Software Project Management

Scheduling
1
Today
• Network Fundamentals
• Gantt Charts
• PERT/CPM Techniques

2
WBS
• Types: Process, product, hybrid
• Formats: Outline or graphical org chart
• High-level WBS does not show dependencies or
durations
• What hurts most ---- is -----what’s missing
• Becomes input to many things, esp. schedule

3
Estimation
• “The single most important task of a
project: setting realistic expectations.
Unrealistic expectations based on
inaccurate estimates are the single largest
cause of software failure.”
•

Futrell, Shafer, Shafer, “Quality Software Project Management”

4
Estimation
• History is your best ally
– Especially when using LOC, function points, etc.

• Use multiple methods if possible
– This reduces your risk
– If using “experts”, use two

• Get buy-in
• Remember: it’s an iterative process!
• Know your “presentation” techniques
5
Estimation
• Bottom-up
• More work to create but more accurate
• Often with Expert Judgment at the task level

• Top-down
• Used in the earliest phases
• Usually with/as Analogy or Expert Judgment

• Analogy
• Comparison with previous project: formal or informal

• Expert Judgment
• Via staff members who will do the work
• Most common technique along w/analogy
• Best if multiple ‘experts’ consulted
6
Estimation
• Parametric Methods
– Know the trade-offs of: LOC & Function Points

• Function Points
– Benefit: relatively independent of the technology used to develop
the system
– We will re-visit this briefly later in semester

• Re-Use Estimation

7
Your Early Phase Processes
• Initial Planning:
• Why
– SOW, Charter

• What/How (partial/1st pass)
– WBS
– Other planning documents
» Software Development Plan, Risk Mgmt., Cfg. Mgmt.

• Estimating
• Size (quantity/complexity) and Effort (duration)
• Iterates

• Scheduling
• Begins along with 1st estimates
• Iterates

8
Scheduling
• Once tasks (from the WBS) and size/effort (from
estimation) are known: then schedule
• Primary objectives
• Best time
• Least cost
• Least risk

• Secondary objectives
• Evaluation of schedule alternatives
• Effective use of resources
• Communications
9
Terminology
• Precedence:
• A task that must occur before another is said to have
precedence of the other

• Concurrence:
• Concurrent tasks are those that can occur at the
same time (in parallel)

• Leads & Lag Time
• Delays between activities
• Time required before or after a given task
10
Terminology
• Milestones
– Identify critical points in your schedule
– Shown as inverted triangle or a diamond
– Often used at “review” or “delivery” times
• Or at end or beginning of phases
• Ex: Software Requirements Review (SRR)
• Ex: User Sign-off

– Can be tied to contract terms

11
Terminology
Example
Milestones

12
Terminology
• Slack & Float
– Float & Slack: synonymous terms
– Free Slack
– Slack an activity has before it delays next task

– Total Slack
– Slack an activity has before delaying whole project

– Slack Time TS = TL – TE
• TE = earliest time an event can take place
• TL = latest date it can occur w/o extending project’s
completion date
13
Scheduling Techniques
– Mathematical Analysis
• Network Diagrams
– PERT
– CPM
– GERT

– Bar Charts
• Milestone Chart
• Gantt Chart

14
Network Diagrams
• Developed in the 1950’s
• A graphical representation of the tasks
necessary to complete a project
• Visualizes the flow of tasks & relationships

15
Mathematical Analysis
• PERT
– Program Evaluation and Review Technique

• CPM
– Critical Path Method

• Sometimes treated synonymously
• All are models using network diagrams

16
MS-Project Example

17
Network Diagrams
• Two classic formats
– AOA: Activity on Arrow
– AON: Activity on Node

• Each task labeled with
• Identifier (usually a letter/code)
• Duration (in std. unit like days)

• There are other variations of labeling
• There is 1 start & 1 end event
• Time goes from left to right
18
Node Formats

19
Network Diagrams
• AOA consists of
• Circles representing Events
– Such as ‘start’ or ‘end’ of a given task

• Lines representing Tasks
– Thing being done ‘Build UI’

• Arrow Diagramming Method (ADM)

• AON
• Tasks on Nodes
– Nodes can be circles or rectangles (usually latter)
– Task information written on node

• Arrows are dependencies between tasks
• Precedence Diagramming Method (PDM)
20
Critical Path
• “The specific set of sequential tasks upon
which the project completion date depends”
– or “the longest full path”

• All projects have a Critical Path
• Accelerating non-critical tasks do not
directly shorten the schedule

21
Critical Path Example

22
CPM
• Critical Path Method
– The process for determining and optimizing the
critical path

• Non-CP tasks can start earlier or later w/o
impacting completion date
• Note: Critical Path may change to another
as you shorten the current
• Should be done in conjunction with the you
& the functional manager
23
4 Task Dependency Types
• Mandatory Dependencies
•
•
•
•

“Hard logic” dependencies
Nature of the work dictates an ordering
Ex: Coding has to precede testing
Ex: UI design precedes UI implementation

• Discretionary Dependencies
•
•
•
•

“Soft logic” dependencies
Determined by the project management team
Process-driven
Ex: Discretionary order of creating certain modules
24
4 Task Dependency Types
• External Dependencies
• Outside of the project itself
• Ex: Release of 3rd party product; contract signoff
• Ex: stakeholders, suppliers, Y2K, year end

