limited fixing.
Aluminum formwork
• Manufactured using light weight aluminum.
• Made up of aluminum metal frame that provides very sturdy
and durable mold for pouring concrete.
Advantages of aluminum formwork
• Quickly and accurately assembled.
• Reduces the labor cost owing to its easy installation.
• Light weight component provides low pressure on the lower part of the
buildings.
• Aluminum metal surface offers easy cleaning after concrete is removed.
• Faster construction cycles.
• Easy to handle.
• High quality finishes.
• Can be easily recycled.
• Can be repeatedly used without losing quality
• Safe work platforms.
Disadvantages of aluminum formwork
• Initial high investment.
• Compares very poorly on modifications, against brick work
constructions.
• Fear of theft of valuable Aluminum Extrusions & sheets &
hence kit not being complete at critical stages of construction.
• Mass Housing projects are not as high for investing in large
number of Aluminum Formwork.
Plywood formwork
• The plywood is built up of odd number of layers with grain of
adjacent layers perpendicular to each other.
• Plywood is used extensively for formwork for concrete,
especially for sheathing, decking and form linings.
• There are two types of plywood – internal and exterior.
• The interior type is bonded with water resistant glue and
exterior type is bonded with water proof glue.
Plywood formwork
Advantages of plywood formwork
• Easily cut to shape on site.
• Reusable.
• Thinner plywood is used to facilitate bending.
• Thicker plywood is used when the weight of concrete caused
a standard thickness plywood to blow out, it might distorting
the concrete face.
Disadvantages of plywood formwork
• The layering effect in plywood makes it porous and
susceptible to water damage if exposed over time.
• Plywood becomes heavy when wet and should be covered if
left outside to reduce the risk of water damage.
PLASTIC FORMWORK
• Lightweight
• Reusable
• Chemical resistant
• Fungus and termites resistant
• Can be easily cut and nail by
using wood working tools
• Non degradable
Construction of formwork
• Propping and centering.
• Shuttering.
• Provision of camber.
• Cleaning and surface treatment.
Order and method of removing
formwork
• Shuttering forming the vertical faces of walls, beams and
column sides should be removed first as they bear no
load but only retain the concrete.
• Shuttering forming soffit of slabs should be removed
next.
• Shuttering forming soffit of beams, girders or other
heavily loaded shuttering should be removed in the end.
RCC column formwork
Stair formwork
Causes of formwork failure
• Improper stripping and shore
removal
• Inadequate bracing
• Vibration
• Unstable soil under mudsills,
shoring not plumb
• Inadequate control of
concrete placement
• Lack of attention to
formwork details
Safety precaution
• Material used for the construction of formwork must
fulfill the specification.
• Formwork is fixed firmly & properly
• Construction area must be protected to prevent
vandalism of formwork.
Period for removal of formwork
S.No Description of structural member Period of time
1 Walls Columns and vertical sides of beam 1 to 2 days
2 Slab 3 days
3 Beam soffits 7 days
4 Removal of props to slabs:
(a)For slabs spanning up to 4.5 m
(b) For slabs spanning over 4.5 m
7 days
14 days
5 Removal of props to beams and arches
(a)Spanning up to 6 m
(b)Spanning over 6 m
14 days
21 days
THE END

Contenu connexe

Tendances (20)

Masonry construction (Building Construction)
Masonry construction (Building Construction)Masonry construction (Building Construction)
Masonry construction (Building Construction)
 
Form-work in construction
Form-work in construction Form-work in construction
Form-work in construction
 
Temporary works
Temporary worksTemporary works
Temporary works
 
Details of roofs and floors
Details of roofs and floorsDetails of roofs and floors
Details of roofs and floors
 
REPAIRS AND REHABILITATION OF STRUCTURES
REPAIRS AND REHABILITATION OF STRUCTURESREPAIRS AND REHABILITATION OF STRUCTURES
REPAIRS AND REHABILITATION OF STRUCTURES
 
Flooring
FlooringFlooring
Flooring
 
Shoring
ShoringShoring
Shoring
 
One way slab and two way slab- Difference between
One way slab and two way slab- Difference betweenOne way slab and two way slab- Difference between
One way slab and two way slab- Difference between
 
FormWork
FormWork FormWork
FormWork
 
BRICK MASONRY
BRICK MASONRYBRICK MASONRY
BRICK MASONRY
 
Waterproofing and insulaton
Waterproofing and insulatonWaterproofing and insulaton
Waterproofing and insulaton
 
Concrete
ConcreteConcrete
Concrete
 
PRESENTATION ON CONCRETE
PRESENTATION ON CONCRETEPRESENTATION ON CONCRETE
PRESENTATION ON CONCRETE
 
FORMWORK, SCAFFOLDING, CENTERING
FORMWORK, SCAFFOLDING, CENTERINGFORMWORK, SCAFFOLDING, CENTERING
FORMWORK, SCAFFOLDING, CENTERING
 
Building maintenance
Building maintenance Building maintenance
Building maintenance
 
Underpinning
UnderpinningUnderpinning
Underpinning
 
Joints in concrete
Joints in concreteJoints in concrete
Joints in concrete
 
Roofs
RoofsRoofs
Roofs
 
What is wall? Different types of wall.
What is wall? Different types of wall.What is wall? Different types of wall.
What is wall? Different types of wall.
 
