PRINCE2®	
Practitioner	Training
Frank	Turley
Unbored.training	
PT0078	
17/12/2017
2
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
IPR	acknowledgements
• PRINCE2®	is	a	registered	Trade	Mark	of	AXELOS	Limited.	
• ITIL®	is	a	registered	Trade	Mark	of	AXELOS	Limited.
• M_o_R®	is	a	registered	Trade	Mark	of	AXELOS	Limited.
• P3O®	is	a	registered	Trade	Mark	of	AXELOS	Limited.
• MSP®	is	a	registered	Trade	Mark	of	AXELOS	Limited.
• P3M3®	is	a	registered	Trade	Mark	of	AXELOS	Limited.	
• MoV®	is	a	registered	Trade	Mark	of	AXELOS	Limited.
• MoP®	is	a	registered	Trade	Mark	of	AXELOS	Limited.
• The	Swirl	logo™	is	a	Trade	Mark	of	AXELOS	Limited.
3
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Course	Objectives
• Learn	what	a	project	is	and	what	is	its	context
• Establish	an	understanding	of	the	benefits	of	using	PRINCE2
• Establish	the	purpose	of	the	PRINCE2	themes
• Learn	about	the	roles	and	the	management	products	used
• Learn	about	the	PRINCE2	principles
• Establish	the	purpose,	objectives	and	context	of	the	PRINCE2	processes
• Work	on	PRINCE2	project	scenarios
4
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Target	Audience
• Project	managers	(or	those	who	would	like	to	become	one)
• Key	staff	involved	in	the	design,	development	and	delivery	of	projects
– Project	Board	members
– Team	managers
– Project	assurance
– Project	support	
– Operational	line	managers/staff.
5
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Themes	
Review
Break Tailoring
Lunch
Processes	
-1-
Day	1
Lunch
Practitioner	Exam
Day	2
Break
Sample	Exam	+	Review
Processes	
-2-
Sample	Exam	+	Review
6
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
ABOUT	THE	COURSE
7
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
The	whole	PRINCE2	Practitioner	training	is	based	
on	the	assumption	that	you	are	familiar	with	the	
PRINCE2	Foundation	concept
PRINCE2	Practitioner	Reminder…
PRINCE2	Foundation
8
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
• PRINCE2	practitioner	classroom	slides
• PRINCE2	process	model	diagram
• PRINCE2	management	product	map
• PRINCE2	timeline	diagram
• Official	sample	exam	#1	and	rationale
• Official	sample	exam	#2	and	rationale
• Management	plaza	sample	exam	#1	and	rationale
• Management	plaza	sample	exam	#2	and	rationale
• PRINCE2	practitioner	training	manual
• “Managing	Successful	Projects	with	PRINCE2”
PRINCE2	Practitioner
Training	Material
9
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
BUSINESS	CASE
PRINCE2	Themes	
Additional	information	for	practitioner	syllabus
10
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Business	case:	Management	documents
Delivery
Teammanager
Direction
ProjectBoard
Corp..
Corporate, programme management, customer
Business case
Benefits M.A.
Business case
Stage	Boundary:	Updated
Management
Projectmanager
P
I
D
SU process
Benefits M.A.
Updated
Created
Business case
Project brief
-- Outline BC
Starting	up
a project Closing	a	project
Benefits M.A.
Develop	business	case	 Maintain	business	case	
Planning
Initiation – 1st
stage Delivery stages : Controlling a stage & stage boundary Closing a projectPre-Project
Project
mandate
Business	case	documentation
1-Outline business	case	
- Created	by	executive:	part	of	the	project	brief	
2-Business	case		
3-Benefits	management	approach
4-Updated	business	case	
5-Updated	benefits	management	approach	(if	necessary)
6-Update	benefits	management	approach
- Plan	the	post-project	benefits	review
7- business	case	(final	update	with	cost	data)
1 2
3
4
5
6
7
by Frank Turley
mplaza.pm
Version 1.2d
Based	on	AXELOS	PRINCE2®	material.	Reproduced	under	licence from	AXELOS	Limited.	All	rights	reserved.
11
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Business	case
Summary	of	key	points	and	ROI	information:
e.g.		Give	out	pens	to	clients	to	increase	contracts	renewals	
Benefit:	Reduce	loss	of	maintenance	contracts	by	50%	:	€58,600		
ROI:	Return	on	Investment:	Cost	=	€4,800:	Gain	=	€58,600		
1. Executive summary
Examine	options:	Do	nothing,	do	minimum,	do	something.		E.g.	
Option	1:	do	nothing	:	Continue	losing	contracts:		lose	€84,000
Option	2:	offer	a	calendar:
• Value:	not	perceived	as	a	quality	item	
Option	3:	offer	pen	that	clients	will	continue	to	use:		
• Value:	Contacts	will	hold	on	to	the	pens	
• Believe	this	will	have	the	effect	to	reduce	loss	
3. Business options
List	measureable	benefits	that	are	aligned	to	corporate	strategy	
e.g.	Reduce	loss	of	maintenance	contracts	by	50%	:	€42,000	(each	year)
4. Expected benefits
Date:	Document: Project: Author:
Timescales	for	project	plan	and	benefits	realization.	
E.g.	Project	start:	March	5th,	Project	End:	May	31st (12	weeks)	
E.g.	Measure	benefits	on	28/12/2017	and	31/05/2018	
6. Timescales
Summary	of	the	key	risks	(taken from	risk	register)	
e.g.	Due		to	the	variety	of	possible	pens,	there	is	a	threat	that	we	can	choose	the	wrong	pen	which	
the	majority	of	clients	will	not	keep	using	the	pen	as	expected.
9. Major risks
List	reasons for	the	project	and	impact	on	corporate	strategy.
e.g.	Build	better	relationship	with	clients	and	reduce	the	loss	in	the	renewal	of	maintenance	
contracts	from	10%	to	5%.		
CopyWorld has	4,200	maintenance	contracts	with	an	average	profit	of	€200	per	contract	=	
€840,000.
2. Reasons
List	dis-benefits	(seen as	negative	by	some	stakeholders)		
5. Expected dis-benefits
Include	project	(Project	plan)	and	maintenance	costs	
e.g.	Pen	costs:	€10	by	400	pens	=	€4,000		
e.g.	Other	project	costs:	€800	
7. Costs
Document	investment	appraisal	– show	project	value.		E.g.		
• Project	cost:	 €4,800			
• Expected	gain: €58,400			
• Time	: 1	year	
• ROI: 1120.80%	(to	update)	
8. Investment appraisal
Business	case	(sample	from	Pen	Project)
Based	on	AXELOS	PRINCE2®	material.	Reproduced	under	licence from	AXELOS	Limited.	All	rights	reserved.
12
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Pre-project Initiation stage Subsequent delivery stages Final delivery stage Post-project
Verify outline business
case
Verify updated business
case
Develop business case Maintain business case
Verify detailed business
case
Answer:			
• First	verification	point	by	project	board	is	at	the end	of	SU	process		
• Second	verification	point	by	project	board	is	at	the end	of	IP	process
• Next	verifications	points	are	at the end	of	each	stage	
• Last	verification	point	for	project	board	is	at	the end	of	the	project				
Question:	Where	do	you	verify	the	business	case?	
Business	case
Verifying the business case
Based	on	AXELOS	PRINCE2®	material.	Reproduced	under	licence from	AXELOS	Limited.	All	rights	reserved.
13
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
1. Created	by	project	manager	in	the	initiation	stage	
2. Information	is	provided	by	senior	user
3. Project	board	approves	the	benefits	management	approach
4. Check	for	realized	benefits at	the	end	of	each	stage
5. Plan	benefits	review	after	project	(Post-project)
6. Check	for	realized	benefits	(Post-project)	
• Some	projects	check	for	realized	benefits	during	the	project:		
• Example:	New	CRM	functionality	released	to	users	after	each	stage	
• The	senior	supplier	is	responsible	for	creating	the	products	to	achieve	the	benefits	
• CPC	Mgmt	do	the	benefit	review	after	the	project.	Eg:	6,	12,	18,	24	months		
• Project	manager
• Senior	user
• Project	board
• Project	manager
• Project	manager
• CPC
• A	plan	that	defines	how	&	when	benefits	are	measured
• A	plan to	review the	benefits è benefits	management	approach	
Benefits	management	approach	steps:	
Pre-project Initiation stage Subsequent delivery stages Final delivery stage Post-project
Create BMA
Check benefits
Approve BMA
Check
benefits
Who:	 PM PM Corp…
Check benefits
Plan post reviews
3
1
2
4 5 6
Business	case
Benefits	management	approach
14
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
ORGANIZATION
PRINCE2	Themes	
Additional	information	for	practitioner	syllabus
15
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Delivery
Team	manager
Direction
Project	Board
Corp..
Authorize
initiation
Authorize
the	project
Authorize	a	stage		
or	exception	plan
Give	ad	hoc	
direction
Auth.	project
closure
Directing	a	project
Initiation – 1st
stage Closing a project
Corporate,	programme	management,	customer
End	stage	reportCommunication	M.A.
Stage	Boundary:	Created
Management
Project	manager
-- Team	manager	assists	the	project	manager
-- Created	once	during	project	(can	be	updated)
-- Created	or	updated	once	per	stage
-- Created	or	updated	many	times	during	a	stage	
-- Once	per	work	package
-- Many	per	work	package
P
I
D
SU process
Pre-Project
CP	is	the	last	part	
of	the	last	stage
Created
Project	brief
Assists	with	Planning
*
Initiation – 1st
stage Delivery stages : Controlling a stage & stage boundary Closing a projectPre-Project
- PMT
Starting	up
a project Closing	a	project
Delivery Stages : Controlling a stage & stage boundary
PMT	- roles
Organization	documentation
1-PMT	(Project	management	team)
- This	is	part	of	the	project	brief
2-Communication	management	approach
- Guideline	for	communication	during	project
3-PMT	role	descriptions
4-End	stage	report		
- Performance	review	and	 change	suggestions	to	PMT
1 2
3
4
Organization:	Management	products
Based	on	AXELOS	PRINCE2®	material.	Reproduced	under	licence from	AXELOS	Limited.	All	rights	reserved.
16
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Project	management	team
Delivery
Management
Direction
Senior	user Executive Senior	supplier
Corporate,	programme	management,	customer	
Project	manager
Team	manager
Change	authority
Project	support
Project	assurance
Business	Assurance
User	Assurance
Supplier	Assurance PROJECT
ANAGEMENT
TEAM
Organization:
Based	on	AXELOS	PRINCE2®	material.	Reproduced	under	licence from	AXELOS	Limited.	All	rights	reserved.
17
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Organization
• Monitors	all	aspects	of	the	project’s	performance	and	products	
• Independent	of	the	project	manager
• Gives	advice	and	guidance	to	the	project	manager
Project assurance
Business	assurance
User	assurance
Supplier	assurance
Project	assurance Risks	are	controlled,	right	people	are	involved	in	quality	inspection
Business	assurance Solution	provides	value	for	money,	payments	are	authorized
User	assurance Solution	will	meet	user	needs,	advise	on	changes
Supplier	assurance Review	product	descriptions,	monitor	production	risks
Project	assurance
18
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Organization
Introduction Purpose, objectives	and	scope	of	the	strategy
Communication	Procedure Communication	methods	to	be	used
Tools	and	Techniques
Communication	tools,	preferred techniques,	steps	in	the	
communication	process
Records Required	records and	where	they	will	be	stored
Reporting Communication process	(purpose,	timing, recipients)
Timing	of	communication activities
Timing	of	formal	communication	activities	and	performance audits	
for	the	methods
Roles	and	responsibilities Responsibilities	of	the	aspects	of	the	communication	process
Stakeholder	analysis Identification of	the	interested	parties,	relationship	status,	interfaces
Information	needs	for	interested	parties
Information	to/from	the	stakeholders;	frequency,	means	and	format	
of	communication
Communication	management	approach
19
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
This	document	describes	how	communication	will	be	done	during	the	project:	It	is	based	on	the	
standard	strategy	document	for	all	projects.	
1. Introduction
A	description	of	communication	methods	to	be	used	during	the	project	plus	any	variance	from	the	
corporate	standards.
e.g.	The	PM	is	responsible	for	all	internal	communication	and	will	report	each	week	on	the	project	
board	using	a	highlight	report.	The	Sales	Manager	is	responsible	for	all	external	communication.
2. Communication Procedure
Define	when	formal	communication	activities	will	take	place.	
e.g.	The	PM	will	meet	with	the project board	each	two	weeks.
5. Timing of communication activities
Communication	management	approach Date:	Document: Project: Author:
7. Roles & responsibilities
8. Scales: Priority & Severity
List	the	communication	tools	and	techniques	that	will	be	used.	
e.g.	The	PM	will	use	the	internal	portal	site	for	all	internal	communication	and	project	documents.	
The	Sales	Manager	will	use	a	newsletter	and	site	visits	to	communicate	with	clients.
3. Tools and techniques
Define	the	record(s)	that	will	be	used	to	log	communication	activities	and	the	location	that	they	will	
be	kept.
e.g.	A	log	to	keep	track	of	external	communication.
4. Records
6. reports / Stakeholder Matrix
Highlight	report
Report	Name Timing Recipients
Weekly Project	board
End	stage	report End	of	stage Project	board
End	project	report End	of	project Project	board
Issue	report Anytime CA/Project	board
Electronic	newsletter Once Clients	
Project	board Inform	the	rest	of	the	management	team
Project	manager All	internal	communication	(project	team)	
Create	the	required	PRINCE2®	documents
Senior	user Communicate	with	clients	
Priority Use	MoSCoW	(Must,	Should,	Could,	Won’t..)	
Severity	levels 1	=	project	manager,	2	=	project	board	
Clients
Stakeholders Current	Relationship Desired	Relation
90%	Good	 95%	Good	
Sales	Team Excellent Excellent	
Good	 Good	
9. Stakeholder Analysis
Attitude
Neutral
Support
Co. Mgmt Support
Organization
Based	on	AXELOS	PRINCE2®	material.	Reproduced	under	licence from	AXELOS	Limited.	All	rights	reserved.
20
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
QUALITY
PRINCE2	Themes	
Additional	information	for	practitioner	syllabus
21
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Delivery
Teammanager
Direction
ProjectBoard
Corp..
Corporate, programme management, customer
Team plan
Next stage planQuality M.A.
Project plan
or exception plan
Controlling	a	stage	Stage	Boundary:	Created
Products	are	created	here
Update	register	after	quality	check.
Management
Projectmanager
Work packages
-- Team manager is also responsible
-- Created once during project (can be updated)
-- Created or updated once per stage
-- Created or updated many times during a stage
-- Once per work package
-- Many per work package
P
I
D
SU process
Project brief
Quality	register
Assists	with	Planning
*
Initiation – 1st
stage Delivery stages : Controlling a stage & stage boundary Closing a projectPre-Project
- PPD
* Product descriptions
Quality register
Starting	up
a project
Closing	a	project
1:	Quality	planning	 2:	Quality	control	
Updated
Acceptance	criteria
(Acceptance	records)	
1-Project	product	description	(PPD)
2-Quality	management	approach
3-Product	descriptions	
4-Quality	register	(record	quality	activities)	
5-New	products	can	be	defined	
6-Quality	register	is	updated	(pass	or	fail)	
7-Acceptance	criteria	(handover)			
51 2
3
4
6
7
Quality:	Management	products
Based	on	AXELOS	PRINCE2®	material.	Reproduced	under	licence from	AXELOS	Limited.	All	rights	reserved.
22
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Delivery
Teammanager
Pre-Project – SU Initiation – 1st stage
Quality	register	– contents	
• List	all	products	names	+	IDs	(from	Plan)	
• List	quality	method		
• Quality	reviewer	&	approver			
• Expected	delivery	dates	
• Target	&	actual	quality	review	dates	
Management
Projectmanager
Project brief
PPD
QMS
Project plan
Product
Descriptions
Acceptance	criteria
Project	product	
description	(PPD)
Quality requirements
from Customer
Customer’s	quality	
expectations
Quality	
responsibilities
Quality information in product
descriptions
Quality	criteria	and	
tolerances
Quality	methods
Quality	planning	– 6	Steps
Quality	register	:	Plan	Quality	Activities
1
2
3
4
5
6
Quality	management	approach
Quality	planning	steps
1. Understand - customer’s	quality	expectations
2. Defining	the	project’s	acceptance	Criteria
3. Add	to	project product	description
4. Prepare	the	quality management	approach
5. PD’s	with	quality	information	
6. Set the	quality register	(record	quality	activities)
Questions:	
• When	does	PRINCE2®	first	think	about	quality?	
• Where	does	the	quality	data	come	from?		
• What	is	the	value	of	the	QMS?		
• Why	is	a	quality	register	part	of	quality	planning?	
Quality:	Planning	Steps
Based	on	AXELOS	PRINCE2®	material.	Reproduced	under	licence from	AXELOS	Limited.	All	rights	reserved.
23
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
A.21	Project	product	description
Title
Purpose
Composition	(parts)	
Derivation	(tools,	design	plans)	
Development	skills	required	
Customer’s	quality	expectations
Acceptance	criteria
Project	level	quality	tolerances	
Acceptance	method	
Acceptance	responsibilities
Identifier
Title
Purpose		
Composition
Derivation	
Format	and	presentation
Development	skills	required	
Quality	criteria
Quality	tolerance	
Quality	method		
Quality	skills	required	
Quality	responsibilities		
A.17	Product	description
Quality
Product	quality	information
24
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Quality	
Introduction Purpose, objectives	and	scope	of	the	strategy
Quality	Management	Procedure
Quality	management procedure	to	be	used	(quality	planning and	
control,	assurance	activities)
Tools	and	Techniques
Any	quality	management systems	or	tools	to	be	used	and	preferred
techniques
Records
Types	of	required	quality	records	,	where	they	will	be	stored	and	the	
format	of	the	quality	register
Reporting Reports	on	the	quality	management	(purpose,	timing	and	recipients)
Timing	of	communication activities Timing	of	formal	quality	management	activities	such	as	audits	
Roles	and	responsibilities
Responsibilities	for	quality	management	activities, including	quality	
responsibilities	from	CPC
CPC:	Corporate,	programme	management,	customer	
Quality	management	approach
25
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Producer
Quality
Reviewer
Approval
16 31 Wall	Insulation Inspection JV WP RT 28/9 2/10 10/10 10/10 11/10 Pass links
17 32 Heating
Furnace
Inspection TM TL RT 8/10 14/10 21/10 27/10 Fail links
18 33 Heating
Furnace
Performance test MP TL RT 17/10 21/10 27/10
19 34 Kitchen
Fittings
Inspection AM OH BD 1/11 5/11 14/11
Quality	ID
Product	ID
Quality		
Reviewers
Quality
Method
Product	
Name
Producer
Approver	
Target	Quality	
Review	Date
Actual	Quality		
Review	Date
Actual	Approval
Date
Target
Approval		Date
Result
Records
Quality
Dates
Approval
Dates
* * * * *
* Data	is	taken	from	the	project,	stage,	team	plan	(schedule)	
PD PD
PD Data	is	taken	from	the	product	descriptions	(project	plan)