• Resource Dependencies
• Two task rely on the same resource
• Ex: You have only one DBA but multiple DB tasks

25
Task Dependency Relationships
• Finish-to-Start (FS)
– B cannot start till A finishes
– A: Construct fence; B: Paint Fence

• Start-to-Start (SS)
– B cannot start till A starts
– A: Pour foundation; B: Level concrete

• Finish-to-Finish (FF)
– B cannot finish till A finishes
– A: Add wiring; B: Inspect electrical

• Start-to-Finish (SF)
– B cannot finish till A starts (rare)

26
Example Step 1

27
Forward Pass
• To determine early start (ES) and early finish (EF) times
for each task
• Work from left to right
• Adding times in each path
• Rule: when several tasks converge, the ES for the next task
is the largest of preceding EF times

28
Example Step 2

29
Backward Pass
•
•
•
•

To determine the last finish (LF) and last start (LS) times
Start at the end node
Compute the bottom pair of numbers
Subtract duration from connecting node’s earliest start
time

30
Example Step 3

31
Example Step 4

32
Slack & Reserve
• How can slack be negative?
• What does that mean?
• How can you address that situation?

33
Slack & Reserve
Reserve
Time

Negative
Slack

Forward
Pass
A

B
Backward
Pass

Start
Date

Project Due
Date

34
35
Network Diagrams
• Advantages
– Show precedence well
– Reveal interdependencies not shown in other
techniques
– Ability to calculate critical path
– Ability to perform “what if” exercises

• Disadvantages
– Default model assumes resources are unlimited
• You need to incorporate this yourself (Resource
Dependencies) when determining the “real” Critical Path

– Difficult to follow on large projects
36
PERT
• Program Evaluation and Review Technique
• Based on idea that estimates are uncertain
– Therefore uses duration ranges
– And the probability of falling to a given range

• Uses an “expected value” (or weighted average) to
determine durations
• Use the following methods to calculate the
expected durations, then use as input to your
network diagram
37
PERT
• Start with 3 estimates
– Optimistic
• Would likely occur 1 time in 20

– Most likely
• Modal value of the distribution

– Pessimistic
• Would be exceeded only one time in 20

38
PERT Formula
• Combined to estimate a task duration

39
PERT Formula
• Confidence Interval can be determined
• Based on a standard deviation of the
expected time
• Using a bell curve (normal distribution)

• For the whole critical path use
40
PERT Example
Description

10d

10d

a

9d

9d

b

12d

20d

PERT time

10.16d

11.5d

Std. Dev.

•

Planner 2

m

•

Planner 1

0.5d

1.8d

Confidence interval for P2 is 4 times wider than P1 for a given
probability
Ex: 68% probability of 9.7 to 11.7 days (P1) vs. 9.5-13.5 days (P2)

41
PERT
• Advantages
– Accounts for uncertainty

• Disadvantages
–
–
–
–

Time and labor intensive
Assumption of unlimited resources is big issue
Lack of functional ownership of estimates
Mostly only used on large, complex project

• Get PERT software to calculate it for you
42
CPM vs. PERT
•
•
•
•
•

Both use Network Diagrams
CPM: deterministic
PERT: probabilistic
CPM: one estimate, PERT, three estimates
PERT is infrequently used

43
Milestone Chart
• Sometimes called a “bar charts”
• Simple Gantt chart
– Either showing just highest summary bars
– Or milestones only

44
Bar Chart

45
Gantt Chart

46
Gantt Chart
• Disadvantages
– Does not show interdependencies well
– Does not uncertainty of a given activity (as does PERT)

• Advantages
– Easily understood
– Easily created and maintained

• Note: Software now shows dependencies among
tasks in Gantt charts
– In the “old” days Gantt charts did not show these
dependencies, bar charts typically do not
47
Reducing Project Duration
• How can you shorten the schedule?
• Via
–
–
–
–

Reducing scope (or quality)
Adding resources
Concurrency (perform tasks in parallel)
Substitution of activities

48
Compression Techniques
• Shorten the overall duration of the project
• Crashing
•
•
•
•
•

Looks at cost and schedule tradeoffs
Gain greatest compression with least cost
Add resources to critical path tasks
Limit or reduce requirements (scope)
Changing the sequence of tasks

• Fast Tracking
• Overlapping of phases, activities or tasks that would otherwise
be sequential
• Involves some risk
• May cause rework
49
Mythical Man-Month
• Book: “The Mythical Man-Month”
– Author: Fred Brooks

• “The classic book on the human elements of
software engineering”
• First two chapters are full of terrific insight
(and quotes)

50
Mythical Man-Month
• “Cost varies as product of men and months,
progress does not.”
• “Hence the man-month as a unit for
measuring the size of job is a dangerous and
deceptive myth”

51
Mythical Man-Month
• Why is software project disaster so common?
– 1. Estimation techniques are poor & assume things will
go well (an ‘unvoiced’ assumption)
– 2. Estimation techniques fallaciously confuse effort
with progress, hiding the assumption that men and
months are interchangeable
– 3. Because of estimation uncertainty, manager lack
courteous stubbornness
– 4. Schedule progress is poorly monitored
– 5. When schedule slippage is recognized, the natural
response is to add manpower. Which, is like dousing a
fire with gasoline.
52
Mythical Man-Month
• Optimism
– “All programmers are optimists”
– 1st false assumption: “all will go well” or “each task
takes only as long as it ‘ought’ to take”
– The Fix: Consider the larger probabilities