Reinforced Cement Concrete (RCC)
Reinforced Cement Concrete (RCC) Reinforced Cement Concrete (RCC)
Reinforced Cement Concrete (RCC)
 

En vedette

Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structuresRithika Ravishankar
 
Formwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyFormwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyI'mMiss Lily
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsHamdija Velagic
 
Different Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryDifferent Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryAbhishek Shah
 
Formwork in civil engineering
Formwork in civil engineeringFormwork in civil engineering
Formwork in civil engineeringFazal-E- Jalal
 
Formwork presentation my gp
Formwork presentation my gpFormwork presentation my gp
Formwork presentation my gpcheeweishan
 
MIVAN_An Aluminum Formwork Construction Technique
MIVAN_An Aluminum Formwork Construction TechniqueMIVAN_An Aluminum Formwork Construction Technique
MIVAN_An Aluminum Formwork Construction TechniqueSandeep Jain
 
formwork centering and scaffolding by khalid
formwork centering and scaffolding by khalid formwork centering and scaffolding by khalid
formwork centering and scaffolding by khalid shaikh khalid
 
Formwork seminar 2
Formwork seminar 2Formwork seminar 2
Formwork seminar 2Gali Suresh
 
Kompetensi 2 lengkap
Kompetensi 2 lengkapKompetensi 2 lengkap
Kompetensi 2 lengkapZul Hilmi
 
7 Types of Cladding
7 Types of Cladding7 Types of Cladding
7 Types of CladdingScullivan
 
FORM WORK AND SUPPORT WORK
FORM WORK AND SUPPORT WORKFORM WORK AND SUPPORT WORK
FORM WORK AND SUPPORT WORKElsje Nel
 

En vedette (20)

Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structures
 
Formwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyFormwork Presentation for Construction Technology
Formwork Presentation for Construction Technology
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldings
 
Formwork
FormworkFormwork
Formwork
 
Different Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryDifferent Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction Industry
 
Formwork in civil engineering
Formwork in civil engineeringFormwork in civil engineering
Formwork in civil engineering
 
Formwork presentation my gp
Formwork presentation my gpFormwork presentation my gp
Formwork presentation my gp
 
MIVAN_An Aluminum Formwork Construction Technique
MIVAN_An Aluminum Formwork Construction TechniqueMIVAN_An Aluminum Formwork Construction Technique
MIVAN_An Aluminum Formwork Construction Technique
 
Formwork
FormworkFormwork
Formwork
 
formwork centering and scaffolding by khalid
formwork centering and scaffolding by khalid formwork centering and scaffolding by khalid
formwork centering and scaffolding by khalid
 
Jump Formwork
Jump FormworkJump Formwork
Jump Formwork
 
Formwork seminar 2
Formwork seminar 2Formwork seminar 2
Formwork seminar 2
 
Scaffolding
ScaffoldingScaffolding
Scaffolding
 
Form Work
Form Work Form Work
Form Work
 
Kompetensi 2 lengkap
Kompetensi 2 lengkapKompetensi 2 lengkap
Kompetensi 2 lengkap
 
7 Types of Cladding
7 Types of Cladding7 Types of Cladding
7 Types of Cladding
 
Mesh Training
Mesh Training Mesh Training
Mesh Training
 
Site report
Site reportSite report
Site report
 
Scheme of work
Scheme of workScheme of work
Scheme of work
 
FORM WORK AND SUPPORT WORK
FORM WORK AND SUPPORT WORKFORM WORK AND SUPPORT WORK
FORM WORK AND SUPPORT WORK
 

Similaire à Formwork

types of formwork.pdf
types of formwork.pdftypes of formwork.pdf
types of formwork.pdfReigerRoyal
 
formwork Bco (1) final.pdf
formwork Bco (1) final.pdfformwork Bco (1) final.pdf
formwork Bco (1) final.pdfFaizanSolanki
 
All you need to know about Construction Formwork
All you need to know about Construction FormworkAll you need to know about Construction Formwork
All you need to know about Construction FormworkAnkit Singhai
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shutteringKishor Ade
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formworkKHUSHBU SHAH
 