Production	
date	
**
Steps	are:	
Results	of	Quality	Tests	+	Links	
Quality
Quality	register
Based	on	AXELOS	PRINCE2®	material.	Reproduced	under	licence
from	AXELOS	Limited.	All	rights	reserved.
26
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
• Quality	assurance	reports	to	CPC
• Project	assurance is	the	responsibility	of	the	project	board	
Quality
Quality	
Assurance
Corporate,	programme	management,	customer
DeliveryManagementDirection
Senior
User
Executive
Project manager
Project assurance
Business	assurance
User	assurance
Supplier	assurance
Team
manager
QA	is	focused	on	the:
• Quality	process	of	the	project
• Company	standards	are	met
• Risk	management	is	done	correctly
• Communication	is	done	correctly
• Business	case	is	verified			
• Issues are	tracked	correctly
• Etc..	
This	role	has	nothing	to	do	with	
checking	the	quality	of	the	products	
after	they	are	produced.	
Senior supplier
Change
authority
Project
support
Quality	assurance
Based	on	AXELOS	PRINCE2®	material.	Reproduced	under	licence from	AXELOS	Limited.	All	rights	reserved.
27
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Quality	assurance	
• Interested	to	see	that	all	projects	are	following	company	standards
• This	role	is	defined	in	the	PRINCE2®	manual	
Quality	Tester	
• This	role	is	NOT	defined	in	the	PRINCE2®	manual	
• They	test	the	products	before	they	are	returned	to	the	project	manager
• The	following	information	is	defined	in	each	product	description	
• Quality	method		(how	the	testing	will	be	done)	
• Quality	skills	required	
• Quality	responsibilities		(who	does	what)	
Quality
Quality	assurance	vs	Quality	testers
28
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
PLANS
PRINCE2	Themes	
Additional	information	for	practitioner	syllabus
29
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Delivery
Teammanager
Direction
ProjectBoard
Initiation – 1st stage Delivery stages / controlling a stage Closing a project
Corporate, programme management, customer
Team plan
SB: Next stage plan
IS plan Project plan
or exception plan .
Updated
Created
SB: Project plan
- Optional
- Non	PRINCE2®	Format		
Management
Projectmanager
Updated
-- Once during project
-- Once per stage
-- Many times during stage
-- Once per work package
-- Many per work package
Project plan
PFD The	path	to	planning	
1-Create	project	product	description	(PPD)
2-IS	Plan	(Plan	for	initiation	stage)
3-Product	based planning	
- PBS:	Product	breakdown	structure	
- PDs:	Product	descriptions	
- PFD:	Product	flow	diagrams	
4-Project	plan	
5-Next	stage	plan		
6-Exception	plan	(if	needed)	
7-Update	project	plan
8-Create	team	plan	(optional)		
9-Update	project	plan	(show	complete)	
Product	Base	Planning
PBS
PDs
PPD
2
3
4
1
6
5
8
7
9
Plans:	Management	products
Based	on	AXELOS	PRINCE2®	material.	Reproduced	under	licence from	AXELOS	Limited.	All	rights	reserved.
30
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Stage	plan		- example
Brief introduction / description of a project plan
e.g. This is the plan for the initiation stage of the Pen Project
1. Plan description
What	must	be	and	remain	in	place	for	the	plan	to	succeed	
e.g.	Sales	Manager	provides	the	necessary	time	for	the	project	
e.g.	Twenty	sales	persons will	be	available	to	evaluate	the	pens	
2. Plan prerequisites
Attached:	Project	product	description	
9. Products description(s)
Date:	Document: Project: Pen	Project Author: Project	manager
e.g.	A	business	gift	company	will	have	to	provide	the	pens	to	evaluate	and	the	400	pens	after	
chosing.	
3. External dependencies
Lists the	assumptions on	which	the	plan	is	based.
e.g.	Internal	recourses	will	not	be	charged to	the	project.	
4. Planning assumptions
List	the	lessons	that	have	value	for	this	plan.
e.g.	Allow	buffer	time	for	delivery	of	pens	(lessons	log)
e.g.	Investigate	the	ISO	standard	for	pens:	ISO	12757-2
5. Lessons incorporated
How	the	plan	will	be	monitored	and	controlled	
e.g.	The	PM	will	use	the	standard	PRINCE2®	documents.
e.g.	A	highlight	report will	be	sent	at	the	end of	week 1 to	the	PB.
6. Monitoring & control
e.g.	Initiation	stage	budget:		€	200	(internal	people	time	is	not	charged)	
e.g.	Risk	budget:	€0,			Change	budget:	€0		
7. Budgets
e.g.	Time:		+- 50%		:		Cost:	+- 50%		:		Quality:	+- 10%		:		Scope:	0%					
8. Tolerances
10. Schedule (Example)
4th 5th 6th 7th 8th 11th 12th 13th 14th 15thDeliverables	- March
Strategy	documents
WBS
Product descriptions	
Risks &	issues
Project	plan
Benefits	M.A.
Business	case
PID
Next stage	plan	
1 hr
8 hrs
1 hr
4 hrs
2 hrs
2 hrs
4 hrs
3 hrs
2 hrs
Plans
Based	on	AXELOS	PRINCE2®	material.	Reproduced	under	licence from	AXELOS	Limited.	All	rights	reserved.
31
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
• Three	levels	of	plans:	project,	stage	and	team	(optional)	
• Project	product	description	
– Composition	lists	the	major	products	that	the	project	will	produce	
– Also	includes	customer’s	quality	expectations	and	acceptance	criteria		
– Each	product	listed	may	also	have	a	product	description		
• Product	descriptions	
– Details	requirements	and	quality	information		
– A	product	breakdown	structure	will	be	used	to	identify	all	products
– Product	descriptions	are	created	and updated in	IP	and	SB	processes	
– Includes	quality	criteria,	tolerances,	producer	and	quality	method
Plans
Other	Key	Points:	Plans
32
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
RISK
PRINCE2	Themes	
Additional	information	for	practitioner	syllabus
33
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Delivery
Team	manager
Direction
Project	Board
Corp..
Authorize
initiation
Authorize
the	project
Authorize	a	stage		
or	exception	plan
Give	ad	hoc	
direction
Auth.	project
closure
Directing	a	project
Initiation – 1st stage Closing a project
Corporate,	programme	management,	customer
CS:		Highlight	Risk	M.A.
Business	case
Controlling	a	stage	
Business	case		
Stage	Boundary:	Updated
Management
Project	manager
-- Team	manager	assists	the	project	manager
-- Created	once	during	project	(can	be	updated)
-- Created	or	updated	once	per	stage
-- Created	or	updated	many	times	during	a	stage	
-- Once	per	work	package
-- Many	per	work	package
P
I
D
SU process
Pre-Project
CP	is	the	last	part	
of	the	last	stage
CS: Risk register
Project	brief
Daily	log
Risk register
Assists	with	Planning
*
Initiation	– 1st
stage Delivery stages : Controlling a stage & stage boundary Closing a projectPre-Project
-- Outline	BC
Updated
Starting	up
a project Closing	a	project
Delivery stages : Controlling a stage & stage boundary
1-Outline	BC	– lists major	risks	
2-Risks	stored	in	daily	log	in	SU	process	
3-Business	case	(major	risks)	
4-Risk	M.A.	(guideline	for	risks)	
5-Risk	register	(all	risks	are	listed	here)	
6-Update	of	major	risks	
7-Include	major	risk	information	
8-Update	risks	in	the	risk	register
3
1
2
4
5
76
8
Risk:	Management	products
Based	on	AXELOS	PRINCE2®	material.	Reproduced	under	licence from	AXELOS	Limited.	All	rights	reserved.
34
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Risk
Risk	management	approach
Introduction Purpose, objectives	and	scope,	who	is	responsible
Risk	management	procedure Defining the	steps	of	the	risk	management	procedure
Tools	and	techniques Risk	management systems	or	tools	to	be	used
Records Composition	and	format	of	the	risk	register	and	other	records
Reporting Reports	to	be	produced, including	their	purpose,	timing	and	recipients
Timing	of	risk	management	activities Timing	of	formal risk	management	activities	like	end	stage	assements
Roles	and	responsibilities Roles	and	responsibilities	for	risk management	activities
Scales Defining scales	for	estimating	probability	and	impact,	e.g.	low,	medium,	high
Proximity How	proximity	for	risks	is	to	be	assessed
Risk categories Risk	categories to	be	used
Risk	response	categories Risk	response	categories to	be	used
Early	warning	indicators Any	indicators	to	be	used	to	track	critical	aspects of	the	project
Risk tolerance Threshold	levels	of	risk	exposure
Risk budget How	the	risk	budget	will	be	used
35
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Risk	register	:	Sample	 Date:	Document: Project: Pen	Project Author: Project	manager
ID
Risk		
Author
Date
register
Risk Category Risk	Description
Probability
x	Impact
Proximity
Response
Category
Status
Risk
Owner
Risk
Actionee
1 P	Smith 6/3/18 Ordering
A	risk	that	pens will	be	delivered	2-4	weeks	later	
which	will	impact	the	time	of	the	project <	€1000 Medium Reduce Active P	Smith J	Bell
2 S. Kelly 7/3/18 Product
50%	users may	not	like	the	pens	and	therefore	not	
keep	using	them	which	result	in	50%	less	benefits	 €	29,000
Medium Reduce Active S. Kelly R	Clark
3	 S. Kelly	 9/3/18 Product
Some	sales	people may	not	distribute	the	pens	as	
intended,	therefore	the	benefits	will	not	be	realized	
for	these	users
€	5,600 Medium Reduce Active S. Kelly S.	Kelly
This	risk	register	is	take	from	the	sample	PRINCE2®	Pen	project	
Project	Name Pen	Project	 Risk		/		Impact
Project	No 008 High	risk		>	€	7,500
Project	manager Rose	Clark Medium	>	€	1000
Project	executive John	King Low	risk	< €	1000
Amount	is	related	to	the	value
of	the	expected	benefits	
Expected	gain	is:		€58,400			
The	response	text	is	not	included	in	this	example	
Risk
Based	on	AXELOS	PRINCE2®	material.	Reproduced	under	licence from	AXELOS	Limited.	All	rights	reserved.
36
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Risk	identifier
Risk	author
Date	registered
Risk	category
Risk	description	
Probability
Proximity	
Risk	response	categories
Risk	response	
Risk	status		
Risk	owner	
Risk	actionee	
Provides	records	of	identified	risks	including status,	history,	impact…	
Unique	reference	for	each	risk
Person	who	raised	the	risk	
Date	identified	/	registered	
Choose	category:	e.g.	Schedule,	Quality,	Legal,	…
Description:		Due	to…	there	is	a	risk….	Impacts	are….	
Probability,	impact	and	expected	value	
How	close	in	time	in	relation	to	the	project	
Choose	threat	or	opportunity	responses	
List	action	to	resolve	the	risk		
Normally	“Active”	or	“Closed”	
Person	responsible	for	managing	the	risk	
Person	who	will	implement	actions	listed in	response
Risk
Risk	register
37
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Inherent	risk:
• The	identified	and	assessed	risk
Residual	risk:
• Leftover	impact	after	a	response	was	implemented
Secondary	risk:
• New	risk	caused	by	the	implementation	of	a	response
Inherent,	secondary	and	residual	risks
Risk
Risk	planning
38
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Avoid	a	threat
• Eliminate	the	impact	or	prevent	it	from	happening	(probability	zero)
Reduce	a	threat
• Proactive
• Reduce	the	probability	of	the	event
• Reduce	the	impact	of	the	event
Prepare	contigent	plans
• Reactive	and	affects	only	the	impact
• Reduces	the	impact
• A	plan	of	actions	implemented	to	reduce	the	impact
• Preparing	plans	now,	but	not	taking	action	now.	
Threats	risk	responses
Risk
39
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Transfer	the	risk	
• A	form	of	“reduce”	response
• Reduces	financial	impact	only
• Some	of	the	impact	becomes	the	responsibility	of	a	third	party
• Mostly	on	a	contractual	basis
Accept	the	risk
• Organization	‘takes	the	chance’	that	the	risk	will	occur
• And	with	full	impact	if	it	did.	
Share	the	risk
• Application	of	a	pain/gain	formula
• Within	preset	limits,	both	parties	share	the	pain	or	the	gain
Threat	risk	responses	
Risk
40
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Exploit	an	opportunity
• Ensuring	that	the	impact	will	happen
• Ensuring	that	the	impact	will	realize
Enhance	an	opportunity
• Enhance	the	probability	of	the	event	occuring
• Enhance	the	impact	of	the	event
Transfer	the	risk	
• Transfer	can	apply	to	opportunities	
• Not	a	commonly	used	option	for	opportunities
Opportinity	risk	responses
Risk
41
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Share	the	risk
• Application	of	a	pain/gain	formula
• Within	preset	limits,	both	parties	share	the	pain	or	the	gain
Accept	the	risk
• Organization	‘takes	the	chance’	that	the	risk	will	occur
• And	with	full	impact	if	it	did.	
Prepare	contigent	plans
• We	will	accept	the	risk	for	now,	
• Make	a	plan	for	what	we’ll	do	if	the	situation	changes	
Opportinity	risk	responses
Risk
42
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
CHANGES
PRINCE2	Themes	
Additional	information	for	practitioner	syllabus
43
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Approve
Reject	
Defer	decision
Request	more	info	
Ask	for	exception	plan	
Request	for	
Change
Project	board
(Change	authority)
PM	may	decide	on	small	changes
So	the	PM	has	some	change	authority
Grant	a	concession
Instruct	it	be	resolved		
Defer	decision	
Request	more	info	
Ask	for	exception	plan	
Off-Specification Project	board
(Change	Authority)
Out	of	specification	with	product	
description		
Problem	/	
Concern
Provide	guidance
Ask	for	exception	plan	Project	board
PM	may	decide	if	with	tolerance
PM may	also	be	able	to	handle	issues
e.g.	small	issues	<	€500
The	PM	can	have	some	change	authority	responsibility	
New	
Issue
If	an	issue	will	bring	the	stage/project	out	of	tolerance,	then	the	issue	report	becomes	an	exception	report
Issue
report
Issue
report
Issue
report
Normally	from	user
Normally	from	supplier
Good	or	bad	news
Change
Based	on	AXELOS	PRINCE2®	material.	Reproduced	under	licence	from	AXELOS
Dealing	with	project	issues
Based	on	AXELOS	PRINCE2®	material.	Reproduced	under	licencefrom	
AXELOS	Limited.	All	rights	reserved.
44
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Project	board	/	Change	authority
Enter	or	update	in
Daily	log	or	issue	register	or	issue	report	
Request	
for	advice
Request	for	advice	/		
Exception	report
I)	Determine
• Issue	Type
• Severity
• Priority		
II)	Add	to	
• Daily	log?	
• Issue	register?
I)	Assess	impact	on
• Project	objectives
(6	performance	targets)
• Business	case	
• Project	plan
II)	Check	
• Severity	(Level)	
• Priority	(MoSCoW)
Propose	options	
Identify	options
Evaluate	options
Recommend	options	
Decide	
I)	Escalate	if	beyond	
delegated	authority	
II)	Approve	reject	or		
defer	option
PM	/	CA	/	Board	may	
decide	
PM	Implements	
I)	Take	corrective	action		
- New/Update	work	package
- Or	create	exception	plan		
II)	Update	records	and	
plans	(status)
Capture Examine Propose Decide Implement
Change
Issue	and	change	control	procedure
Based	on	AXELOS	PRINCE2®	material.	Reproduced	under	licence from	AXELOS	Limited.	All	rights	reserved.
45
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Delivery
Team	manager
Direction
Project	Board
Corp..
Initiation – 1st
stage Closing a project
Project
mandate
Corporate,	programme	management,	customer
Issue	reportsChange	control	approach
Management
Project	manager
-- Team	manager	assists	the	project	manager
-- Created	once	during	project	(can	be	updated)
-- Created	or	updated	once	per	stage
-- Created	or	updated	many	times	during	a	stage	
-- Once	per	work	package
-- Many	per	work	package
P
I
D
SU process
Pre-Project
Updated
Issue register
Daily log
Configuration item
records (CIR)
CIR docs (cmdb)
Daily	log
Issue	registers
*
Initiation	– 1st stage Delivery stages : Controlling a stage & stage boundary Closing a projectPre-Project
Updated
Starting	up
a project Closing	a	project
Delivery stages : Controlling a stage & stage boundary
CIR	docs
Product	status	account
Product	status	account
1
2
2
2
3
4
4
5
5
3
6
Change:	Management	products
Based	on	AXELOS	PRINCE2®	material.	Reproduced	under	licence from	AXELOS	Limited.	All	rights	reserved.
46
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
1. Change	control	approach
– Guideline	to	issue,	change	and	configuration	management	
2. Configuration	items	records
– One	record	per	product
– Contains	meta	data	for	each	product	
3. Product	status	accounts	
– Report	on	the	status	of	one	or	more	products
– Usually	created	during	SB	&	CP	processes
4. Daily	log	
– Used for	informal	issues	and	all	issues	during	the	SU	process	
5. Issue	register	
– Container	for	all	issues	(changes,	concerns	and	positive	issues)	that	are	handled	formally
6. Issue	reports			
– A	detailed	report	for	one	issue
– An	issue	report	which	describes	an	out	of	tolerance	issue	is	an	exception	report
…See	also	previous	slide		
Change
Management	products	to	control	issues	and	configuration
47
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Change
Request	
for	
Change
Approved
Use	the	change	
budget
Use	additional	
budget
De-scope	the	
project
How	to	fund	the	resolution	of	issues...
Tolerances	should	not	be	used	to	fund	requests	for	change
48
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Change
Off-
specification
Grant	a	
concession
No	immediate	
action	is	
required
How	to	fund	the	resolution	of	issues...
49
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Change
Problem
/Concern
Provide	
guidance
Ask	for	an	
exception	
plan
Resolve	the	
issue	by	
relaxing	
tolerances?
How	to	fund	the	resolution	of	issues...
50
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
PSA:	Product	status	account
CIR:	Configuration	item	records
Change
Change	control	approach
Introduction Purpose, objectives	and	scope,	identifies	who	is	responsible	
for	the	strategy
Configuration	management	procedure Defines	the	configuration	management procedure	to	be	used
Issue	and	change	control	procedure Defined	the	issue	and	change	control	procedure	to	be	used
Tools and	techniques Any	configuration	management systems	or	tools	to	be	used
Records Composition	and	format	of	the	issue	register	and	CIR
Reporting Composition,	format,	purpose,	timing	and	recipients	of	issue
report	and	PSA;	reviewing	the	performance	of	the	procedures
Timing	of	configuration	and	issue and	change	
control	activities
Timing of	formal	activities,	e.g.	configuration	audits
Roles	and	responsibilities Who	is	responsible	for	the	procedures, including	CPC	roles.	
Describes	change	authority	and	change	budget
Scales for	priority	and	severity For	prioritizing requests	for	change	and	off-specifications;	
determining	decision	makers	for	severity	and	priority	levels
51
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Change
Issue	report
Issue	identifier Unique	reference	for	every	issue,	same	as	the	one	in	Issue	register
Issue	type Type	of	issue	being	recorded
Date	raised Date issue	was	raised
Raised	by Person or	team	who	raised	the	issue
Issue	report	author Person or	team	who	created	the	issue	report