• Cost (overhead) of communication (and training)
• His formula: n(n-1)/2

– How long does a 12 month project take?
– 1 person: 1 month
– 2 persons = 7 months (2 man-months extra)
– 3 persons = 5 months (e man-months extra)

– Fix: don’t assume adding people will solve the problem
53
Mythical Man-Month
• Sequential nature of the process
– “The bearing of a child takes nine months, no matter
how many women are assigned”

• What is the most mis-scheduled part of process?
• Testing (the most linear process)

• Why is this particularly bad?
• Occurs late in process and w/o warning
• Higher costs: primary and secondary

• Fix: Allocate more test time
• Understand task dependencies
54
Mythical Man-Month
• Reliance on hunches and guesses
– What is ‘gutless estimating’?

• The myth of additional manpower
– Brooks Law
– “Adding manpower to a late project makes it
later”

55
Mythical Man-Month
• Q: “How does a project get to be a year late”?
– A: “One day at a time”

• Studies
– Each task: twice as long as estimated
– Only 50% of work week was programming

• Fixes
– No “fuzzy” milestones (get the “true” status)
– Reduce the role of conflict
– Identify the “true status”
56
Review - Fundamentals
• Projects, programs, products
• McConnell’s four dimensions
• Classic mistakes
– Know a set of these
– Remember by “type”
• People, process, product, technology related

57
Review
• Trade-offs & constraints
– The triangle
– Cost, Time, Scope
– (And Quality)

• PMI processes and knowledge areas
– Process groups

• Organizational structures
– Advantages & disadvantages of each form
58
Review
• Classic project phases
• Key documents at each phase
– SOW, Charter
– Project Management Plan
– Identify key planning documents

59
Review - Lifecycle
• Methodologies
– Trade-offs
– Basic Pros & Cons

• Given a specific scenario decide what SDLC is
most appropriate
• Waterfall process
• Challenges of each phase
• Requirements
• Criticality
• Issues
• Functional & Non-functional
60
Review
• Wherever I gave you say 5 types of ‘things’
– Like estimation techniques or methodologies

• I may ask ‘Tell me two approaches to X’
• Especially interested in the pros & cons
• You did your readings, yes?
– Text & class slides

61
Review – Estimate & Schedule
• Four primary steps
–
–
–
–

Define work to be done (WBS)
Estimate size
Estimate effort
Build schedule

62
Review - WBS
•
•
•
•

Types: Process, product, hybrid
Formats: Outline or graphical org chart
Shows hierarchical task relationships
High-level version does not show dependencies or
durations
• What hurts most is what’s missing
• Becomes input to many things, esp. schedule

63
Review – Estimation
• Size Estimation Techniques
–
–
–
–

Bottom-up vs. Top-down
Analogy
Expert Judgment
Parametric (not the formulas, just the gist)
• Function Points
• LOC

• Schedule presentation techniques
– Q3, 6-8 months, best/worst case
64
Review - Scheduling
• Dependencies
– Types: mandatory, etc.
– Relationships: FS, SF, etc.

• Network Diagrams
– CPM
– PERT

• Schedule Optimization Techniques
65
Things I Won’t Ask
• Ambiguous terminology
– Tasks vs. Activities vs. Work Packages
– WBS: does it start at 0 or 1
– Details of Function Point calculation method

66
Homework
• No homework, just exam study
• You can get a jump on MS-Project by
reading Schwalbe Appendix A “Guide to
Using Microsoft Project 2000” (447-477)

67
Questions?

68

Contenu connexe

Tendances

Software Project Scheduling Diagrams
Software Project Scheduling DiagramsSoftware Project Scheduling Diagrams
Software Project Scheduling DiagramsSaqib Raza
 
Software Project Fundamentals and Classic Mistakes - P&MSP2010 (1/11)
Software Project Fundamentals and Classic Mistakes - P&MSP2010 (1/11)Software Project Fundamentals and Classic Mistakes - P&MSP2010 (1/11)
Software Project Fundamentals and Classic Mistakes - P&MSP2010 (1/11)Emanuele Della Valle
 
Software Engineering (Project Management )
Software Engineering (Project  Management )Software Engineering (Project  Management )
Software Engineering (Project Management )ShudipPal
 
Lect-2: Overview and Traditional SPM, Classic mistakes
Lect-2: Overview and Traditional SPM, Classic mistakesLect-2: Overview and Traditional SPM, Classic mistakes
Lect-2: Overview and Traditional SPM, Classic mistakesMubashir Ali
 
Software project management
Software project managementSoftware project management
Software project managementR A Akerkar
 
Selection of an appropriate project approach
Selection of an appropriate project approachSelection of an appropriate project approach
Selection of an appropriate project approachtumetr1
 
Software Project Managment
Software Project ManagmentSoftware Project Managment
Software Project ManagmentSaqib Naveed
 
SOFTWARE ENGINEERING
SOFTWARE ENGINEERING  SOFTWARE ENGINEERING
SOFTWARE ENGINEERING Gaditek
 
Rational unified process
Rational unified processRational unified process
Rational unified processnaveed428
 
