This document outlines a project plan with multiple tasks over 66 days to complete Units 4, 5, and 62. It includes 38 tasks with details on task name, duration, start and finish dates, and predecessors. The project involves tasks such as creating a Gantt chart, risk assessment, research, video production, and gathering feedback. The project is broken into three assignments that will be completed between November 2012 and May 2013.
1. ID Task Task Name Duration Start Finish Predecessors 05 Nov '12 12 Nov '12 19 Nov '12
Mode M T W T F S S M T W T F S S M T W T
1 Start Unit 4, 5 & 62 66 days Tue 06/11/12 Tue 05/02/13
Assignment 2
2 Task 1 8 days Tue 06/11/12 Thu 15/11/12
3 A - Gant Chart 4 days Tue 06/11/12 Fri 09/11/12
4 B - Schedule 2 days Mon 12/11/12Tue 13/11/12 3
5 C - Risk Assessment 2 days Wed Thu 15/11/12 4
14/11/12
6 Task 2 19 days Fri 16/11/12 Wed 12/12/12
7 A - Research 6 days Fri 16/11/12 Fri 23/11/12
8 B - Primary Content 6 days Mon Mon 7
Research 26/11/12 03/12/12
9 C - Planning 8 days Mon 03/12/12Wed 12/12/12
10 Task 3 20 days Thu 13/12/12 Wed 09/01/13
11 A - Proposal 6 days Thu 13/12/12 Thu 20/12/12
12 B - Pitch 3 days Mon 07/01/13Wed 09/01/13
13 Task 4 3 days Thu 10/01/13 Mon 14/01/13
14 A - Production 3 days Thu 10/01/13 Mon
Meeting 14/01/13
15 Task 5 5 days Tue 15/01/13 Mon 21/01/13
16 A - Video Assets 5 days Tue 15/01/13 Mon 21/01/13
17 Task 6 7 days Tue 22/01/13 Wed 30/01/13
18 A - Shoot Video 7 days Tue 22/01/13 Wed 30/01/13
19
20 Additional Buffer Time 2 days Thu 31/01/13 Fri 01/02/13
Task External Milestone Manual Summary Rollup
Split Inactive Task Manual Summary
Project: Project Plan Milestone Inactive Milestone Start-only
Date: Wed 07/11/12 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress
Page 1
2. ID Task Task Name Duration Start Finish Predecessors 05 Nov '12 12 Nov '12 19 Nov '12
Mode M T W T F S S M T W T F S S M T W T
21 End Unit 4, 5, & 62 2 days Mon Tue 05/02/13
Assignment 2 04/02/13
22
23 Start Unit 4, 5, & 62 66 days Mon Mon
Assignment 3 18/02/13 20/05/13
24 Task 1 2 days Mon 18/02/13Tue 19/02/13
25 A - Import Video 2 days Mon Tue 19/02/13
with Diary 18/02/13
26 Task 2 15 days Wed 20/02/13Tue 12/03/13
27 A - Edit Video 15 days Wed 20/02/13Tue 12/03/13
28 Task 3 11 days Wed 13/03/13Wed 27/03/13
29 A - Export Video 2 days Wed 13/03/13Thu 14/03/13
30 B - Gather Feedback 4 days Fri 15/03/13 Wed
20/03/13
31 C - Create a Report 5 days Thu 21/03/13 Wed 27/03/13
32 Task 4 7 days Thu 28/03/13 Fri 05/04/13
33 A - Create a 4 days Thu 28/03/13 Tue 02/04/13
Questionnaire
34 B - End of Project 3 days Wed Fri 05/04/13
Meeting with Client 03/04/13
35 Task 5 10 days Mon 08/04/13Fri 19/04/13
36 Evaluation 10 days Mon 08/04/13Fri 19/04/13
37
Task External Milestone Manual Summary Rollup
Split Inactive Task Manual Summary
Project: Project Plan Milestone Inactive Milestone Start-only
Date: Wed 07/11/12 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress
Page 2
3. ID Task Task Name Duration Start Finish Predecessors 05 Nov '12 12 Nov '12 19 Nov '12
Mode M T W T F S S M T W T F S S M T W T
38 End Unit 4, 5, & 62 2 days Mon Tue 23/04/13
Assignment 3 22/04/13
Task External Milestone Manual Summary Rollup
Split Inactive Task Manual Summary
Project: Project Plan Milestone Inactive Milestone Start-only
Date: Wed 07/11/12 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress
Page 3
4. ov '12 26 Nov '12 03 Dec '12 10 Dec '12 17 Dec '12 24 Dec '12 31 Dec '12
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
Task External Milestone Manual Summary Rollup
Split Inactive Task Manual Summary
Project: Project Plan Milestone Inactive Milestone Start-only
Date: Wed 07/11/12 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress
Page 4
5. ov '12 26 Nov '12 03 Dec '12 10 Dec '12 17 Dec '12 24 Dec '12 31 Dec '12
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
