2. CENTER FOR INNOVATION VISUALIZATION & SIMULATION CIVS - POWERS EXPANSION PROJECT TOTAL SQUARE FOOTAGE 11,271 1 ST FLOOR 8,789 2 ND FLOOR 2,482 TOTAL PROJECT BUDGET $3.7M CONSTRUCTION BEGAN – NOVEMBER 2010 CONSTRUCTION COMPLETION - JULY 28, 2011 OCCUPANCY TO OCCUR LATE AUGUST 2011 OPERATIONAL FOR FALL 2011
3. REMOTE VIS LAB VISUALIZATION THEATER THEATER LOBBY VIS BOX STAFF WORKROOM STAFF OFFICES/ PRODUCTION AREA CVIS CIVS-FIRST FLOOR PLAN
13. HOSPITALITY & TOURISM MANAGEMENT THE CENTER REMODEL PROJECT TOTAL SQUARE FOOTAGE 20,145 TOTAL PROJECT BUDGET $4.7M CONSTRUCTION BEGAN – NOVEMBER 2010 CONSTRUCTION COMPLETION - JULY 18, 2011 OCCUPANCY TO OCCUR EARLY AUGUST 2011 OPERATIONAL FOR FALL 2011
14. STAFF OFFICES LOCKER ROOM/ STORAGE LEARNING LAB BEVERAGE LAB 63 SEAT RESTAURANT COMMERCIAL KITCHEN FOODS LAB CLASSROOMS STUDY ROOMS FACULTY OFFICES CLASSROOMS CONFERENCE ROOM PLAN VIEW OF HTM
15. HTM – VIEW LOOKING SOUTH INTO COORIDOR OUTSIDE THE STUDENT COMPUTER LAB