Chapter1 conventional softwaremanagement (1)
Chapter1 conventional softwaremanagement (1)Chapter1 conventional softwaremanagement (1)
Chapter1 conventional softwaremanagement (1)Jkumararaja
 
CS 414 (IT Project Management)
CS 414 (IT Project Management)CS 414 (IT Project Management)
CS 414 (IT Project Management)raszky
 
Unit4 Proof of Correctness, Statistical Tools, Clean Room Process and Quality...
Unit4 Proof of Correctness, Statistical Tools, Clean Room Process and Quality...Unit4 Proof of Correctness, Statistical Tools, Clean Room Process and Quality...
Unit4 Proof of Correctness, Statistical Tools, Clean Room Process and Quality...Reetesh Gupta
 
Chapter 1,2,3,4 notes
Chapter 1,2,3,4 notesChapter 1,2,3,4 notes
Chapter 1,2,3,4 notesAruna M
 
Lecture6
Lecture6Lecture6
Lecture6soloeng
 
Spm ksp
Spm kspSpm ksp
Spm kspktosri
 

Tendances (20)

Software Project Scheduling Diagrams
Software Project Scheduling DiagramsSoftware Project Scheduling Diagrams
Software Project Scheduling Diagrams
 
Planning Phase - P&MSP2010 (3/11)
Planning Phase - P&MSP2010 (3/11)Planning Phase - P&MSP2010 (3/11)
Planning Phase - P&MSP2010 (3/11)
 
Software Project Fundamentals and Classic Mistakes - P&MSP2010 (1/11)
Software Project Fundamentals and Classic Mistakes - P&MSP2010 (1/11)Software Project Fundamentals and Classic Mistakes - P&MSP2010 (1/11)
Software Project Fundamentals and Classic Mistakes - P&MSP2010 (1/11)
 
Software Engineering (Project Management )
Software Engineering (Project  Management )Software Engineering (Project  Management )
Software Engineering (Project Management )
 
Lect-2: Overview and Traditional SPM, Classic mistakes
Lect-2: Overview and Traditional SPM, Classic mistakesLect-2: Overview and Traditional SPM, Classic mistakes
Lect-2: Overview and Traditional SPM, Classic mistakes
 
Lect3
Lect3Lect3
Lect3
 
Software project management
Software project managementSoftware project management
Software project management
 
Selection of an appropriate project approach
Selection of an appropriate project approachSelection of an appropriate project approach
Selection of an appropriate project approach
 
Software Project Managment
Software Project ManagmentSoftware Project Managment
Software Project Managment
 
SOFTWARE ENGINEERING
SOFTWARE ENGINEERING  SOFTWARE ENGINEERING
SOFTWARE ENGINEERING
 
Mg6088 spm unit-2
Mg6088 spm unit-2Mg6088 spm unit-2
Mg6088 spm unit-2
 
Rational unified process
Rational unified processRational unified process
Rational unified process
 
Chapter1 conventional softwaremanagement (1)
Chapter1 conventional softwaremanagement (1)Chapter1 conventional softwaremanagement (1)
Chapter1 conventional softwaremanagement (1)
 
CS 414 (IT Project Management)
CS 414 (IT Project Management)CS 414 (IT Project Management)
CS 414 (IT Project Management)
 
Unit4 Proof of Correctness, Statistical Tools, Clean Room Process and Quality...
Unit4 Proof of Correctness, Statistical Tools, Clean Room Process and Quality...Unit4 Proof of Correctness, Statistical Tools, Clean Room Process and Quality...
Unit4 Proof of Correctness, Statistical Tools, Clean Room Process and Quality...
 
Chapter 1,2,3,4 notes
Chapter 1,2,3,4 notesChapter 1,2,3,4 notes
Chapter 1,2,3,4 notes
 
Lecture6
Lecture6Lecture6
Lecture6
 
Estimation
EstimationEstimation
Estimation
 
Spm ksp
Spm kspSpm ksp
Spm ksp
 
Chapter 03
Chapter 03Chapter 03
Chapter 03
 

En vedette

Program evaluation review technique (pert)
Program evaluation review technique (pert)Program evaluation review technique (pert)
Program evaluation review technique (pert)tomeh
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERTPulchowk Campus
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure pptnazi2020
 
The Mythical Man Month
The Mythical Man MonthThe Mythical Man Month
The Mythical Man MonthMr Cracker
 
Project Manager Success Summit - The Mythical Man-Month
Project Manager Success Summit - The Mythical Man-MonthProject Manager Success Summit - The Mythical Man-Month
Project Manager Success Summit - The Mythical Man-MonthMichael Charles
 
Mythical Man Month Essays on Software Engineering
Mythical Man Month Essays on Software EngineeringMythical Man Month Essays on Software Engineering
Mythical Man Month Essays on Software Engineeringmustafa sarac
 
Project Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectProject Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectMeryem Yıldız
 
Razorfish Scrum for Teams and Organizations Software Architect Conference 2013
Razorfish Scrum for Teams and Organizations Software Architect Conference 2013Razorfish Scrum for Teams and Organizations Software Architect Conference 2013
Razorfish Scrum for Teams and Organizations Software Architect Conference 2013Razorfish
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Schedulingsslovepk
 
Project Management
Project ManagementProject Management
Project ManagementMark Roman
 
203wbs Network Gantt Chart
203wbs Network Gantt Chart203wbs Network Gantt Chart
203wbs Network Gantt Chartbtecexpert
 