Task External Milestone Manual Summary Rollup
Split Inactive Task Manual Summary
Project: Project Plan Milestone Inactive Milestone Start-only
Date: Wed 07/11/12 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress
Page 5
6. ov '12 26 Nov '12 03 Dec '12 10 Dec '12 17 Dec '12 24 Dec '12 31 Dec '12
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
Task External Milestone Manual Summary Rollup
Split Inactive Task Manual Summary
Project: Project Plan Milestone Inactive Milestone Start-only
Date: Wed 07/11/12 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress
Page 6
7. 07 Jan '13 14 Jan '13 21 Jan '13 28 Jan '13 04 Feb '13 11 Feb '13 18 Feb '13
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Task External Milestone Manual Summary Rollup
Split Inactive Task Manual Summary
Project: Project Plan Milestone Inactive Milestone Start-only
Date: Wed 07/11/12 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress
Page 7
8. 07 Jan '13 14 Jan '13 21 Jan '13 28 Jan '13 04 Feb '13 11 Feb '13 18 Feb '13
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Task External Milestone Manual Summary Rollup
Split Inactive Task Manual Summary
Project: Project Plan Milestone Inactive Milestone Start-only
Date: Wed 07/11/12 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress
Page 8
9. 07 Jan '13 14 Jan '13 21 Jan '13 28 Jan '13 04 Feb '13 11 Feb '13 18 Feb '13
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Task External Milestone Manual Summary Rollup
Split Inactive Task Manual Summary
Project: Project Plan Milestone Inactive Milestone Start-only
Date: Wed 07/11/12 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress
Page 9
10. 3 25 Feb '13 04 Mar '13 11 Mar '13 18 Mar '13 25 Mar '13 01 Apr '13 08 Apr '13
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
Task External Milestone Manual Summary Rollup
Split Inactive Task Manual Summary
Project: Project Plan Milestone Inactive Milestone Start-only
Date: Wed 07/11/12 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress
Page 10
11. 3 25 Feb '13 04 Mar '13 11 Mar '13 18 Mar '13 25 Mar '13 01 Apr '13 08 Apr '13
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
Task External Milestone Manual Summary Rollup
Split Inactive Task Manual Summary
Project: Project Plan Milestone Inactive Milestone Start-only
Date: Wed 07/11/12 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress
Page 11
12. 3 25 Feb '13 04 Mar '13 11 Mar '13 18 Mar '13 25 Mar '13 01 Apr '13 08 Apr '13
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
Task External Milestone Manual Summary Rollup
Split Inactive Task Manual Summary
Project: Project Plan Milestone Inactive Milestone Start-only
Date: Wed 07/11/12 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress
Page 12
13. 08 Apr '13 15 Apr '13 22 Apr '13 29 Apr '13 06 May '13 13 May '13 20 May '13
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Task External Milestone Manual Summary Rollup
Split Inactive Task Manual Summary
Project: Project Plan Milestone Inactive Milestone Start-only
Date: Wed 07/11/12 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress
Page 13
14. 08 Apr '13 15 Apr '13 22 Apr '13 29 Apr '13 06 May '13 13 May '13 20 May '13
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Task External Milestone Manual Summary Rollup
Split Inactive Task Manual Summary
Project: Project Plan Milestone Inactive Milestone Start-only
Date: Wed 07/11/12 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress
Page 14
15. 08 Apr '13 15 Apr '13 22 Apr '13 29 Apr '13 06 May '13 13 May '13 20 May '13
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Task External Milestone Manual Summary Rollup
Split Inactive Task Manual Summary
Project: Project Plan Milestone Inactive Milestone Start-only
Date: Wed 07/11/12 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress
Page 15