Issue	description Issue	description in	terms	of	its	cause	and	impact
Impact	analysis Detailed	analysis of	the	impact
Recommendation PM’s	recommendation	to	solve the	issue
Priority Given	in	project’s	chosen	scale,	re-evaluated	after	impact analysis
Severity Given	in	project’s	chosen	scale,	indicates	the	management level who	will	decide	on	the	issue
Decision The decision
Approved by Who	made the	decision
Decision	date Date of	decision
Closure date When	the	issue	is	closed
52
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
PROGRESS
PRINCE2	Themes	
Additional	information	for	practitioner	syllabus
53
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
• Authorizations
– Initiation	
– Project
– Each	stage
– Project	closure
• Progress	updates
– Highlight	reports
– End	stage	reports
• Exceptions	and	changes
– Exception	reports
– Issue	reports
– Exception	plans
What	does	the	project	board	use	to	control	the	project?	
Receive	Progress	reports	from	PM
Receive	from	PM	at	end	of	stage	
From	PM	if	expected	to	go	out	of	tolerance	
If	out	of	tolerance	or	need	advice	
When	requested	by	project	board	
Decision	point	1		
Decision	point	2	
Decision	point	for	each	stage	
Decision	point	Last	
Progress
Project	board	controls
54
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
• Authorizations
– Agreeing	and	authorizing	work	packages	and	work	
package	tolerances
• Progress	updates
– Checkpoint	reports
• Exceptions	and	changes
– PM	uses	project	registers	and	logs	to	review	progress	
and	identify	issues	and	risks	that	may	need	to	be	
resolved
What	does	the	project	manager	use	to	control	the	project?	
They authorize	when	they	are	sure	that	the	products	
will	be	created	as	expected
Regular	report	from	team	manager	to	the	project	
manager	
Eg:	Compare	planned	dates	vs actuals	
Eg:	Sort	Issues	&	Risks	by	most	critical
Deal	with	Issues	or	Escalate	
Progress
Project	manager	controls
55
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Delivery
Team	manager
Direction
Project	Board
Initiation	– 1st stage Closing a project
Management
Project	manager
SU process
Pre-Project Delivery stages : Controlling a stage & stage boundary
Team	plan	
Next	stage	plan	
IS	plan
Project	plan
Benefits	M.A.
or	exception	plan	
Stage	Boundary:	Updated
Stage	Boundary:	Created
Project	plan	
Updated
-- Team	manager	assists	the	project	manager
-- Created	once	during	project	(can	be	updated)
-- Created	or	updated	once	per	stage
-- Created	or	updated	many	times	during	a	stage	
-- Once	per	work	package
-- Many	per	work	package
P
I
D
Benefits	M.A.
Updated
Project	plan
CS: Risk register
CS: Issue register
CS: Daily log
CS: Product status
account
Daily	log
Risk,	quality,	issue	registers
Assists	with	Planning
*
Quality register
Controlling	a	stage	
Starting	up
a project
Project	controls
Which	products	are	used	by	the	PM	to	review	progress	against	plan?
Progress:	Management	products
Based	on	AXELOS	PRINCE2®	material.	Reproduced	under	licence from	AXELOS	Limited.	All	rights	reserved.
56
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Delivery
Teammanager
Direction
ProjectBoard
Checkpoint reports
Initiation – 1st stage Closing a project
End stage report CS: Highlight
Controlling	a	stage	
Created	Stage	Boundary:	Created
Product	delivery:	Created
Management
Projectmanager
Pre-Project
End project report
Created
Closing	a	project
Delivery stages : Controlling a stage & stage boundary
Which	reports	are	used	to	report	progress?	
• Checkpoint	report
• Highlight	report	
• End	stage	report	
• End	project	report	
Which	products	are	used	to	set	and	report	progress?
CS: Exception reportProject	controls
Part	of	the	PID
- Tolerances	
- #	of	stages
- Length	of	stages
- Frequency	reports
Project	controls	define	how	the	project	will	
be	controlled	
Progress:	Management	products
Based	on	AXELOS	PRINCE2®	material.	Reproduced	under	licence from	AXELOS	Limited.	All	rights	reserved.
57
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Progress
Highlight	report
Date Date	of	the	report
Period Period covered	by	this	highlight	report
Status	summary Overview of	the	status	of	the	stage	at	this	time
This	reporting period • WP’s	– pending	authorization,	in	execution	and	completed
• Products	completed
• Products	planned	but not	started	or	completed
• Corrective actions	taken
Next	reporting	period • WP’s	– to	be	authorized, in	execution	and	to	be	completed
• Products	to	be	completed
• Corrective	actions	to	be	completed
Project	and	stage	tolerance status How	the	project	and	the	stage	performing	against	tolerances
Requests	for	change Requests	for	change	received	in	this	period
Key	issues	and risks Summary	of actual	issues	and	risks
Lessons report A	review of	what	went	good/bad	and	recommendations	for	CPC
58
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Progress
End	stage	report
Project	manager’s	report Summary	of	the stage	performance
Review	of	the	business	case Summarizing the	validity	of	the	BC:	Deviations	from	BC,	aggregated	risk	exposure
Review	of	project objectives How	the	project	performed against	its	targets,	review	of	strategies	and	controls
Review	of	stage	objectives How	the	stage	performed against	its	targets
Review	of	team	performance Providing recognition	for	good	performance
Review	of	producs
Quality	records Quality	activities	planned	and	completed
Approval	records Products planned	for	completion
Off-specifications Products	with	off-specifications and	concessions	granted
Phased	handover Client confirmation	that	they	are	ready	to	receive	the	release
Summary	of	follow-on	action	
recommendations
Asking	for	advice	who	will	receive	the recommended	actions
Lessons	report Review	of	what	went	good/bad,	recommendations	for	CPC
Issues and	risks Summary	of	current	issues and	risks
Forecast PM’s	forecast	for	the project	and	the	stage	against	targets	and	tolerances
59
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
TAILORING
60
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Tailoring	PRINCE2
Tailoring	vs	Embedding
Tailoring...
...	Adapting	PRINCE2	to	the	context	of	a	specific	project
...	Done	by	the	project	management	team
Embedding...
...	Adopting	PRINCE2	in	the	organization
...	Done	by	the	organization
61
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
• TAILORING	focuses	on…	
– Adapting	the	themes	
(through	the	strategies	and	controls)	
– Incorporating	specific	terms	and	
language
– Revising	the	product	descriptions	for	
the	management	products	
– Revising	the	role	descriptions	for	the	
PRINCE2	project	roles	
– Adjusting	the	processes	to	match	
the	above.	
Tailoring	PRINCE2
Tailoring	vs	Embedding
• EMBEDDING	focuses	on…
– Process	responsibilities	
– Scaling	rules/guidance	
(e.g.	score	card)	
– Standards	(templates,	definitions)	
– Training	and	development	
– Integration	with	business	processes	
– Tools	&	process	assurance
62
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
• PRINCE2®	assumes	that	there	will	be:	
– A	customer specifying	the	desired	result	and	probably	pay	for	the	project	
– A	supplier	providing	the	resources	and	skills	to	deliver	that	result.	
• If	the	relationship	between	customer	and	supplier	is	a	commercial	one,	then	
there	are	at	least	two	sets	of:	
– Reasons	for	undertaking	the	project	(own	reasons)	
– Management	systems	(project	methods)		
– Governance	structures	(may	require	disclosure	of	project	data)	
– Corporate	cultures	(e.g.	formality,	risk	taking)		
Tailoring	PRINCE2
Customer/Supplier	Environment
63
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
• Two	business	cases
– one	for	the	Customer	and	one	for	the	Supplier	projects
Customer	business	case
• Benefits	to	the	customer	against	the	costs	and	risks
• Costs	include	internal	costs	(customer	project	resources,	ongoing	operations	
and	maintenance	resources)	and	external	costs	(supplier	goods	and	services)
• Risks	should	include	project	risks	and	ongoing	operations	risks
Supplier	business	case
• Covers	the	supplier	part	of	the	customer	project
• Should	also	consider	how	the	project	will	affect	the	supplier’s	sales	and	
market	objectives
Tailoring	PRINCE2
Commercial	Customer/Supplier	Environment
Business	case
64
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
• Who	should	be	the	senior	supplier	in	the	customer	project?
– Is	it	appropriate	to	have	a	senior	supplier	from	an	external	organization?
– What	happens	if	there	are	multiple	suppliers?
– Would	it	be	ok	to	work	with	a	temporary	senior	supplier	for	a	procurement	
stage?
– Would	the	person	responsible	for	the	performance	of	the	supplier	be	a	good	
choice	as	the	senior	supplier?
• Who	will	supply	the	project	manager?	Customer	or	supplier?	
– Normally	from	the	customer	organization,	supplier	project	manager	will	the	
team	manager	in	the	customer	project
– Supplier	can	provide	the	project	manager	(Project	assurance	will	be	critical)
Tailoring	PRINCE2
Commercial	Customer/Supplier	Environment
Organization
65
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
• Quality	management	approach
– Use	the	customer’s	quality	management	system?
– Use	the	supplier’s	quality	management	system?
– Or	use	a	combination	of	both?
Tailoring	PRINCE2
Commercial	Customer/Supplier	Environment
Quality
66
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
• Awarding	the	contract
– Purchase	orders	and	milestone	payments	aligned	to	stages
– Consider	break-points	in	the	contracts	if	project	closes	prematurely
Tailoring	PRINCE2
Commercial	Customer/Supplier	Environment
Plans
67
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
• Risk	register
– Need	separate	risk	registers?
– Some	risks	may	be	unique	to	one	party
– With	a	joint	risk	register
• Determine	whose	risk	it	is
• Assign	an	appropriate	risk	owner
Tailoring	PRINCE2
Commercial	Customer/Supplier	Environment
Risk
68
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
• Change	control	approach
– Align	the	change	control	procedures
– Align	the	change	provisions	(change	budget)
• Change	budget
– If	a	change	dudget	exists,
• Align	customer’s	purchasing	procedures	with	supplier’s	business	
approval	procedures
Tailoring	PRINCE2
Commercial	Customer/Supplier	Environment
Change
69
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
• Reviewing	and	reporting
– Align	both	organizations’	governance	requirements
Tailoring	PRINCE2
Commercial	Customer/Supplier	Environment
Progress
70
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
• Customer’s	processes
– Unlikely	that	tailoring	is	required
• Supplier’s	processes
– Starting	up	a	project	process
• Will	take	place	pre-contract
• Probably	be	in	response	to	the	customer’s	request	for	a	proposal
– Initiating	a	project	process
• Assessing	the	desirability	and	viability	of	the	sale	(pre-contract)
• Process	ends	only	after	customer	authorizes	the	project
• Contract	negotiations	are	managed	through	change	control
Tailoring	PRINCE2
Commercial	Customer/Supplier	Environment
Processes
71
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
• Contracts
– Liabilities	in	case	of	failure	to	fullfil	obligations
• Project	initiation	documentation
– Focuses	on	ensuring	that	obligations	are	fullfilled
– Can	be	part	of	the	contract
• But	then	each	change	may	require	a	legal	review
• Work	package
– Legally	binding	contract
– Include	terms	and	conditions
Tailoring	PRINCE2
Commercial	Customer/Supplier	Environment
Management	
Products
72
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
PROCESSES
73
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
• Management	product	map
– Overview	of	all	PRINCE2®	management		products		
• Provide	3	summary	slides	for	each	process	
1. Process	activity	slides	
2. Process	input	/	output	slide		
3. Process	responsibility	slides		
Processes	Introduction
Processes
74
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Processes:	Management	products	mapDelivery
Teammanager
Direction
ProjectBoard
Corp..
Authorize
initiation
Authorize
the project
Authorize a stage
or exception plan
Give ad hoc
direction
Auth. project
closure
Checkpoint reports
Directing a project
Initiation – 1st
Stage (Planning) Closing	a	project
Project
mandate
Corporate, programme management, customer
End stage report
CS: Highlight report
Team plan
CS: Issue/exc. reportsNext stage plan
IS plan
Communication M.A.
Change control approach
Quality M.A. Risk M.A.
Business case
Project plan
Benefits M.A.
or exception plan
Controlling a stage
Created
Business case
Stage Boundary: Updated
Stage Boundary: Created
Project plan
Product delivery: Created Updated
Management
Projectmanager
Work packages
-- Team manager is also responsible
-- Created once during project (can be updated)
-- Created or updated once per stage
-- Created or updated many times during a stage
-- Once per work package
-- Many per work package
P
I
DProject controls
PMT – roles
Project approach
Pre-Project
End project report
Follow on actions
Lessons report
Draft closure not.
Benefits M.A.
Updated
Created
Business case
Project plan
CS: Risk register
CS: Issue register
CS: Lessons log
CS: Daily log
CS: CIR
Project brief
CIR docs (cmdb)
Lessons	log
Daily	log
Risk,	Quality,	Issue	registers
+ Acceptance Records
TM assists with planning
*
Initiation – 1st
stage Delivery	stages	:	Controlling	a	stage	&	stage	boundary	 Closing	a	projectPre-Project
-- Outline BC
-- PPD
-- Approach
-- PMT
PBS
PDs
PFD
*
*
Quality register
Controlling a stage
Updated
Starting up
a project
Closing a project
Delivery	stages	:	Controlling	a	stage	&	stage	boundary	
e.g.80%
New requirements?
Issue/Risk register
Conf. Item Records
PRINCE2®	is	a	registered	trade	mark	of	AXELOS	Limited.		
The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited.		
Stage Boundary: Created
Product status account
Benefits M.A.
Based	on	AXELOS	PRINCE2®	material.	Reproduced	under	licence from	AXELOS	Limited.	All	rights	reserved.
75
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Processes:	Management	products	mapDelivery
Teammanager
Direction
ProjectBoard
CPC
Authorize
initiation
Authorize
the project
Authorize a stage
or exception plan
Give ad hoc
direction
Auth. project
closure
Checkpoint reports
Directing a project
Initiation – 1st
Stage (Planning) Closing	a	project
Project
mandate
Corporate, programme management, customer
End stage report
CS: Highlight report
Team plan
CS: Issue/exc. reportsNext stage plan
IS plan
Communication M.A.
Change control approach
Quality M.A. Risk M.A.
Business case
Project plan
Benefits M.A.
or exception plan
Controlling a stage
Created
Business case
Stage Boundary: Updated
Stage Boundary: Created
Project plan
Product delivery: Created Updated
Management
Projectmanager
Work packages
-- Team manager is also responsible
-- Created once during project (can be updated)
-- Created or updated once per stage
-- Created or updated many times during a stage
-- Once per work package
-- Many per work package
P
I
DProject controls
PMT – roles
Project approach
Pre-Project
End project report
Follow on actions
Lessons report
Draft closure not.
Benefits M.A.
Updated
Created
Business case
Project plan
CS: Risk register
CS: Issue register
CS: Lessons log
CS: Daily log
CS: CIR
Project brief
CIR docs (cmdb)
Lessons	log
Daily	log
Risk,	Quality,	Issue	registers
+ Acceptance Records
TM assists with planning
*
-- Outline BC
-- PPD
-- Approach
-- PMT
PBS
PDs
PFD
*
*
Quality register
Controlling a stage
Updated
Starting up
a project
Closing a project
Delivery	stages	:	Controlling	a	stage	&	stage	boundary	
e.g.80%
New requirements?
Issue/Risk register
Conf. Item Records
PRINCE2®	is	a	registered	trade	mark	of	AXELOS	Limited.		
The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited.		
Stage Boundary: Created
Product status account
Benefits M.A.
Based	on	AXELOS	PRINCE2®	material.	Reproduced	under	licence from	AXELOS	Limited.	All	rights	reserved.
76
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Processes:	Project	Timeline
1	week 4	weeks 8	weeks 8	weeks 8		weekse.g.	time
2:	Authorize	
the	project
CS	:	Stage	 CS	:	Stage	 CS	:	Stage	
I P
CPSB SB SB
Closing	a	project
Work	packages Work	packages Work	packages
60	hrs	 850	hrs	
Reports		&		Advise		 Reports		&		Advise		 Reports		&		Advise		
Authorize	next	stage
Project	board	decisions
Closing
1:	Authorize	
Initiation
Initiation	(Planning)
1st	stage
Pre-project
(feasibility)
Authorize	
project	close
delivery	stages	- (Execution)	
-- Once	during	project
-- Once	per	stage
-- Many	times	during	stage
-- Once	per	work	package
PRINCE2®	Project	Timeline	/	Example
project
mandate
Ver 1.3
7	processes
1	week
CS	:	Optional
Project	
board
Project	
manager
Team	
manager
SU PM
PM
PM
Team
PB
PM
PM
PM
Team
PB
PM
PM
PM
Team
PBDP
CS
SU	- IP
SB	/	CP		
MP
DP:	Directing	a	project
SU:	Starting	up	a	project
IP:	Initiating	a	project
CS:	Controlling	a	stage
SB:	Managing	a	stage	boundary
CP:	Closing	a	project
MP:	Managing	product	delivery
Based	on	AXELOS	PRINCE2®	material.	Reproduced	under	licence from	AXELOS	Limited.	All	rights	reserved.
77
PT0078-P2P-Class-EN, Version V013Copyright	©	PTCoE	NV and	AXELOS	Limited	2017.	All	rights	reserved. Material	in	this	document	has	been	sourced	from	Managing	Successful	Projects	with	PRINCE2®	2017	Edition. No	part	of	this	document	may	
be	reproduced	in	any	form	without	the	written	permission	of	both	PTCoE	NV and	AXELOS	Limited.	Permission	can	be	requested	at	support@mplaza.pm	and	licensing@axelos.com.	PRINCE2®	is	a	registered	
trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.	The	Swirl	logo™	is	a	trade	mark	of	AXELOS	Limited,	used	under	permission	of	AXELOS	Limited.	All	rights	reserved.
Starting	up	a	
project
Directing	a	
project
Initiating	a	
project
Controlling	a	
stage
Managing	
product	
delivery
Managing	a	
stage	
boundary
Closing	a	
project
PROCESSES
PRINCE2 Practitioner Classroom slides - Sample
PRINCE2 Practitioner Classroom slides - Sample
PRINCE2 Practitioner Classroom slides - Sample
PRINCE2 Practitioner Classroom slides - Sample
PRINCE2 Practitioner Classroom slides - Sample
PRINCE2 Practitioner Classroom slides - Sample
PRINCE2 Practitioner Classroom slides - Sample
PRINCE2 Practitioner Classroom slides - Sample
PRINCE2 Practitioner Classroom slides - Sample
PRINCE2 Practitioner Classroom slides - Sample
PRINCE2 Practitioner Classroom slides - Sample
PRINCE2 Practitioner Classroom slides - Sample
PRINCE2 Practitioner Classroom slides - Sample
PRINCE2 Practitioner Classroom slides - Sample
PRINCE2 Practitioner Classroom slides - Sample