Project Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert ChartProject Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert ChartVinay Prajapati
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertRaj J Das
 

En vedette (20)

Wbs For Building Project
Wbs For Building ProjectWbs For Building Project
Wbs For Building Project
 
Program evaluation review technique (pert)
Program evaluation review technique (pert)Program evaluation review technique (pert)
Program evaluation review technique (pert)
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
 
Project Management PERT and CPM
Project Management PERT and CPMProject Management PERT and CPM
Project Management PERT and CPM
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure ppt
 
The Mythical Man Month
The Mythical Man MonthThe Mythical Man Month
The Mythical Man Month
 
Project Manager Success Summit - The Mythical Man-Month
Project Manager Success Summit - The Mythical Man-MonthProject Manager Success Summit - The Mythical Man-Month
Project Manager Success Summit - The Mythical Man-Month
 
Mythical Man Month Essays on Software Engineering
Mythical Man Month Essays on Software EngineeringMythical Man Month Essays on Software Engineering
Mythical Man Month Essays on Software Engineering
 
Mythical Man-Month
Mythical Man-MonthMythical Man-Month
Mythical Man-Month
 
Project Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectProject Management focused on Scheduling of a Project
Project Management focused on Scheduling of a Project
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
 
Razorfish Scrum for Teams and Organizations Software Architect Conference 2013
Razorfish Scrum for Teams and Organizations Software Architect Conference 2013Razorfish Scrum for Teams and Organizations Software Architect Conference 2013
Razorfish Scrum for Teams and Organizations Software Architect Conference 2013
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
 
Project Management
Project ManagementProject Management
Project Management
 
203wbs Network Gantt Chart
203wbs Network Gantt Chart203wbs Network Gantt Chart
203wbs Network Gantt Chart
 
Project Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert ChartProject Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert Chart
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gert
 
Pert
PertPert
Pert
 

Similaire à Software Project Mangmement (Lecture 5)

project on software industry
project on software industryproject on software industry
project on software industryAamir chouhan
 
Cpm critical path method
Cpm   critical path methodCpm   critical path method
Cpm critical path methodPrathima Girish
 
08. Project Time Management Upload
08. Project Time Management Upload08. Project Time Management Upload
08. Project Time Management UploadBhuWan Khadka
 
Crictal path identification
Crictal path identificationCrictal path identification
Crictal path identificationFarhana Rehman
 
06 project time management
06  project time management06  project time management
06 project time managementAla Ibrahim
 
PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersIIMSE Edu
 
C03.05-Scheduling.key.pdf
C03.05-Scheduling.key.pdfC03.05-Scheduling.key.pdf
C03.05-Scheduling.key.pdfssuser8babb7
 
3210cpmslideshare-1610302073773770419.pdf
3210cpmslideshare-1610302073773770419.pdf3210cpmslideshare-1610302073773770419.pdf
3210cpmslideshare-1610302073773770419.pdfPabitraMitra3
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisAsif Sultan Razu
 
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptx
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptxSession 9 - Project scheduling-PERT-CPM-Network diagram.pptx
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptxAlRashedinKawser2
 
Software Project Management (lecture 3)
Software Project Management (lecture 3)Software Project Management (lecture 3)
Software Project Management (lecture 3)Syed Muhammad Hammad
 
CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementAmit Kumbar
 
L2_Project_Management.pdf
L2_Project_Management.pdfL2_Project_Management.pdf
L2_Project_Management.pdfJerryHung19
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..pptPedadaSaikumar
 
L6.2 planing&scheduling
L6.2 planing&schedulingL6.2 planing&scheduling
L6.2 planing&schedulingmanusug
 
Reference Model of Real Time System
Reference Model of Real Time SystemReference Model of Real Time System
Reference Model of Real Time SystemRaaz Karkee
 

Similaire à Software Project Mangmement (Lecture 5) (20)

project on software industry
project on software industryproject on software industry
project on software industry
 
Cpm critical path method
Cpm   critical path methodCpm   critical path method
Cpm critical path method
 
08. Project Time Management Upload
08. Project Time Management Upload08. Project Time Management Upload
08. Project Time Management Upload
 
Crictal path identification
Crictal path identificationCrictal path identification
Crictal path identification
 
06 project time management
06  project time management06  project time management
06 project time management
 
PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For Beginners
 
C03.05-Scheduling.key.pdf
C03.05-Scheduling.key.pdfC03.05-Scheduling.key.pdf
C03.05-Scheduling.key.pdf
 
3210cpmslideshare-1610302073773770419.pdf
3210cpmslideshare-1610302073773770419.pdf3210cpmslideshare-1610302073773770419.pdf
3210cpmslideshare-1610302073773770419.pdf
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
 
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptx
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptxSession 9 - Project scheduling-PERT-CPM-Network diagram.pptx
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptx
 
Software Project Management (lecture 3)
Software Project Management (lecture 3)Software Project Management (lecture 3)
Software Project Management (lecture 3)
 
CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource management
 
L2_Project_Management.pdf
L2_Project_Management.pdfL2_Project_Management.pdf
L2_Project_Management.pdf
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
lec11.ppt
lec11.pptlec11.ppt
lec11.ppt
 
Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
 
L6.2 planing&scheduling
L6.2 planing&schedulingL6.2 planing&scheduling
L6.2 planing&scheduling
 