Introduction and types of Form Work in civil engineering
Introduction and types of Form Work in civil engineeringIntroduction and types of Form Work in civil engineering
Introduction and types of Form Work in civil engineeringUjasPandya2
 
form work - Building construction necessities
form work - Building construction necessities  form work - Building construction necessities
form work - Building construction necessities Pradumn Suryakar
 
STEEL PPT FOR UPLOAD.pptx
STEEL PPT FOR UPLOAD.pptxSTEEL PPT FOR UPLOAD.pptx
STEEL PPT FOR UPLOAD.pptxPRAVII3
 
alternate wall technologies.pdf
alternate wall technologies.pdfalternate wall technologies.pdf
alternate wall technologies.pdfNithyashree594058
 
Forms and materials for speedy construction
Forms and materials for speedy constructionForms and materials for speedy construction
Forms and materials for speedy constructionMudassir khan
 
BUILDING MATERIALS.pptx
BUILDING MATERIALS.pptxBUILDING MATERIALS.pptx
BUILDING MATERIALS.pptxPRAVII3
 
The 6 Process Of Aluminium Castings
The 6 Process Of Aluminium CastingsThe 6 Process Of Aluminium Castings
The 6 Process Of Aluminium CastingsTurbo Cast
 

Similaire à Formwork (20)

types of formwork.pdf
types of formwork.pdftypes of formwork.pdf
types of formwork.pdf
 
formwork Bco (1) final.pdf
formwork Bco (1) final.pdfformwork Bco (1) final.pdf
formwork Bco (1) final.pdf
 
Gurme santoshkumar
Gurme santoshkumarGurme santoshkumar
Gurme santoshkumar
 
All you need to know about Construction Formwork
All you need to know about Construction FormworkAll you need to know about Construction Formwork
All you need to know about Construction Formwork
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shuttering
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
Steel formwork
Steel formworkSteel formwork
Steel formwork
 
FORMWORK.pptx
FORMWORK.pptxFORMWORK.pptx
FORMWORK.pptx
 
Introduction and types of Form Work in civil engineering
Introduction and types of Form Work in civil engineeringIntroduction and types of Form Work in civil engineering
Introduction and types of Form Work in civil engineering
 
form work - Building construction necessities
form work - Building construction necessities  form work - Building construction necessities
form work - Building construction necessities
 
Mivan shuttering
Mivan shutteringMivan shuttering
Mivan shuttering
 
Chapter 4
Chapter 4Chapter 4
Chapter 4
 
Formwork
FormworkFormwork
Formwork
 
STEEL PPT FOR UPLOAD.pptx
STEEL PPT FOR UPLOAD.pptxSTEEL PPT FOR UPLOAD.pptx
STEEL PPT FOR UPLOAD.pptx
 
alternate wall technologies.pdf
alternate wall technologies.pdfalternate wall technologies.pdf
alternate wall technologies.pdf
 
Formwork
FormworkFormwork
Formwork
 
Forms and materials for speedy construction
Forms and materials for speedy constructionForms and materials for speedy construction
Forms and materials for speedy construction
 
BUILDING MATERIALS.pptx
BUILDING MATERIALS.pptxBUILDING MATERIALS.pptx
BUILDING MATERIALS.pptx
 
The 6 Process Of Aluminium Castings
The 6 Process Of Aluminium CastingsThe 6 Process Of Aluminium Castings
The 6 Process Of Aluminium Castings
 
Formwork
FormworkFormwork
Formwork
 

Dernier

INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the weldingMuhammadUzairLiaqat
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction managementMariconPadriquez1
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
lifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxlifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxsomshekarkn64
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 

Dernier (20)

INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the welding
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction management
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
lifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxlifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptx
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 