Contenu connexe

Tendances

PRINCE2 Foundation Training Manual by Frank Turley
PRINCE2 Foundation Training Manual by Frank TurleyPRINCE2 Foundation Training Manual by Frank Turley
PRINCE2 Foundation Training Manual by Frank TurleyFrank Turley
 
PRINCE2 Foundation Guide - Sample - by Frank Turley
PRINCE2 Foundation Guide - Sample - by Frank TurleyPRINCE2 Foundation Guide - Sample - by Frank Turley
PRINCE2 Foundation Guide - Sample - by Frank TurleyFrank Turley
 
7 Themes of Prince2
7 Themes of Prince27 Themes of Prince2
7 Themes of Prince2Barry Hodge
 
7 Principles of PRINCE 2
7 Principles of PRINCE 27 Principles of PRINCE 2
7 Principles of PRINCE 2Barry Hodge
 
PRINCE2-Foundation PRINCE2 Real Exam Questions - 100% Free Prince2-Foundation...
PRINCE2-Foundation PRINCE2 Real Exam Questions - 100% Free Prince2-Foundation...PRINCE2-Foundation PRINCE2 Real Exam Questions - 100% Free Prince2-Foundation...
PRINCE2-Foundation PRINCE2 Real Exam Questions - 100% Free Prince2-Foundation...passleaders
 
The new PMP, what it is and how to get prepared for it
The new PMP, what it is and how to get prepared for itThe new PMP, what it is and how to get prepared for it
The new PMP, what it is and how to get prepared for itPMIUKChapter
 
PRINCE2 Foundation Workshops -- Organization
PRINCE2 Foundation Workshops -- OrganizationPRINCE2 Foundation Workshops -- Organization
PRINCE2 Foundation Workshops -- OrganizationFrank Turley
 
7 Processes of Prince2
7 Processes of Prince27 Processes of Prince2
7 Processes of Prince2Barry Hodge
 
PRINCE2 Process Model
PRINCE2 Process ModelPRINCE2 Process Model
PRINCE2 Process ModelprojectingIT
 
PMP Certification Chapter one Summary of PMBOK
PMP Certification Chapter one Summary of PMBOKPMP Certification Chapter one Summary of PMBOK
PMP Certification Chapter one Summary of PMBOKskiltful
 
Learn the PRINCE2 Principles ebook
Learn the PRINCE2 Principles ebookLearn the PRINCE2 Principles ebook
Learn the PRINCE2 Principles ebookKnowledge Train
 
Prince2 resources e book 2
Prince2 resources e book 2Prince2 resources e book 2
Prince2 resources e book 2Knowledge Train
 
The prince2 business case
The prince2 business caseThe prince2 business case
The prince2 business caseprojectingIT
 
The funkiest PRINCE2 Processes revision guide on the internet
The funkiest PRINCE2 Processes revision guide on the internetThe funkiest PRINCE2 Processes revision guide on the internet
The funkiest PRINCE2 Processes revision guide on the internetKnowledge Train
 
PMP Exam Prep_sample slides
PMP Exam Prep_sample slidesPMP Exam Prep_sample slides
PMP Exam Prep_sample slidesWilber Tuttleman
 
Prince2 & PMBOK Comparison Demystified
Prince2 & PMBOK Comparison DemystifiedPrince2 & PMBOK Comparison Demystified
Prince2 & PMBOK Comparison DemystifiedCTE Solutions Inc.
 