Reference Model of Real Time System
Reference Model of Real Time SystemReference Model of Real Time System
Reference Model of Real Time System
 
Bpp 3213 lecture 2
Bpp 3213 lecture 2Bpp 3213 lecture 2
Bpp 3213 lecture 2
 

Plus de Syed Muhammad Hammad

Plus de Syed Muhammad Hammad (8)

Software Project Management (lecture 4)
Software Project Management (lecture 4)Software Project Management (lecture 4)
Software Project Management (lecture 4)
 
Software Project Management( lecture 1)
Software Project Management( lecture 1)Software Project Management( lecture 1)
Software Project Management( lecture 1)
 
Scm
ScmScm
Scm
 
Java easy learning
Java easy  learningJava easy  learning
Java easy learning
 
An interdisciplinary course_in_digital_image_processing
An interdisciplinary course_in_digital_image_processingAn interdisciplinary course_in_digital_image_processing
An interdisciplinary course_in_digital_image_processing
 
Image Segmentation
 Image Segmentation Image Segmentation
Image Segmentation
 
Image processing tatorial
Image processing tatorialImage processing tatorial
Image processing tatorial
 
Mat-lab image processing tatorial
Mat-lab  image processing tatorialMat-lab  image processing tatorial
Mat-lab image processing tatorial
 

Dernier

How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17Celine George
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Celine George
 
ROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxVanesaIglesias10
 
Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Seán Kennedy
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...JhezDiaz1
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfPatidar M
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Celine George
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...Nguyen Thanh Tu Collection
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYKayeClaireEstoconing
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4MiaBumagat1
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPCeline George
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONHumphrey A Beña
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptxmary850239
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parentsnavabharathschool99
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfErwinPantujan2
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)lakshayb543
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Celine George
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxHumphrey A Beña
 

Dernier (20)

How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
 
ROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptx
 
Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdf
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4
 
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptxYOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERP
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parents
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
 

Software Project Mangmement (Lecture 5)