Formwork

  • 1. Presentation on FORMWORK Presented by Md. Imadul Islam MD.Samiul Islam Md.Tajmul Islam Md.Mahmudul Hasan Prince Kumar Mondal
  • 2. What is formwork? • Formwork is a mould including all supporting structures, used to shape and support the concrete until it attains sufficient strength to carry its own weight. • It should be capable of carrying all imposed dead and live loads apart from its own weight.
  • 3. Requirements good formwork 1. It should be strong enough to withstand all types of dead and live loads. 2. It should be rigidly constructed and efficiently propped and braced both horizontally and vertically, so as to retain its shape. 3. The joints in the formwork should be tight against leakage of cement grout. 4. Construction of formwork should permit removal of various parts in desired sequences without damage to the concrete. 5. The material of the formwork should be cheap, easily available and should be suitable for reuse. 6. The formwork should be set accurately to the desired line and levels should have plane surface. 7. It should be as light as possible. 8. The material of the formwork should not warp or get distorted when exposed to the elements. 9. It should rest on firm base.
  • 4. Economy in formwork • The cost of formwork may range between 30 to 40% of the cost of concrete work. • Special structure like bridge ,tall chimneys, dams etc; the cost of formwork may range between 50 to 100%. • The building should be planned in such a way that there are minimum number of various in the size rooms, floor area etc. so as to permit reuse of the formwork moulds repeatedly. • Formwork shall be made of low cost materials, energy and labor if possible. • Formwork care and maintenance should be done according to specifications.
  • 5. Types of formwork • Timber formwork • Steel formwork • Plywood formwork • Aluminum formwork • Plastics formwork
  • 6. Timber formwork • It should be well seasoned. • It should be light weight. • It should be easily workable with nail without splitting. • It should be free from knots.
  • 7. Advantage of timber formwork • Easy handling because it is light weight. • Easy to disassemble. • Damaged parts can be replaced with new one. • Very flexible. • Easy to produce. • Easily available.
  • 8. Disadvantage of timber formwork • Limited size of shape. • Excessive loss of heat. • A very smooth surface will be produced which would give problems for finishing process. • Limited fixing.
  • 9. STEEL FORMWORK • This consists of panels fabricated out of the thin steel plates stiffened along the edges by small steel angles. • The panel units can be held together through the use of suitable clamps or bolts and nuts. • The panels can be fabricated in large number in any desired modular shape or size. • Steel forms are largely used in large projects or in situation where large number reuses of the shuttering is possible. • This type of shuttering is considered most suitable for circular or curved structures.
  • 10. Advantages of steel formwork • It can be used for a no. of times. • It is non absorbent. • Smooth finish surface obtained. • No shrinkage of formwork occurs. • Easy to use. • Its volume is less. • Its strength is more.
  • 11. Disadvantage of steel formwork • Limited size or shape. • Excessive loss of heat. • A very smooth surface will be produced which would give problems for finishing process. • Limited fixing.
  • 12. Aluminum formwork • Manufactured using light weight aluminum. • Made up of aluminum metal frame that provides very sturdy and durable mold for pouring concrete.
  • 13. Advantages of aluminum formwork • Quickly and accurately assembled. • Reduces the labor cost owing to its easy installation. • Light weight component provides low pressure on the lower part of the buildings. • Aluminum metal surface offers easy cleaning after concrete is removed. • Faster construction cycles. • Easy to handle. • High quality finishes. • Can be easily recycled. • Can be repeatedly used without losing quality • Safe work platforms.
  • 14. Disadvantages of aluminum formwork • Initial high investment. • Compares very poorly on modifications, against brick work constructions. • Fear of theft of valuable Aluminum Extrusions & sheets & hence kit not being complete at critical stages of construction. • Mass Housing projects are not as high for investing in large number of Aluminum Formwork.
  • 15. Plywood formwork • The plywood is built up of odd number of layers with grain of adjacent layers perpendicular to each other. • Plywood is used extensively for formwork for concrete, especially for sheathing, decking and form linings. • There are two types of plywood – internal and exterior. • The interior type is bonded with water resistant glue and exterior type is bonded with water proof glue.
  • 17. Advantages of plywood formwork • Easily cut to shape on site. • Reusable. • Thinner plywood is used to facilitate bending. • Thicker plywood is used when the weight of concrete caused a standard thickness plywood to blow out, it might distorting the concrete face.
  • 18. Disadvantages of plywood formwork • The layering effect in plywood makes it porous and susceptible to water damage if exposed over time. • Plywood becomes heavy when wet and should be covered if left outside to reduce the risk of water damage.
  • 19. PLASTIC FORMWORK • Lightweight • Reusable • Chemical resistant • Fungus and termites resistant • Can be easily cut and nail by using wood working tools • Non degradable
  • 20. Construction of formwork • Propping and centering. • Shuttering. • Provision of camber. • Cleaning and surface treatment.
  • 21. Order and method of removing formwork • Shuttering forming the vertical faces of walls, beams and column sides should be removed first as they bear no load but only retain the concrete. • Shuttering forming soffit of slabs should be removed next. • Shuttering forming soffit of beams, girders or other heavily loaded shuttering should be removed in the end.
  • 24. Causes of formwork failure • Improper stripping and shore removal • Inadequate bracing • Vibration • Unstable soil under mudsills, shoring not plumb • Inadequate control of concrete placement • Lack of attention to formwork details
  • 25. Safety precaution • Material used for the construction of formwork must fulfill the specification. • Formwork is fixed firmly & properly • Construction area must be protected to prevent vandalism of formwork.
  • 26. Period for removal of formwork S.No Description of structural member Period of time 1 Walls Columns and vertical sides of beam 1 to 2 days 2 Slab 3 days 3 Beam soffits 7 days 4 Removal of props to slabs: (a)For slabs spanning up to 4.5 m (b) For slabs spanning over 4.5 m 7 days 14 days 5 Removal of props to beams and arches (a)Spanning up to 6 m (b)Spanning over 6 m 14 days 21 days