Tendances (20)

PRINCE2 Foundation Training Manual by Frank Turley
PRINCE2 Foundation Training Manual by Frank TurleyPRINCE2 Foundation Training Manual by Frank Turley
PRINCE2 Foundation Training Manual by Frank Turley
 
PRINCE2 Foundation Guide - Sample - by Frank Turley
PRINCE2 Foundation Guide - Sample - by Frank TurleyPRINCE2 Foundation Guide - Sample - by Frank Turley
PRINCE2 Foundation Guide - Sample - by Frank Turley
 
7 Themes of Prince2
7 Themes of Prince27 Themes of Prince2
7 Themes of Prince2
 
7 Principles of PRINCE 2
7 Principles of PRINCE 27 Principles of PRINCE 2
7 Principles of PRINCE 2
 
PRINCE2-Foundation PRINCE2 Real Exam Questions - 100% Free Prince2-Foundation...
PRINCE2-Foundation PRINCE2 Real Exam Questions - 100% Free Prince2-Foundation...PRINCE2-Foundation PRINCE2 Real Exam Questions - 100% Free Prince2-Foundation...
PRINCE2-Foundation PRINCE2 Real Exam Questions - 100% Free Prince2-Foundation...
 
PRINCE2 Overview
PRINCE2 OverviewPRINCE2 Overview
PRINCE2 Overview
 
PRINCE2 Process Model Flow Diagram
PRINCE2 Process Model Flow DiagramPRINCE2 Process Model Flow Diagram
PRINCE2 Process Model Flow Diagram
 
The new PMP, what it is and how to get prepared for it
The new PMP, what it is and how to get prepared for itThe new PMP, what it is and how to get prepared for it
The new PMP, what it is and how to get prepared for it
 
PRINCE2 Foundation Workshops -- Organization
PRINCE2 Foundation Workshops -- OrganizationPRINCE2 Foundation Workshops -- Organization
PRINCE2 Foundation Workshops -- Organization
 
7 Processes of Prince2
7 Processes of Prince27 Processes of Prince2
7 Processes of Prince2
 
PRINCE2 Process Model
PRINCE2 Process ModelPRINCE2 Process Model
PRINCE2 Process Model
 
PMP Certification Chapter one Summary of PMBOK
PMP Certification Chapter one Summary of PMBOKPMP Certification Chapter one Summary of PMBOK
PMP Certification Chapter one Summary of PMBOK
 
Prince2 Methodology
Prince2 MethodologyPrince2 Methodology
Prince2 Methodology
 
Learn the PRINCE2 Principles ebook
Learn the PRINCE2 Principles ebookLearn the PRINCE2 Principles ebook
Learn the PRINCE2 Principles ebook
 
Prince2 resources e book 2
Prince2 resources e book 2Prince2 resources e book 2
Prince2 resources e book 2
 
The prince2 business case
The prince2 business caseThe prince2 business case
The prince2 business case
 
PMO - Delivering Business Results
PMO - Delivering Business ResultsPMO - Delivering Business Results
PMO - Delivering Business Results
 
The funkiest PRINCE2 Processes revision guide on the internet
The funkiest PRINCE2 Processes revision guide on the internetThe funkiest PRINCE2 Processes revision guide on the internet
The funkiest PRINCE2 Processes revision guide on the internet
 
PMP Exam Prep_sample slides
PMP Exam Prep_sample slidesPMP Exam Prep_sample slides
PMP Exam Prep_sample slides
 
Prince2 & PMBOK Comparison Demystified
Prince2 & PMBOK Comparison DemystifiedPrince2 & PMBOK Comparison Demystified
Prince2 & PMBOK Comparison Demystified
 

Similaire à PRINCE2 Practitioner Classroom slides - Sample

Introduction to PRINCE2 Trainings
Introduction to PRINCE2 TrainingsIntroduction to PRINCE2 Trainings
Introduction to PRINCE2 TrainingsTania Aslam
 
Python Development Company - Paragyte Technology
Python Development Company - Paragyte TechnologyPython Development Company - Paragyte Technology
Python Development Company - Paragyte TechnologyParagyte Technologies
 
Arkatay on pmbok guide 6th ed, seminar october 3 2017
Arkatay on pmbok guide 6th ed, seminar october 3 2017Arkatay on pmbok guide 6th ed, seminar october 3 2017
Arkatay on pmbok guide 6th ed, seminar october 3 2017Jan Raaschou
 
PRINCE2 Practitioner Course Training Part 16
PRINCE2 Practitioner Course Training Part 16PRINCE2 Practitioner Course Training Part 16
PRINCE2 Practitioner Course Training Part 16Skillogic Solutions
 
Python Django tutorial | Getting Started With Django | Web Development With D...
Python Django tutorial | Getting Started With Django | Web Development With D...Python Django tutorial | Getting Started With Django | Web Development With D...
Python Django tutorial | Getting Started With Django | Web Development With D...Edureka!
 
PRINCE2 Certification Training - Foundation & Practitioner Part 1 (3)
PRINCE2 Certification Training - Foundation & Practitioner Part 1 (3)PRINCE2 Certification Training - Foundation & Practitioner Part 1 (3)
PRINCE2 Certification Training - Foundation & Practitioner Part 1 (3)Skillogic Solutions
 
MySQL Shell - The DevOps Tool for MySQL
MySQL Shell - The DevOps Tool for MySQLMySQL Shell - The DevOps Tool for MySQL
MySQL Shell - The DevOps Tool for MySQLMiguel Araújo
 
PRINCE2 Practitioner Course Training Part 4
PRINCE2 Practitioner Course Training Part 4PRINCE2 Practitioner Course Training Part 4
PRINCE2 Practitioner Course Training Part 4Skillogic Solutions
 
OSPX - Professional PostgreSQL Certification Scheme v20201111.pdf
OSPX - Professional PostgreSQL Certification Scheme v20201111.pdfOSPX - Professional PostgreSQL Certification Scheme v20201111.pdf
OSPX - Professional PostgreSQL Certification Scheme v20201111.pdfEqunix Business Solutions
 
PRINCE2 Certification Training - Foundation & Practitioner Part 6
PRINCE2 Certification Training - Foundation & Practitioner Part 6PRINCE2 Certification Training - Foundation & Practitioner Part 6
PRINCE2 Certification Training - Foundation & Practitioner Part 6Skillogic Solutions
 
What is Django | Django Tutorial for Beginners | Python Django Training | Edu...
What is Django | Django Tutorial for Beginners | Python Django Training | Edu...What is Django | Django Tutorial for Beginners | Python Django Training | Edu...
What is Django | Django Tutorial for Beginners | Python Django Training | Edu...Edureka!
 
PRINCE2 Sample Project by Frank Turley
PRINCE2 Sample Project by Frank TurleyPRINCE2 Sample Project by Frank Turley
PRINCE2 Sample Project by Frank TurleyFrank Turley
 
DevOpsDays - Pick any Three - Devops from scratch
DevOpsDays - Pick any Three - Devops from scratchDevOpsDays - Pick any Three - Devops from scratch
DevOpsDays - Pick any Three - Devops from scratchPete Cheslock
 
Latency analysis for your microservices using Spring Cloud & Zipkin
Latency analysis for your microservices using Spring Cloud & ZipkinLatency analysis for your microservices using Spring Cloud & Zipkin
Latency analysis for your microservices using Spring Cloud & ZipkinVMware Tanzu
 
Spring Framework 5.0による Reactive Web Application #JavaDayTokyo
Spring Framework 5.0による Reactive Web Application #JavaDayTokyoSpring Framework 5.0による Reactive Web Application #JavaDayTokyo
Spring Framework 5.0による Reactive Web Application #JavaDayTokyoToshiaki Maki
 
Enhancing Nuxeo with OpenAI by Maretha Solutions
Enhancing Nuxeo with OpenAI by Maretha SolutionsEnhancing Nuxeo with OpenAI by Maretha Solutions
Enhancing Nuxeo with OpenAI by Maretha SolutionsMariana Cedica
 

Similaire à PRINCE2 Practitioner Classroom slides - Sample (20)

Introduction to PRINCE2 Trainings
Introduction to PRINCE2 TrainingsIntroduction to PRINCE2 Trainings
Introduction to PRINCE2 Trainings
 
Python Development Company - Paragyte Technology
Python Development Company - Paragyte TechnologyPython Development Company - Paragyte Technology
Python Development Company - Paragyte Technology
 
Arkatay on pmbok guide 6th ed, seminar october 3 2017
Arkatay on pmbok guide 6th ed, seminar october 3 2017Arkatay on pmbok guide 6th ed, seminar october 3 2017
Arkatay on pmbok guide 6th ed, seminar october 3 2017
 
PRINCE2 Practitioner Course Training Part 16
PRINCE2 Practitioner Course Training Part 16PRINCE2 Practitioner Course Training Part 16
PRINCE2 Practitioner Course Training Part 16
 
Python Django tutorial | Getting Started With Django | Web Development With D...
Python Django tutorial | Getting Started With Django | Web Development With D...Python Django tutorial | Getting Started With Django | Web Development With D...
Python Django tutorial | Getting Started With Django | Web Development With D...
 
PRINCE2 Certification Training - Foundation & Practitioner Part 1 (3)
PRINCE2 Certification Training - Foundation & Practitioner Part 1 (3)PRINCE2 Certification Training - Foundation & Practitioner Part 1 (3)
PRINCE2 Certification Training - Foundation & Practitioner Part 1 (3)
 
MySQL Shell - The DevOps Tool for MySQL
MySQL Shell - The DevOps Tool for MySQLMySQL Shell - The DevOps Tool for MySQL
MySQL Shell - The DevOps Tool for MySQL
 
PRINCE2 Practitioner Course Training Part 4
PRINCE2 Practitioner Course Training Part 4PRINCE2 Practitioner Course Training Part 4
PRINCE2 Practitioner Course Training Part 4
 
04 oxygen
04 oxygen04 oxygen
04 oxygen
 
OSPX - Professional PostgreSQL Certification Scheme v20201111.pdf
OSPX - Professional PostgreSQL Certification Scheme v20201111.pdfOSPX - Professional PostgreSQL Certification Scheme v20201111.pdf
OSPX - Professional PostgreSQL Certification Scheme v20201111.pdf
 
PRINCE2 Certification Training - Foundation & Practitioner Part 6
PRINCE2 Certification Training - Foundation & Practitioner Part 6PRINCE2 Certification Training - Foundation & Practitioner Part 6
PRINCE2 Certification Training - Foundation & Practitioner Part 6
 
What is Django | Django Tutorial for Beginners | Python Django Training | Edu...
What is Django | Django Tutorial for Beginners | Python Django Training | Edu...What is Django | Django Tutorial for Beginners | Python Django Training | Edu...
What is Django | Django Tutorial for Beginners | Python Django Training | Edu...
 
PRINCE2 Sample Project by Frank Turley
PRINCE2 Sample Project by Frank TurleyPRINCE2 Sample Project by Frank Turley
PRINCE2 Sample Project by Frank Turley
 
DevOpsDays - Pick any Three - Devops from scratch
DevOpsDays - Pick any Three - Devops from scratchDevOpsDays - Pick any Three - Devops from scratch
DevOpsDays - Pick any Three - Devops from scratch
 
Latency analysis for your microservices using Spring Cloud & Zipkin
Latency analysis for your microservices using Spring Cloud & ZipkinLatency analysis for your microservices using Spring Cloud & Zipkin
Latency analysis for your microservices using Spring Cloud & Zipkin
 
Spring Framework 5.0による Reactive Web Application #JavaDayTokyo
Spring Framework 5.0による Reactive Web Application #JavaDayTokyoSpring Framework 5.0による Reactive Web Application #JavaDayTokyo
Spring Framework 5.0による Reactive Web Application #JavaDayTokyo
 
Enhancing Nuxeo with OpenAI by Maretha Solutions
Enhancing Nuxeo with OpenAI by Maretha SolutionsEnhancing Nuxeo with OpenAI by Maretha Solutions
Enhancing Nuxeo with OpenAI by Maretha Solutions
 
Ongoing management of your PHP 7 application
Ongoing management of your PHP 7 applicationOngoing management of your PHP 7 application
Ongoing management of your PHP 7 application
 
CAREL con MadCapTM FLARE
CAREL con MadCapTM FLARECAREL con MadCapTM FLARE
CAREL con MadCapTM FLARE
 
Introducing the new Cecomp TestPLUS!
Introducing the new Cecomp TestPLUS!Introducing the new Cecomp TestPLUS!
Introducing the new Cecomp TestPLUS!
 