  • 2. Today • Network Fundamentals • Gantt Charts • PERT/CPM Techniques 2
  • 3. WBS • Types: Process, product, hybrid • Formats: Outline or graphical org chart • High-level WBS does not show dependencies or durations • What hurts most ---- is -----what’s missing • Becomes input to many things, esp. schedule 3
  • 4. Estimation • “The single most important task of a project: setting realistic expectations. Unrealistic expectations based on inaccurate estimates are the single largest cause of software failure.” • Futrell, Shafer, Shafer, “Quality Software Project Management” 4
  • 5. Estimation • History is your best ally – Especially when using LOC, function points, etc. • Use multiple methods if possible – This reduces your risk – If using “experts”, use two • Get buy-in • Remember: it’s an iterative process! • Know your “presentation” techniques 5
  • 6. Estimation • Bottom-up • More work to create but more accurate • Often with Expert Judgment at the task level • Top-down • Used in the earliest phases • Usually with/as Analogy or Expert Judgment • Analogy • Comparison with previous project: formal or informal • Expert Judgment • Via staff members who will do the work • Most common technique along w/analogy • Best if multiple ‘experts’ consulted 6
  • 7. Estimation • Parametric Methods – Know the trade-offs of: LOC & Function Points • Function Points – Benefit: relatively independent of the technology used to develop the system – We will re-visit this briefly later in semester • Re-Use Estimation 7
  • 8. Your Early Phase Processes • Initial Planning: • Why – SOW, Charter • What/How (partial/1st pass) – WBS – Other planning documents » Software Development Plan, Risk Mgmt., Cfg. Mgmt. • Estimating • Size (quantity/complexity) and Effort (duration) • Iterates • Scheduling • Begins along with 1st estimates • Iterates 8
  • 9. Scheduling • Once tasks (from the WBS) and size/effort (from estimation) are known: then schedule • Primary objectives • Best time • Least cost • Least risk • Secondary objectives • Evaluation of schedule alternatives • Effective use of resources • Communications 9
  • 10. Terminology • Precedence: • A task that must occur before another is said to have precedence of the other • Concurrence: • Concurrent tasks are those that can occur at the same time (in parallel) • Leads & Lag Time • Delays between activities • Time required before or after a given task 10
  • 11. Terminology • Milestones – Identify critical points in your schedule – Shown as inverted triangle or a diamond – Often used at “review” or “delivery” times • Or at end or beginning of phases • Ex: Software Requirements Review (SRR) • Ex: User Sign-off – Can be tied to contract terms 11
  • 13. Terminology • Slack & Float – Float & Slack: synonymous terms – Free Slack – Slack an activity has before it delays next task – Total Slack – Slack an activity has before delaying whole project – Slack Time TS = TL – TE • TE = earliest time an event can take place • TL = latest date it can occur w/o extending project’s completion date 13
  • 14. Scheduling Techniques – Mathematical Analysis • Network Diagrams – PERT – CPM – GERT – Bar Charts • Milestone Chart • Gantt Chart 14
  • 15. Network Diagrams • Developed in the 1950’s • A graphical representation of the tasks necessary to complete a project • Visualizes the flow of tasks & relationships 15
  • 16. Mathematical Analysis • PERT – Program Evaluation and Review Technique • CPM – Critical Path Method • Sometimes treated synonymously • All are models using network diagrams 16
  • 18. Network Diagrams • Two classic formats – AOA: Activity on Arrow – AON: Activity on Node • Each task labeled with • Identifier (usually a letter/code) • Duration (in std. unit like days) • There are other variations of labeling • There is 1 start & 1 end event • Time goes from left to right 18
  • 20. Network Diagrams • AOA consists of • Circles representing Events – Such as ‘start’ or ‘end’ of a given task • Lines representing Tasks – Thing being done ‘Build UI’ • Arrow Diagramming Method (ADM) • AON • Tasks on Nodes – Nodes can be circles or rectangles (usually latter) – Task information written on node • Arrows are dependencies between tasks • Precedence Diagramming Method (PDM) 20
  • 21. Critical Path • “The specific set of sequential tasks upon which the project completion date depends” – or “the longest full path” • All projects have a Critical Path • Accelerating non-critical tasks do not directly shorten the schedule 21
  • 23. CPM • Critical Path Method – The process for determining and optimizing the critical path • Non-CP tasks can start earlier or later w/o impacting completion date • Note: Critical Path may change to another as you shorten the current • Should be done in conjunction with the you & the functional manager 23
  • 24. 4 Task Dependency Types • Mandatory Dependencies • • • • “Hard logic” dependencies Nature of the work dictates an ordering Ex: Coding has to precede testing Ex: UI design precedes UI implementation • Discretionary Dependencies • • • • “Soft logic” dependencies Determined by the project management team Process-driven Ex: Discretionary order of creating certain modules 24
  • 25. 4 Task Dependency Types • External Dependencies • Outside of the project itself • Ex: Release of 3rd party product; contract signoff • Ex: stakeholders, suppliers, Y2K, year end • Resource Dependencies • Two task rely on the same resource • Ex: You have only one DBA but multiple DB tasks 25
  • 26. Task Dependency Relationships • Finish-to-Start (FS) – B cannot start till A finishes – A: Construct fence; B: Paint Fence • Start-to-Start (SS) – B cannot start till A starts – A: Pour foundation; B: Level concrete • Finish-to-Finish (FF) – B cannot finish till A finishes – A: Add wiring; B: Inspect electrical • Start-to-Finish (SF) – B cannot finish till A starts (rare) 26
  • 28. Forward Pass • To determine early start (ES) and early finish (EF) times for each task • Work from left to right • Adding times in each path • Rule: when several tasks converge, the ES for the next task is the largest of preceding EF times 28
  • 30. Backward Pass • • • • To determine the last finish (LF) and last start (LS) times Start at the end node Compute the bottom pair of numbers Subtract duration from connecting node’s earliest start time 30
  • 33. Slack & Reserve • How can slack be negative? • What does that mean? • How can you address that situation? 33
  • 35. 35
  • 36. Network Diagrams • Advantages – Show precedence well – Reveal interdependencies not shown in other techniques – Ability to calculate critical path – Ability to perform “what if” exercises • Disadvantages – Default model assumes resources are unlimited • You need to incorporate this yourself (Resource Dependencies) when determining the “real” Critical Path – Difficult to follow on large projects 36
  • 37. PERT • Program Evaluation and Review Technique • Based on idea that estimates are uncertain – Therefore uses duration ranges – And the probability of falling to a given range • Uses an “expected value” (or weighted average) to determine durations • Use the following methods to calculate the expected durations, then use as input to your network diagram 37
  • 38. PERT • Start with 3 estimates – Optimistic • Would likely occur 1 time in 20 – Most likely • Modal value of the distribution – Pessimistic • Would be exceeded only one time in 20 38