Plus de Frank Turley

AgilePM 16: Planning
AgilePM 16: PlanningAgilePM 16: Planning
AgilePM 16: PlanningFrank Turley
 
AgilePM 11: The Process
AgilePM 11: The ProcessAgilePM 11: The Process
AgilePM 11: The ProcessFrank Turley
 
AgilePM 01: Introduction
AgilePM 01: IntroductionAgilePM 01: Introduction
AgilePM 01: IntroductionFrank Turley
 
AgilePM 03: Incremental delivery
AgilePM 03: Incremental deliveryAgilePM 03: Incremental delivery
AgilePM 03: Incremental deliveryFrank Turley
 
PRINCE2 Agile Guidance Preview
PRINCE2 Agile Guidance PreviewPRINCE2 Agile Guidance Preview
PRINCE2 Agile Guidance PreviewFrank Turley
 
PRINCE2 Timeline - 1 Slide
PRINCE2 Timeline - 1 Slide PRINCE2 Timeline - 1 Slide
PRINCE2 Timeline - 1 Slide Frank Turley
 
PRINCE2 Timeline Slides
PRINCE2 Timeline SlidesPRINCE2 Timeline Slides
PRINCE2 Timeline SlidesFrank Turley
 
PSM I Assessment Simulator
PSM I Assessment SimulatorPSM I Assessment Simulator
PSM I Assessment SimulatorFrank Turley
 
PSM-Professional Scrum Master-Lesson-01
PSM-Professional Scrum Master-Lesson-01PSM-Professional Scrum Master-Lesson-01
PSM-Professional Scrum Master-Lesson-01Frank Turley
 
An Introduction to PRINCE2 (book)
An Introduction to PRINCE2 (book)An Introduction to PRINCE2 (book)
An Introduction to PRINCE2 (book)Frank Turley
 

Plus de Frank Turley (10)

AgilePM 16: Planning
AgilePM 16: PlanningAgilePM 16: Planning
AgilePM 16: Planning
 
AgilePM 11: The Process
AgilePM 11: The ProcessAgilePM 11: The Process
AgilePM 11: The Process
 
AgilePM 01: Introduction
AgilePM 01: IntroductionAgilePM 01: Introduction
AgilePM 01: Introduction
 
AgilePM 03: Incremental delivery
AgilePM 03: Incremental deliveryAgilePM 03: Incremental delivery
AgilePM 03: Incremental delivery
 
PRINCE2 Agile Guidance Preview
PRINCE2 Agile Guidance PreviewPRINCE2 Agile Guidance Preview
PRINCE2 Agile Guidance Preview
 
PRINCE2 Timeline - 1 Slide
PRINCE2 Timeline - 1 Slide PRINCE2 Timeline - 1 Slide
PRINCE2 Timeline - 1 Slide
 
PRINCE2 Timeline Slides
PRINCE2 Timeline SlidesPRINCE2 Timeline Slides
PRINCE2 Timeline Slides
 
PSM I Assessment Simulator
PSM I Assessment SimulatorPSM I Assessment Simulator
PSM I Assessment Simulator
 
PSM-Professional Scrum Master-Lesson-01
PSM-Professional Scrum Master-Lesson-01PSM-Professional Scrum Master-Lesson-01
PSM-Professional Scrum Master-Lesson-01
 
An Introduction to PRINCE2 (book)
An Introduction to PRINCE2 (book)An Introduction to PRINCE2 (book)
An Introduction to PRINCE2 (book)
 

Dernier

Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpinRaunakKeshri1
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...fonyou31
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfAyushMahapatra5
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024Janet Corral
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...Sapna Thakur
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Disha Kariya
 

Dernier (20)

Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 

PRINCE2 Practitioner Classroom slides - Sample

  • 1. 1 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. PRINCE2® Practitioner Training Frank Turley Unbored.training PT0078 17/12/2017
  • 2. 2 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. IPR acknowledgements • PRINCE2® is a registered Trade Mark of AXELOS Limited. • ITIL® is a registered Trade Mark of AXELOS Limited. • M_o_R® is a registered Trade Mark of AXELOS Limited. • P3O® is a registered Trade Mark of AXELOS Limited. • MSP® is a registered Trade Mark of AXELOS Limited. • P3M3® is a registered Trade Mark of AXELOS Limited. • MoV® is a registered Trade Mark of AXELOS Limited. • MoP® is a registered Trade Mark of AXELOS Limited. • The Swirl logo™ is a Trade Mark of AXELOS Limited.
  • 3. 3 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Course Objectives • Learn what a project is and what is its context • Establish an understanding of the benefits of using PRINCE2 • Establish the purpose of the PRINCE2 themes • Learn about the roles and the management products used • Learn about the PRINCE2 principles • Establish the purpose, objectives and context of the PRINCE2 processes • Work on PRINCE2 project scenarios
  • 4. 4 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Target Audience • Project managers (or those who would like to become one) • Key staff involved in the design, development and delivery of projects – Project Board members – Team managers – Project assurance – Project support – Operational line managers/staff.
  • 5. 5 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Themes Review Break Tailoring Lunch Processes -1- Day 1 Lunch Practitioner Exam Day 2 Break Sample Exam + Review Processes -2- Sample Exam + Review
  • 6. 6 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. ABOUT THE COURSE
  • 7. 7 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The whole PRINCE2 Practitioner training is based on the assumption that you are familiar with the PRINCE2 Foundation concept PRINCE2 Practitioner Reminder… PRINCE2 Foundation
  • 8. 8 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. • PRINCE2 practitioner classroom slides • PRINCE2 process model diagram • PRINCE2 management product map • PRINCE2 timeline diagram • Official sample exam #1 and rationale • Official sample exam #2 and rationale • Management plaza sample exam #1 and rationale • Management plaza sample exam #2 and rationale • PRINCE2 practitioner training manual • “Managing Successful Projects with PRINCE2” PRINCE2 Practitioner Training Material
  • 9. 9 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. BUSINESS CASE PRINCE2 Themes Additional information for practitioner syllabus
  • 10. 10 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Business case: Management documents Delivery Teammanager Direction ProjectBoard Corp.. Corporate, programme management, customer Business case Benefits M.A. Business case Stage Boundary: Updated Management Projectmanager P I D SU process Benefits M.A. Updated Created Business case Project brief -- Outline BC Starting up a project Closing a project Benefits M.A. Develop business case Maintain business case Planning Initiation – 1st stage Delivery stages : Controlling a stage & stage boundary Closing a projectPre-Project Project mandate Business case documentation 1-Outline business case - Created by executive: part of the project brief 2-Business case 3-Benefits management approach 4-Updated business case 5-Updated benefits management approach (if necessary) 6-Update benefits management approach - Plan the post-project benefits review 7- business case (final update with cost data) 1 2 3 4 5 6 7 by Frank Turley mplaza.pm Version 1.2d Based on AXELOS PRINCE2® material. Reproduced under licence from AXELOS Limited. All rights reserved.
  • 11. 11 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Business case Summary of key points and ROI information: e.g. Give out pens to clients to increase contracts renewals Benefit: Reduce loss of maintenance contracts by 50% : €58,600 ROI: Return on Investment: Cost = €4,800: Gain = €58,600 1. Executive summary Examine options: Do nothing, do minimum, do something. E.g. Option 1: do nothing : Continue losing contracts: lose €84,000 Option 2: offer a calendar: • Value: not perceived as a quality item Option 3: offer pen that clients will continue to use: • Value: Contacts will hold on to the pens • Believe this will have the effect to reduce loss 3. Business options List measureable benefits that are aligned to corporate strategy e.g. Reduce loss of maintenance contracts by 50% : €42,000 (each year) 4. Expected benefits Date: Document: Project: Author: Timescales for project plan and benefits realization. E.g. Project start: March 5th, Project End: May 31st (12 weeks) E.g. Measure benefits on 28/12/2017 and 31/05/2018 6. Timescales Summary of the key risks (taken from risk register) e.g. Due to the variety of possible pens, there is a threat that we can choose the wrong pen which the majority of clients will not keep using the pen as expected. 9. Major risks List reasons for the project and impact on corporate strategy. e.g. Build better relationship with clients and reduce the loss in the renewal of maintenance contracts from 10% to 5%. CopyWorld has 4,200 maintenance contracts with an average profit of €200 per contract = €840,000. 2. Reasons List dis-benefits (seen as negative by some stakeholders) 5. Expected dis-benefits Include project (Project plan) and maintenance costs e.g. Pen costs: €10 by 400 pens = €4,000 e.g. Other project costs: €800 7. Costs Document investment appraisal – show project value. E.g. • Project cost: €4,800 • Expected gain: €58,400 • Time : 1 year • ROI: 1120.80% (to update) 8. Investment appraisal Business case (sample from Pen Project) Based on AXELOS PRINCE2® material. Reproduced under licence from AXELOS Limited. All rights reserved.
  • 12. 12 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Pre-project Initiation stage Subsequent delivery stages Final delivery stage Post-project Verify outline business case Verify updated business case Develop business case Maintain business case Verify detailed business case Answer: • First verification point by project board is at the end of SU process • Second verification point by project board is at the end of IP process • Next verifications points are at the end of each stage • Last verification point for project board is at the end of the project Question: Where do you verify the business case? Business case Verifying the business case Based on AXELOS PRINCE2® material. Reproduced under licence from AXELOS Limited. All rights reserved.
  • 13. 13 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. 1. Created by project manager in the initiation stage 2. Information is provided by senior user 3. Project board approves the benefits management approach 4. Check for realized benefits at the end of each stage 5. Plan benefits review after project (Post-project) 6. Check for realized benefits (Post-project) • Some projects check for realized benefits during the project: • Example: New CRM functionality released to users after each stage • The senior supplier is responsible for creating the products to achieve the benefits • CPC Mgmt do the benefit review after the project. Eg: 6, 12, 18, 24 months • Project manager • Senior user • Project board • Project manager • Project manager • CPC • A plan that defines how & when benefits are measured • A plan to review the benefits è benefits management approach Benefits management approach steps: Pre-project Initiation stage Subsequent delivery stages Final delivery stage Post-project Create BMA Check benefits Approve BMA Check benefits Who: PM PM Corp… Check benefits Plan post reviews 3 1 2 4 5 6 Business case Benefits management approach
  • 14. 14 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. ORGANIZATION PRINCE2 Themes Additional information for practitioner syllabus
  • 15. 15 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Delivery Team manager Direction Project Board Corp.. Authorize initiation Authorize the project Authorize a stage or exception plan Give ad hoc direction Auth. project closure Directing a project Initiation – 1st stage Closing a project Corporate, programme management, customer End stage reportCommunication M.A. Stage Boundary: Created Management Project manager -- Team manager assists the project manager -- Created once during project (can be updated) -- Created or updated once per stage -- Created or updated many times during a stage -- Once per work package -- Many per work package P I D SU process Pre-Project CP is the last part of the last stage Created Project brief Assists with Planning * Initiation – 1st stage Delivery stages : Controlling a stage & stage boundary Closing a projectPre-Project - PMT Starting up a project Closing a project Delivery Stages : Controlling a stage & stage boundary PMT - roles Organization documentation 1-PMT (Project management team) - This is part of the project brief 2-Communication management approach - Guideline for communication during project 3-PMT role descriptions 4-End stage report - Performance review and change suggestions to PMT 1 2 3 4 Organization: Management products Based on AXELOS PRINCE2® material. Reproduced under licence from AXELOS Limited. All rights reserved.
  • 16. 16 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Project management team Delivery Management Direction Senior user Executive Senior supplier Corporate, programme management, customer Project manager Team manager Change authority Project support Project assurance Business Assurance User Assurance Supplier Assurance PROJECT ANAGEMENT TEAM Organization: Based on AXELOS PRINCE2® material. Reproduced under licence from AXELOS Limited. All rights reserved.
  • 17. 17 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Organization • Monitors all aspects of the project’s performance and products • Independent of the project manager • Gives advice and guidance to the project manager Project assurance Business assurance User assurance Supplier assurance Project assurance Risks are controlled, right people are involved in quality inspection Business assurance Solution provides value for money, payments are authorized User assurance Solution will meet user needs, advise on changes Supplier assurance Review product descriptions, monitor production risks Project assurance
  • 18. 18 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Organization Introduction Purpose, objectives and scope of the strategy Communication Procedure Communication methods to be used Tools and Techniques Communication tools, preferred techniques, steps in the communication process Records Required records and where they will be stored Reporting Communication process (purpose, timing, recipients) Timing of communication activities Timing of formal communication activities and performance audits for the methods Roles and responsibilities Responsibilities of the aspects of the communication process Stakeholder analysis Identification of the interested parties, relationship status, interfaces Information needs for interested parties Information to/from the stakeholders; frequency, means and format of communication Communication management approach
  • 19. 19 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. This document describes how communication will be done during the project: It is based on the standard strategy document for all projects. 1. Introduction A description of communication methods to be used during the project plus any variance from the corporate standards. e.g. The PM is responsible for all internal communication and will report each week on the project board using a highlight report. The Sales Manager is responsible for all external communication. 2. Communication Procedure Define when formal communication activities will take place. e.g. The PM will meet with the project board each two weeks. 5. Timing of communication activities Communication management approach Date: Document: Project: Author: 7. Roles & responsibilities 8. Scales: Priority & Severity List the communication tools and techniques that will be used. e.g. The PM will use the internal portal site for all internal communication and project documents. The Sales Manager will use a newsletter and site visits to communicate with clients. 3. Tools and techniques Define the record(s) that will be used to log communication activities and the location that they will be kept. e.g. A log to keep track of external communication. 4. Records 6. reports / Stakeholder Matrix Highlight report Report Name Timing Recipients Weekly Project board End stage report End of stage Project board End project report End of project Project board Issue report Anytime CA/Project board Electronic newsletter Once Clients Project board Inform the rest of the management team Project manager All internal communication (project team) Create the required PRINCE2® documents Senior user Communicate with clients Priority Use MoSCoW (Must, Should, Could, Won’t..) Severity levels 1 = project manager, 2 = project board Clients Stakeholders Current Relationship Desired Relation 90% Good 95% Good Sales Team Excellent Excellent Good Good 9. Stakeholder Analysis Attitude Neutral Support Co. Mgmt Support Organization Based on AXELOS PRINCE2® material. Reproduced under licence from AXELOS Limited. All rights reserved.
  • 20. 20 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. QUALITY PRINCE2 Themes Additional information for practitioner syllabus
  • 21. 21 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Delivery Teammanager Direction ProjectBoard Corp.. Corporate, programme management, customer Team plan Next stage planQuality M.A. Project plan or exception plan Controlling a stage Stage Boundary: Created Products are created here Update register after quality check. Management Projectmanager Work packages -- Team manager is also responsible -- Created once during project (can be updated) -- Created or updated once per stage -- Created or updated many times during a stage -- Once per work package -- Many per work package P I D SU process Project brief Quality register Assists with Planning * Initiation – 1st stage Delivery stages : Controlling a stage & stage boundary Closing a projectPre-Project - PPD * Product descriptions Quality register Starting up a project Closing a project 1: Quality planning 2: Quality control Updated Acceptance criteria (Acceptance records) 1-Project product description (PPD) 2-Quality management approach 3-Product descriptions 4-Quality register (record quality activities) 5-New products can be defined 6-Quality register is updated (pass or fail) 7-Acceptance criteria (handover) 51 2 3 4 6 7 Quality: Management products Based on AXELOS PRINCE2® material. Reproduced under licence from AXELOS Limited. All rights reserved.
  • 22. 22 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Delivery Teammanager Pre-Project – SU Initiation – 1st stage Quality register – contents • List all products names + IDs (from Plan) • List quality method • Quality reviewer & approver • Expected delivery dates • Target & actual quality review dates Management Projectmanager Project brief PPD QMS Project plan Product Descriptions Acceptance criteria Project product description (PPD) Quality requirements from Customer Customer’s quality expectations Quality responsibilities Quality information in product descriptions Quality criteria and tolerances Quality methods Quality planning – 6 Steps Quality register : Plan Quality Activities 1 2 3 4 5 6 Quality management approach Quality planning steps 1. Understand - customer’s quality expectations 2. Defining the project’s acceptance Criteria 3. Add to project product description 4. Prepare the quality management approach 5. PD’s with quality information 6. Set the quality register (record quality activities) Questions: • When does PRINCE2® first think about quality? • Where does the quality data come from? • What is the value of the QMS? • Why is a quality register part of quality planning? Quality: Planning Steps Based on AXELOS PRINCE2® material. Reproduced under licence from AXELOS Limited. All rights reserved.
  • 23. 23 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. A.21 Project product description Title Purpose Composition (parts) Derivation (tools, design plans) Development skills required Customer’s quality expectations Acceptance criteria Project level quality tolerances Acceptance method Acceptance responsibilities Identifier Title Purpose Composition Derivation Format and presentation Development skills required Quality criteria Quality tolerance Quality method Quality skills required Quality responsibilities A.17 Product description Quality Product quality information
  • 24. 24 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Quality Introduction Purpose, objectives and scope of the strategy Quality Management Procedure Quality management procedure to be used (quality planning and control, assurance activities) Tools and Techniques Any quality management systems or tools to be used and preferred techniques Records Types of required quality records , where they will be stored and the format of the quality register Reporting Reports on the quality management (purpose, timing and recipients) Timing of communication activities Timing of formal quality management activities such as audits Roles and responsibilities Responsibilities for quality management activities, including quality responsibilities from CPC CPC: Corporate, programme management, customer Quality management approach
  • 25. 25 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Producer Quality Reviewer Approval 16 31 Wall Insulation Inspection JV WP RT 28/9 2/10 10/10 10/10 11/10 Pass links 17 32 Heating Furnace Inspection TM TL RT 8/10 14/10 21/10 27/10 Fail links 18 33 Heating Furnace Performance test MP TL RT 17/10 21/10 27/10 19 34 Kitchen Fittings Inspection AM OH BD 1/11 5/11 14/11 Quality ID Product ID Quality Reviewers Quality Method Product Name Producer Approver Target Quality Review Date Actual Quality Review Date Actual Approval Date Target Approval Date Result Records Quality Dates Approval Dates * * * * * * Data is taken from the project, stage, team plan (schedule) PD PD PD Data is taken from the product descriptions (project plan) Production date ** Steps are: Results of Quality Tests + Links Quality Quality register Based on AXELOS PRINCE2® material. Reproduced under licence from AXELOS Limited. All rights reserved.
  • 26. 26 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. • Quality assurance reports to CPC • Project assurance is the responsibility of the project board Quality Quality Assurance Corporate, programme management, customer DeliveryManagementDirection Senior User Executive Project manager Project assurance Business assurance User assurance Supplier assurance Team manager QA is focused on the: • Quality process of the project • Company standards are met • Risk management is done correctly • Communication is done correctly • Business case is verified • Issues are tracked correctly • Etc.. This role has nothing to do with checking the quality of the products after they are produced. Senior supplier Change authority Project support Quality assurance Based on AXELOS PRINCE2® material. Reproduced under licence from AXELOS Limited. All rights reserved.
  • 27. 27 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Quality assurance • Interested to see that all projects are following company standards • This role is defined in the PRINCE2® manual Quality Tester • This role is NOT defined in the PRINCE2® manual • They test the products before they are returned to the project manager • The following information is defined in each product description • Quality method (how the testing will be done) • Quality skills required • Quality responsibilities (who does what) Quality Quality assurance vs Quality testers
  • 28. 28 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. PLANS PRINCE2 Themes Additional information for practitioner syllabus
  • 29. 29 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Delivery Teammanager Direction ProjectBoard Initiation – 1st stage Delivery stages / controlling a stage Closing a project Corporate, programme management, customer Team plan SB: Next stage plan IS plan Project plan or exception plan . Updated Created SB: Project plan - Optional - Non PRINCE2® Format Management Projectmanager Updated -- Once during project -- Once per stage -- Many times during stage -- Once per work package -- Many per work package Project plan PFD The path to planning 1-Create project product description (PPD) 2-IS Plan (Plan for initiation stage) 3-Product based planning - PBS: Product breakdown structure - PDs: Product descriptions - PFD: Product flow diagrams 4-Project plan 5-Next stage plan 6-Exception plan (if needed) 7-Update project plan 8-Create team plan (optional) 9-Update project plan (show complete) Product Base Planning PBS PDs PPD 2 3 4 1 6 5 8 7 9 Plans: Management products Based on AXELOS PRINCE2® material. Reproduced under licence from AXELOS Limited. All rights reserved.
  • 30. 30 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Stage plan - example Brief introduction / description of a project plan e.g. This is the plan for the initiation stage of the Pen Project 1. Plan description What must be and remain in place for the plan to succeed e.g. Sales Manager provides the necessary time for the project e.g. Twenty sales persons will be available to evaluate the pens 2. Plan prerequisites Attached: Project product description 9. Products description(s) Date: Document: Project: Pen Project Author: Project manager e.g. A business gift company will have to provide the pens to evaluate and the 400 pens after chosing. 3. External dependencies Lists the assumptions on which the plan is based. e.g. Internal recourses will not be charged to the project. 4. Planning assumptions List the lessons that have value for this plan. e.g. Allow buffer time for delivery of pens (lessons log) e.g. Investigate the ISO standard for pens: ISO 12757-2 5. Lessons incorporated How the plan will be monitored and controlled e.g. The PM will use the standard PRINCE2® documents. e.g. A highlight report will be sent at the end of week 1 to the PB. 6. Monitoring & control e.g. Initiation stage budget: € 200 (internal people time is not charged) e.g. Risk budget: €0, Change budget: €0 7. Budgets e.g. Time: +- 50% : Cost: +- 50% : Quality: +- 10% : Scope: 0% 8. Tolerances 10. Schedule (Example) 4th 5th 6th 7th 8th 11th 12th 13th 14th 15thDeliverables - March Strategy documents WBS Product descriptions Risks & issues Project plan Benefits M.A. Business case PID Next stage plan 1 hr 8 hrs 1 hr 4 hrs 2 hrs 2 hrs 4 hrs 3 hrs 2 hrs Plans Based on AXELOS PRINCE2® material. Reproduced under licence from AXELOS Limited. All rights reserved.
  • 31. 31 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. • Three levels of plans: project, stage and team (optional) • Project product description – Composition lists the major products that the project will produce – Also includes customer’s quality expectations and acceptance criteria – Each product listed may also have a product description • Product descriptions – Details requirements and quality information – A product breakdown structure will be used to identify all products – Product descriptions are created and updated in IP and SB processes – Includes quality criteria, tolerances, producer and quality method Plans Other Key Points: Plans
  • 32. 32 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. RISK PRINCE2 Themes Additional information for practitioner syllabus
  • 33. 33 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Delivery Team manager Direction Project Board Corp.. Authorize initiation Authorize the project Authorize a stage or exception plan Give ad hoc direction Auth. project closure Directing a project Initiation – 1st stage Closing a project Corporate, programme management, customer CS: Highlight Risk M.A. Business case Controlling a stage Business case Stage Boundary: Updated Management Project manager -- Team manager assists the project manager -- Created once during project (can be updated) -- Created or updated once per stage -- Created or updated many times during a stage -- Once per work package -- Many per work package P I D SU process Pre-Project CP is the last part of the last stage CS: Risk register Project brief Daily log Risk register Assists with Planning * Initiation – 1st stage Delivery stages : Controlling a stage & stage boundary Closing a projectPre-Project -- Outline BC Updated Starting up a project Closing a project Delivery stages : Controlling a stage & stage boundary 1-Outline BC – lists major risks 2-Risks stored in daily log in SU process 3-Business case (major risks) 4-Risk M.A. (guideline for risks) 5-Risk register (all risks are listed here) 6-Update of major risks 7-Include major risk information 8-Update risks in the risk register 3 1 2 4 5 76 8 Risk: Management products Based on AXELOS PRINCE2® material. Reproduced under licence from AXELOS Limited. All rights reserved.
  • 34. 34 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Risk Risk management approach Introduction Purpose, objectives and scope, who is responsible Risk management procedure Defining the steps of the risk management procedure Tools and techniques Risk management systems or tools to be used Records Composition and format of the risk register and other records Reporting Reports to be produced, including their purpose, timing and recipients Timing of risk management activities Timing of formal risk management activities like end stage assements Roles and responsibilities Roles and responsibilities for risk management activities Scales Defining scales for estimating probability and impact, e.g. low, medium, high Proximity How proximity for risks is to be assessed Risk categories Risk categories to be used Risk response categories Risk response categories to be used Early warning indicators Any indicators to be used to track critical aspects of the project Risk tolerance Threshold levels of risk exposure Risk budget How the risk budget will be used
  • 35. 35 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Risk register : Sample Date: Document: Project: Pen Project Author: Project manager ID Risk Author Date register Risk Category Risk Description Probability x Impact Proximity Response Category Status Risk Owner Risk Actionee 1 P Smith 6/3/18 Ordering A risk that pens will be delivered 2-4 weeks later which will impact the time of the project < €1000 Medium Reduce Active P Smith J Bell 2 S. Kelly 7/3/18 Product 50% users may not like the pens and therefore not keep using them which result in 50% less benefits € 29,000 Medium Reduce Active S. Kelly R Clark 3 S. Kelly 9/3/18 Product Some sales people may not distribute the pens as intended, therefore the benefits will not be realized for these users € 5,600 Medium Reduce Active S. Kelly S. Kelly This risk register is take from the sample PRINCE2® Pen project Project Name Pen Project Risk / Impact Project No 008 High risk > € 7,500 Project manager Rose Clark Medium > € 1000 Project executive John King Low risk < € 1000 Amount is related to the value of the expected benefits Expected gain is: €58,400 The response text is not included in this example Risk Based on AXELOS PRINCE2® material. Reproduced under licence from AXELOS Limited. All rights reserved.