  • 39. PERT Formula • Combined to estimate a task duration 39
  • 40. PERT Formula • Confidence Interval can be determined • Based on a standard deviation of the expected time • Using a bell curve (normal distribution) • For the whole critical path use 40
  • 41. PERT Example Description 10d 10d a 9d 9d b 12d 20d PERT time 10.16d 11.5d Std. Dev. • Planner 2 m • Planner 1 0.5d 1.8d Confidence interval for P2 is 4 times wider than P1 for a given probability Ex: 68% probability of 9.7 to 11.7 days (P1) vs. 9.5-13.5 days (P2) 41
  • 42. PERT • Advantages – Accounts for uncertainty • Disadvantages – – – – Time and labor intensive Assumption of unlimited resources is big issue Lack of functional ownership of estimates Mostly only used on large, complex project • Get PERT software to calculate it for you 42
  • 43. CPM vs. PERT • • • • • Both use Network Diagrams CPM: deterministic PERT: probabilistic CPM: one estimate, PERT, three estimates PERT is infrequently used 43
  • 44. Milestone Chart • Sometimes called a “bar charts” • Simple Gantt chart – Either showing just highest summary bars – Or milestones only 44
  • 47. Gantt Chart • Disadvantages – Does not show interdependencies well – Does not uncertainty of a given activity (as does PERT) • Advantages – Easily understood – Easily created and maintained • Note: Software now shows dependencies among tasks in Gantt charts – In the “old” days Gantt charts did not show these dependencies, bar charts typically do not 47
  • 48. Reducing Project Duration • How can you shorten the schedule? • Via – – – – Reducing scope (or quality) Adding resources Concurrency (perform tasks in parallel) Substitution of activities 48
  • 49. Compression Techniques • Shorten the overall duration of the project • Crashing • • • • • Looks at cost and schedule tradeoffs Gain greatest compression with least cost Add resources to critical path tasks Limit or reduce requirements (scope) Changing the sequence of tasks • Fast Tracking • Overlapping of phases, activities or tasks that would otherwise be sequential • Involves some risk • May cause rework 49
  • 50. Mythical Man-Month • Book: “The Mythical Man-Month” – Author: Fred Brooks • “The classic book on the human elements of software engineering” • First two chapters are full of terrific insight (and quotes) 50
  • 51. Mythical Man-Month • “Cost varies as product of men and months, progress does not.” • “Hence the man-month as a unit for measuring the size of job is a dangerous and deceptive myth” 51
  • 52. Mythical Man-Month • Why is software project disaster so common? – 1. Estimation techniques are poor & assume things will go well (an ‘unvoiced’ assumption) – 2. Estimation techniques fallaciously confuse effort with progress, hiding the assumption that men and months are interchangeable – 3. Because of estimation uncertainty, manager lack courteous stubbornness – 4. Schedule progress is poorly monitored – 5. When schedule slippage is recognized, the natural response is to add manpower. Which, is like dousing a fire with gasoline. 52
  • 53. Mythical Man-Month • Optimism – “All programmers are optimists” – 1st false assumption: “all will go well” or “each task takes only as long as it ‘ought’ to take” – The Fix: Consider the larger probabilities • Cost (overhead) of communication (and training) • His formula: n(n-1)/2 – How long does a 12 month project take? – 1 person: 1 month – 2 persons = 7 months (2 man-months extra) – 3 persons = 5 months (e man-months extra) – Fix: don’t assume adding people will solve the problem 53
  • 54. Mythical Man-Month • Sequential nature of the process – “The bearing of a child takes nine months, no matter how many women are assigned” • What is the most mis-scheduled part of process? • Testing (the most linear process) • Why is this particularly bad? • Occurs late in process and w/o warning • Higher costs: primary and secondary • Fix: Allocate more test time • Understand task dependencies 54
  • 55. Mythical Man-Month • Reliance on hunches and guesses – What is ‘gutless estimating’? • The myth of additional manpower – Brooks Law – “Adding manpower to a late project makes it later” 55
  • 56. Mythical Man-Month • Q: “How does a project get to be a year late”? – A: “One day at a time” • Studies – Each task: twice as long as estimated – Only 50% of work week was programming • Fixes – No “fuzzy” milestones (get the “true” status) – Reduce the role of conflict – Identify the “true status” 56
  • 57. Review - Fundamentals • Projects, programs, products • McConnell’s four dimensions • Classic mistakes – Know a set of these – Remember by “type” • People, process, product, technology related 57
  • 58. Review • Trade-offs & constraints – The triangle – Cost, Time, Scope – (And Quality) • PMI processes and knowledge areas – Process groups • Organizational structures – Advantages & disadvantages of each form 58
  • 59. Review • Classic project phases • Key documents at each phase – SOW, Charter – Project Management Plan – Identify key planning documents 59
  • 60. Review - Lifecycle • Methodologies – Trade-offs – Basic Pros & Cons • Given a specific scenario decide what SDLC is most appropriate • Waterfall process • Challenges of each phase • Requirements • Criticality • Issues • Functional & Non-functional 60
  • 61. Review • Wherever I gave you say 5 types of ‘things’ – Like estimation techniques or methodologies • I may ask ‘Tell me two approaches to X’ • Especially interested in the pros & cons • You did your readings, yes? – Text & class slides 61
  • 62. Review – Estimate & Schedule • Four primary steps – – – – Define work to be done (WBS) Estimate size Estimate effort Build schedule 62
  • 63. Review - WBS • • • • Types: Process, product, hybrid Formats: Outline or graphical org chart Shows hierarchical task relationships High-level version does not show dependencies or durations • What hurts most is what’s missing • Becomes input to many things, esp. schedule 63
  • 64. Review – Estimation • Size Estimation Techniques – – – – Bottom-up vs. Top-down Analogy Expert Judgment Parametric (not the formulas, just the gist) • Function Points • LOC • Schedule presentation techniques – Q3, 6-8 months, best/worst case 64
  • 65. Review - Scheduling • Dependencies – Types: mandatory, etc. – Relationships: FS, SF, etc. • Network Diagrams – CPM – PERT • Schedule Optimization Techniques 65
  • 66. Things I Won’t Ask • Ambiguous terminology – Tasks vs. Activities vs. Work Packages – WBS: does it start at 0 or 1 – Details of Function Point calculation method 66
  • 67. Homework • No homework, just exam study • You can get a jump on MS-Project by reading Schwalbe Appendix A “Guide to Using Microsoft Project 2000” (447-477) 67

Notes de l'éditeur

  1. No lab today More lab in later term
  2. draw graphs Training == ramp-up Software is a ‘systems effort’
  3. draw graphs Training == ramp-up Software is a ‘systems effort’
  4. I don’t agree with his formula He advocates 50% of schedule to Test Late Highest cost: most staffed time Changes cost more Secondary costs You need to understand Critical Path and other dependencies
  5. omelet and chef analogy
  6. what does Brooks mean by this? Termites not tornadoes Imperceptibly but inexorably Hard to recognize Reduce conflict: status vs. action meetings