  • 36. 36 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Risk identifier Risk author Date registered Risk category Risk description Probability Proximity Risk response categories Risk response Risk status Risk owner Risk actionee Provides records of identified risks including status, history, impact… Unique reference for each risk Person who raised the risk Date identified / registered Choose category: e.g. Schedule, Quality, Legal, … Description: Due to… there is a risk…. Impacts are…. Probability, impact and expected value How close in time in relation to the project Choose threat or opportunity responses List action to resolve the risk Normally “Active” or “Closed” Person responsible for managing the risk Person who will implement actions listed in response Risk Risk register
  • 37. 37 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Inherent risk: • The identified and assessed risk Residual risk: • Leftover impact after a response was implemented Secondary risk: • New risk caused by the implementation of a response Inherent, secondary and residual risks Risk Risk planning
  • 38. 38 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Avoid a threat • Eliminate the impact or prevent it from happening (probability zero) Reduce a threat • Proactive • Reduce the probability of the event • Reduce the impact of the event Prepare contigent plans • Reactive and affects only the impact • Reduces the impact • A plan of actions implemented to reduce the impact • Preparing plans now, but not taking action now. Threats risk responses Risk
  • 39. 39 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Transfer the risk • A form of “reduce” response • Reduces financial impact only • Some of the impact becomes the responsibility of a third party • Mostly on a contractual basis Accept the risk • Organization ‘takes the chance’ that the risk will occur • And with full impact if it did. Share the risk • Application of a pain/gain formula • Within preset limits, both parties share the pain or the gain Threat risk responses Risk
  • 40. 40 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Exploit an opportunity • Ensuring that the impact will happen • Ensuring that the impact will realize Enhance an opportunity • Enhance the probability of the event occuring • Enhance the impact of the event Transfer the risk • Transfer can apply to opportunities • Not a commonly used option for opportunities Opportinity risk responses Risk
  • 41. 41 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Share the risk • Application of a pain/gain formula • Within preset limits, both parties share the pain or the gain Accept the risk • Organization ‘takes the chance’ that the risk will occur • And with full impact if it did. Prepare contigent plans • We will accept the risk for now, • Make a plan for what we’ll do if the situation changes Opportinity risk responses Risk
  • 42. 42 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. CHANGES PRINCE2 Themes Additional information for practitioner syllabus
  • 43. 43 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Approve Reject Defer decision Request more info Ask for exception plan Request for Change Project board (Change authority) PM may decide on small changes So the PM has some change authority Grant a concession Instruct it be resolved Defer decision Request more info Ask for exception plan Off-Specification Project board (Change Authority) Out of specification with product description Problem / Concern Provide guidance Ask for exception plan Project board PM may decide if with tolerance PM may also be able to handle issues e.g. small issues < €500 The PM can have some change authority responsibility New Issue If an issue will bring the stage/project out of tolerance, then the issue report becomes an exception report Issue report Issue report Issue report Normally from user Normally from supplier Good or bad news Change Based on AXELOS PRINCE2® material. Reproduced under licence from AXELOS Dealing with project issues Based on AXELOS PRINCE2® material. Reproduced under licencefrom AXELOS Limited. All rights reserved.
  • 44. 44 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Project board / Change authority Enter or update in Daily log or issue register or issue report Request for advice Request for advice / Exception report I) Determine • Issue Type • Severity • Priority II) Add to • Daily log? • Issue register? I) Assess impact on • Project objectives (6 performance targets) • Business case • Project plan II) Check • Severity (Level) • Priority (MoSCoW) Propose options Identify options Evaluate options Recommend options Decide I) Escalate if beyond delegated authority II) Approve reject or defer option PM / CA / Board may decide PM Implements I) Take corrective action - New/Update work package - Or create exception plan II) Update records and plans (status) Capture Examine Propose Decide Implement Change Issue and change control procedure Based on AXELOS PRINCE2® material. Reproduced under licence from AXELOS Limited. All rights reserved.
  • 45. 45 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Delivery Team manager Direction Project Board Corp.. Initiation – 1st stage Closing a project Project mandate Corporate, programme management, customer Issue reportsChange control approach Management Project manager -- Team manager assists the project manager -- Created once during project (can be updated) -- Created or updated once per stage -- Created or updated many times during a stage -- Once per work package -- Many per work package P I D SU process Pre-Project Updated Issue register Daily log Configuration item records (CIR) CIR docs (cmdb) Daily log Issue registers * Initiation – 1st stage Delivery stages : Controlling a stage & stage boundary Closing a projectPre-Project Updated Starting up a project Closing a project Delivery stages : Controlling a stage & stage boundary CIR docs Product status account Product status account 1 2 2 2 3 4 4 5 5 3 6 Change: Management products Based on AXELOS PRINCE2® material. Reproduced under licence from AXELOS Limited. All rights reserved.
  • 46. 46 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. 1. Change control approach – Guideline to issue, change and configuration management 2. Configuration items records – One record per product – Contains meta data for each product 3. Product status accounts – Report on the status of one or more products – Usually created during SB & CP processes 4. Daily log – Used for informal issues and all issues during the SU process 5. Issue register – Container for all issues (changes, concerns and positive issues) that are handled formally 6. Issue reports – A detailed report for one issue – An issue report which describes an out of tolerance issue is an exception report …See also previous slide Change Management products to control issues and configuration
  • 47. 47 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Change Request for Change Approved Use the change budget Use additional budget De-scope the project How to fund the resolution of issues... Tolerances should not be used to fund requests for change
  • 48. 48 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Change Off- specification Grant a concession No immediate action is required How to fund the resolution of issues...
  • 49. 49 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Change Problem /Concern Provide guidance Ask for an exception plan Resolve the issue by relaxing tolerances? How to fund the resolution of issues...
  • 50. 50 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. PSA: Product status account CIR: Configuration item records Change Change control approach Introduction Purpose, objectives and scope, identifies who is responsible for the strategy Configuration management procedure Defines the configuration management procedure to be used Issue and change control procedure Defined the issue and change control procedure to be used Tools and techniques Any configuration management systems or tools to be used Records Composition and format of the issue register and CIR Reporting Composition, format, purpose, timing and recipients of issue report and PSA; reviewing the performance of the procedures Timing of configuration and issue and change control activities Timing of formal activities, e.g. configuration audits Roles and responsibilities Who is responsible for the procedures, including CPC roles. Describes change authority and change budget Scales for priority and severity For prioritizing requests for change and off-specifications; determining decision makers for severity and priority levels
  • 51. 51 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Change Issue report Issue identifier Unique reference for every issue, same as the one in Issue register Issue type Type of issue being recorded Date raised Date issue was raised Raised by Person or team who raised the issue Issue report author Person or team who created the issue report Issue description Issue description in terms of its cause and impact Impact analysis Detailed analysis of the impact Recommendation PM’s recommendation to solve the issue Priority Given in project’s chosen scale, re-evaluated after impact analysis Severity Given in project’s chosen scale, indicates the management level who will decide on the issue Decision The decision Approved by Who made the decision Decision date Date of decision Closure date When the issue is closed
  • 52. 52 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. PROGRESS PRINCE2 Themes Additional information for practitioner syllabus
  • 53. 53 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. • Authorizations – Initiation – Project – Each stage – Project closure • Progress updates – Highlight reports – End stage reports • Exceptions and changes – Exception reports – Issue reports – Exception plans What does the project board use to control the project? Receive Progress reports from PM Receive from PM at end of stage From PM if expected to go out of tolerance If out of tolerance or need advice When requested by project board Decision point 1 Decision point 2 Decision point for each stage Decision point Last Progress Project board controls
  • 54. 54 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. • Authorizations – Agreeing and authorizing work packages and work package tolerances • Progress updates – Checkpoint reports • Exceptions and changes – PM uses project registers and logs to review progress and identify issues and risks that may need to be resolved What does the project manager use to control the project? They authorize when they are sure that the products will be created as expected Regular report from team manager to the project manager Eg: Compare planned dates vs actuals Eg: Sort Issues & Risks by most critical Deal with Issues or Escalate Progress Project manager controls
  • 55. 55 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Delivery Team manager Direction Project Board Initiation – 1st stage Closing a project Management Project manager SU process Pre-Project Delivery stages : Controlling a stage & stage boundary Team plan Next stage plan IS plan Project plan Benefits M.A. or exception plan Stage Boundary: Updated Stage Boundary: Created Project plan Updated -- Team manager assists the project manager -- Created once during project (can be updated) -- Created or updated once per stage -- Created or updated many times during a stage -- Once per work package -- Many per work package P I D Benefits M.A. Updated Project plan CS: Risk register CS: Issue register CS: Daily log CS: Product status account Daily log Risk, quality, issue registers Assists with Planning * Quality register Controlling a stage Starting up a project Project controls Which products are used by the PM to review progress against plan? Progress: Management products Based on AXELOS PRINCE2® material. Reproduced under licence from AXELOS Limited. All rights reserved.
  • 56. 56 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Delivery Teammanager Direction ProjectBoard Checkpoint reports Initiation – 1st stage Closing a project End stage report CS: Highlight Controlling a stage Created Stage Boundary: Created Product delivery: Created Management Projectmanager Pre-Project End project report Created Closing a project Delivery stages : Controlling a stage & stage boundary Which reports are used to report progress? • Checkpoint report • Highlight report • End stage report • End project report Which products are used to set and report progress? CS: Exception reportProject controls Part of the PID - Tolerances - # of stages - Length of stages - Frequency reports Project controls define how the project will be controlled Progress: Management products Based on AXELOS PRINCE2® material. Reproduced under licence from AXELOS Limited. All rights reserved.
  • 57. 57 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Progress Highlight report Date Date of the report Period Period covered by this highlight report Status summary Overview of the status of the stage at this time This reporting period • WP’s – pending authorization, in execution and completed • Products completed • Products planned but not started or completed • Corrective actions taken Next reporting period • WP’s – to be authorized, in execution and to be completed • Products to be completed • Corrective actions to be completed Project and stage tolerance status How the project and the stage performing against tolerances Requests for change Requests for change received in this period Key issues and risks Summary of actual issues and risks Lessons report A review of what went good/bad and recommendations for CPC
  • 58. 58 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Progress End stage report Project manager’s report Summary of the stage performance Review of the business case Summarizing the validity of the BC: Deviations from BC, aggregated risk exposure Review of project objectives How the project performed against its targets, review of strategies and controls Review of stage objectives How the stage performed against its targets Review of team performance Providing recognition for good performance Review of producs Quality records Quality activities planned and completed Approval records Products planned for completion Off-specifications Products with off-specifications and concessions granted Phased handover Client confirmation that they are ready to receive the release Summary of follow-on action recommendations Asking for advice who will receive the recommended actions Lessons report Review of what went good/bad, recommendations for CPC Issues and risks Summary of current issues and risks Forecast PM’s forecast for the project and the stage against targets and tolerances
  • 59. 59 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. TAILORING
  • 60. 60 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Tailoring PRINCE2 Tailoring vs Embedding Tailoring... ... Adapting PRINCE2 to the context of a specific project ... Done by the project management team Embedding... ... Adopting PRINCE2 in the organization ... Done by the organization
  • 61. 61 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. • TAILORING focuses on… – Adapting the themes (through the strategies and controls) – Incorporating specific terms and language – Revising the product descriptions for the management products – Revising the role descriptions for the PRINCE2 project roles – Adjusting the processes to match the above. Tailoring PRINCE2 Tailoring vs Embedding • EMBEDDING focuses on… – Process responsibilities – Scaling rules/guidance (e.g. score card) – Standards (templates, definitions) – Training and development – Integration with business processes – Tools & process assurance
  • 62. 62 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. • PRINCE2® assumes that there will be: – A customer specifying the desired result and probably pay for the project – A supplier providing the resources and skills to deliver that result. • If the relationship between customer and supplier is a commercial one, then there are at least two sets of: – Reasons for undertaking the project (own reasons) – Management systems (project methods) – Governance structures (may require disclosure of project data) – Corporate cultures (e.g. formality, risk taking) Tailoring PRINCE2 Customer/Supplier Environment
  • 63. 63 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. • Two business cases – one for the Customer and one for the Supplier projects Customer business case • Benefits to the customer against the costs and risks • Costs include internal costs (customer project resources, ongoing operations and maintenance resources) and external costs (supplier goods and services) • Risks should include project risks and ongoing operations risks Supplier business case • Covers the supplier part of the customer project • Should also consider how the project will affect the supplier’s sales and market objectives Tailoring PRINCE2 Commercial Customer/Supplier Environment Business case
  • 64. 64 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. • Who should be the senior supplier in the customer project? – Is it appropriate to have a senior supplier from an external organization? – What happens if there are multiple suppliers? – Would it be ok to work with a temporary senior supplier for a procurement stage? – Would the person responsible for the performance of the supplier be a good choice as the senior supplier? • Who will supply the project manager? Customer or supplier? – Normally from the customer organization, supplier project manager will the team manager in the customer project – Supplier can provide the project manager (Project assurance will be critical) Tailoring PRINCE2 Commercial Customer/Supplier Environment Organization
  • 65. 65 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. • Quality management approach – Use the customer’s quality management system? – Use the supplier’s quality management system? – Or use a combination of both? Tailoring PRINCE2 Commercial Customer/Supplier Environment Quality
  • 66. 66 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. • Awarding the contract – Purchase orders and milestone payments aligned to stages – Consider break-points in the contracts if project closes prematurely Tailoring PRINCE2 Commercial Customer/Supplier Environment Plans
  • 67. 67 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. • Risk register – Need separate risk registers? – Some risks may be unique to one party – With a joint risk register • Determine whose risk it is • Assign an appropriate risk owner Tailoring PRINCE2 Commercial Customer/Supplier Environment Risk
  • 68. 68 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. • Change control approach – Align the change control procedures – Align the change provisions (change budget) • Change budget – If a change dudget exists, • Align customer’s purchasing procedures with supplier’s business approval procedures Tailoring PRINCE2 Commercial Customer/Supplier Environment Change
  • 69. 69 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. • Reviewing and reporting – Align both organizations’ governance requirements Tailoring PRINCE2 Commercial Customer/Supplier Environment Progress
  • 70. 70 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. • Customer’s processes – Unlikely that tailoring is required • Supplier’s processes – Starting up a project process • Will take place pre-contract • Probably be in response to the customer’s request for a proposal – Initiating a project process • Assessing the desirability and viability of the sale (pre-contract) • Process ends only after customer authorizes the project • Contract negotiations are managed through change control Tailoring PRINCE2 Commercial Customer/Supplier Environment Processes
  • 71. 71 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. • Contracts – Liabilities in case of failure to fullfil obligations • Project initiation documentation – Focuses on ensuring that obligations are fullfilled – Can be part of the contract • But then each change may require a legal review • Work package – Legally binding contract – Include terms and conditions Tailoring PRINCE2 Commercial Customer/Supplier Environment Management Products
  • 72. 72 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. PROCESSES
  • 73. 73 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. • Management product map – Overview of all PRINCE2® management products • Provide 3 summary slides for each process 1. Process activity slides 2. Process input / output slide 3. Process responsibility slides Processes Introduction Processes
  • 74. 74 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Processes: Management products mapDelivery Teammanager Direction ProjectBoard Corp.. Authorize initiation Authorize the project Authorize a stage or exception plan Give ad hoc direction Auth. project closure Checkpoint reports Directing a project Initiation – 1st Stage (Planning) Closing a project Project mandate Corporate, programme management, customer End stage report CS: Highlight report Team plan CS: Issue/exc. reportsNext stage plan IS plan Communication M.A. Change control approach Quality M.A. Risk M.A. Business case Project plan Benefits M.A. or exception plan Controlling a stage Created Business case Stage Boundary: Updated Stage Boundary: Created Project plan Product delivery: Created Updated Management Projectmanager Work packages -- Team manager is also responsible -- Created once during project (can be updated) -- Created or updated once per stage -- Created or updated many times during a stage -- Once per work package -- Many per work package P I DProject controls PMT – roles Project approach Pre-Project End project report Follow on actions Lessons report Draft closure not. Benefits M.A. Updated Created Business case Project plan CS: Risk register CS: Issue register CS: Lessons log CS: Daily log CS: CIR Project brief CIR docs (cmdb) Lessons log Daily log Risk, Quality, Issue registers + Acceptance Records TM assists with planning * Initiation – 1st stage Delivery stages : Controlling a stage & stage boundary Closing a projectPre-Project -- Outline BC -- PPD -- Approach -- PMT PBS PDs PFD * * Quality register Controlling a stage Updated Starting up a project Closing a project Delivery stages : Controlling a stage & stage boundary e.g.80% New requirements? Issue/Risk register Conf. Item Records PRINCE2® is a registered trade mark of AXELOS Limited. The Swirl logo™ is a trade mark of AXELOS Limited. Stage Boundary: Created Product status account Benefits M.A. Based on AXELOS PRINCE2® material. Reproduced under licence from AXELOS Limited. All rights reserved.
  • 75. 75 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Processes: Management products mapDelivery Teammanager Direction ProjectBoard CPC Authorize initiation Authorize the project Authorize a stage or exception plan Give ad hoc direction Auth. project closure Checkpoint reports Directing a project Initiation – 1st Stage (Planning) Closing a project Project mandate Corporate, programme management, customer End stage report CS: Highlight report Team plan CS: Issue/exc. reportsNext stage plan IS plan Communication M.A. Change control approach Quality M.A. Risk M.A. Business case Project plan Benefits M.A. or exception plan Controlling a stage Created Business case Stage Boundary: Updated Stage Boundary: Created Project plan Product delivery: Created Updated Management Projectmanager Work packages -- Team manager is also responsible -- Created once during project (can be updated) -- Created or updated once per stage -- Created or updated many times during a stage -- Once per work package -- Many per work package P I DProject controls PMT – roles Project approach Pre-Project End project report Follow on actions Lessons report Draft closure not. Benefits M.A. Updated Created Business case Project plan CS: Risk register CS: Issue register CS: Lessons log CS: Daily log CS: CIR Project brief CIR docs (cmdb) Lessons log Daily log Risk, Quality, Issue registers + Acceptance Records TM assists with planning * -- Outline BC -- PPD -- Approach -- PMT PBS PDs PFD * * Quality register Controlling a stage Updated Starting up a project Closing a project Delivery stages : Controlling a stage & stage boundary e.g.80% New requirements? Issue/Risk register Conf. Item Records PRINCE2® is a registered trade mark of AXELOS Limited. The Swirl logo™ is a trade mark of AXELOS Limited. Stage Boundary: Created Product status account Benefits M.A. Based on AXELOS PRINCE2® material. Reproduced under licence from AXELOS Limited. All rights reserved.
  • 76. 76 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Processes: Project Timeline 1 week 4 weeks 8 weeks 8 weeks 8 weekse.g. time 2: Authorize the project CS : Stage CS : Stage CS : Stage I P CPSB SB SB Closing a project Work packages Work packages Work packages 60 hrs 850 hrs Reports & Advise Reports & Advise Reports & Advise Authorize next stage Project board decisions Closing 1: Authorize Initiation Initiation (Planning) 1st stage Pre-project (feasibility) Authorize project close delivery stages - (Execution) -- Once during project -- Once per stage -- Many times during stage -- Once per work package PRINCE2® Project Timeline / Example project mandate Ver 1.3 7 processes 1 week CS : Optional Project board Project manager Team manager SU PM PM PM Team PB PM PM PM Team PB PM PM PM Team PBDP CS SU - IP SB / CP MP DP: Directing a project SU: Starting up a project IP: Initiating a project CS: Controlling a stage SB: Managing a stage boundary CP: Closing a project MP: Managing product delivery Based on AXELOS PRINCE2® material. Reproduced under licence from AXELOS Limited. All rights reserved.
  • 77. 77 PT0078-P2P-Class-EN, Version V013Copyright © PTCoE NV and AXELOS Limited 2017. All rights reserved. Material in this document has been sourced from Managing Successful Projects with PRINCE2® 2017 Edition. No part of this document may be reproduced in any form without the written permission of both PTCoE NV and AXELOS Limited. Permission can be requested at support@mplaza.pm and licensing@axelos.com. PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. Starting up a project Directing a project Initiating a project Controlling a stage Managing product delivery Managing a stage boundary Closing a project PROCESSES