SlideShare une entreprise Scribd logo
1  sur  9
Télécharger pour lire hors ligne
International Journal of Managing Value and Supply Chains (IJMVSC) Vol. 6, No. 2, June 2015
DOI: 10.5121/ijmvsc.2015.6203 27
REDUCTION OF WORK IN PROCESS
INVENTORY AND PRODUCTION LEAD
TIME IN A BEARING INDUSTRY USING
VALUE STREAM MAPPING TOOL
Praveen Saraswat1
, Deepak Kumar2
and Manoj Kumar Sain3
1
Senior Lecturer, 2,3
Associate Professor
1,3
Swami Keshvanand Institute of Technology, Jaipur
2
Poornima College of Engineering, Jaipur
ABSTRACT
Manufacturers always face cost-reduction and efficiency challenges in their operations. Industries require
improvement in Production Lead Times, costs and customer service levels to survive. Because of this,
companies have become more customers focused. The result is that companies have been putting in
significant effort to improve their efficiency.
In this paper Value Stream Mapping (VSM) tool is used in bearing manufacturing industry by focusing
both on processes and their cycle times for a product UC- 208 INNER which is used in plumber block. In
order to use the value stream mapping, relevant data has been collected and analyzed. After collecting the
data customer need was identified. Current state map was draw by defining the resources and activities
needed to manufacture, deliver the product. The study of current state map shows the areas for
improvement and identifying the different types of wastes. From the current state map, it was noticeable
that Annealing and CNC Machining processing have higher cycle time and work in process.
The lean principles and techniques implemented or suggested and future state map was created and the
total lead time was reduced from 7.3 days to 3.8 days. The WIP at each work station has also been
reduced. The production lead time was reduced from 409 seconds to 344 seconds.
KEYWORDS
Lean Principles, Value Stream Mapping, Wastes, Work in Process, Production Lead Time
1. INTRODUCTION
Industries upset more capital and resources to improve their productivity. It is necessary to
optimize their capital, time and working environment. Industries needed improvements tools to
optimize its processes to attain more capable results. Many improvement techniques and tools
were developed and adapted to work in the different types of business.
Now day’s industries focused on more production with higher efficiency in less lead time. The
companies focused mainly on customer satisfaction. In an increasingly competitive environment,
International Journal of Managing Value and Supply Chains (IJMVSC) Vol. 6, No. 2, June 2015
28
many manufacturing firms are looking for a winning card over their competition. Manufacturers
have to understand that the conventional production system has to connect with the lean tools and
techniques. Lean manufacturing system was developed by Toyota, Japan.
2. VALUE STREAM MAPPING
Value Stream Mapping (VSM) tool shows all the activities, from supply to final product through
the different processing steps.. In other words it is a sketch of a production line [1].
Value stream map is the techniques that bring the all processing steps at one place. It shows the
big picture of shop floor rather than individual processes and improving the each area at the
production line. It is used to draw attention to different wastes and eliminating them in future
state map.
It is necessary that every process as closely as possible produces only what its customers need
when they need it. The existing processes have some types the waste in a production line which is
the result of product design and machinery
3. LITERATURE REVIEW
Value Stream Mapping (VSM) is used to define and analyze the current state for a product value
stream and design a future state focused on reducing waste, improving lead-time, and improving
workflow [2].A value stream map provides a blueprint for implementing lean manufacturing
concepts by illustrating how the flow of information and materials should operate [3]. VSM is
divided into two components: big picture mapping and detailed mapping [4]. Rajenthirakumar
and R.G. Shankar reported a noticeable reduction in cycle time and increase in cycle efficiency
with an application of value stream mapping (VSM). The production flow was optimized thus
minimizing several non-value added activities/times such as bottleneck time, waiting time,
material handling time, etc. [5]. K. P. Paranitharan provide useful platform for research in
implementation of lean tools in any manufacturing unit. Their results show a significant
improvement in productivity, reduction of Production Lead Time and reduction in inventory.
These can be achieved by creating flow by layout modification and balance to TAKT time
[6].R.M. Belokar reported a case study of application of VSM in an automobile industry where
they achieved nearly 67% improvement in cycle time by improvement in value adding activities
[7]. The conclusion of literature review is shown in below table.
International Journal of Managing Value and Supply Chains (IJMVSC) Vol. 6, No. 2, June 2015
29
Table 1 Inventory and Lead time of different industries
4. RESEARCH METHODOLOGY
The research objective is to reduce the production lead time and WIP in order to increase the
production rate in TEI Company, Jaipur so that customer order demand can be fulfill. Batch
processing in full capacity and bottlenecks in the production process are key contributors to long
Production Lead Times. The results of the research would have direct impact on product
Production Lead Time and WIP which would aid in reducing cost and meeting customer demand.
Figure-1 Methodology Steps for Implementing Value Stream Mapping
The following strategies were applied for achieving the methodology steps:
• Detail of product, processes and other information obtained from company.
• Time studies for finding the time duration & data collected from shop floor observation.
• For drawing current and future state value map E draw software was used.
International Journal of Managing Value and Supply Chains (IJMVSC) Vol. 6, No. 2, June 2015
30
The current information was collected directly from the company by talks and discussions with
managers, owner, and production supervisors. Example of such information is customer demand,
general process flow, supply of raw material etc. Time studies were conducted to get exact
information regarding cycle time, changeover time within each processing steps. The time studies
gave the observed value of time for individual processes.
Information about cycle time, changeover time, and number of operators involved in each
processing steps, amount of inventory and work-in progress between processes was determined.
Current map was drawn which shows the material and information flow. Takt time was calculated
and compared to average cycle time. The different areas were identified which needed
improvement. Thereafter, future state map was developed followed by some suggestions. Lean
tools and techniques were suggested for improvising the material and information flow.
5. PREPARATION OF CURRENT STATE VALUE STREAM MAP
Current state VSM is used to map work processes, material flow, and information flow. For this
project Edraw software is used to create current state and future state VSMs. E-Draw Max is a
vector-based diagramming application with rich examples and templates. Easy to create flow
charts, organizational charts, busi-ness process, UML diagrams, work flows, program structures,
net-work diagrams, chart and graphics, mind map, directional maps and database diagrams.
Table 2 Value Stream map input data
Customer Order 5000 (one week)
Working Hours Two shift with 12 hours per day
Break One hour/shift
Raw Material Weekly
Working Day/ Week 6 days
International Journal of Managing Value and Supply Chains (IJMVSC) Vol. 6, No. 2, June 2015
31
Figure- 2 Current state value stream map
6. ANALYSIS OF CURRENT STATE MAP
(a)Identification of non value adding activities
The actual value added time is 400 seconds and the lead time is 7.3 days so it is clear that the
ratio of value added time to lead time is vey less.
There is a transportation waste from CNC machining to Drilling process, it takes 3 minutes. CNC
machining is done on ground floor while drilling & threading is done on first floor which leads to
increase the unnecessary time between the processes.
The furnace is a bottleneck for the CNC machining process. The capacity of the furnace is low
due to which there is WIP worth of 1.3 days accumulates before it. The other reason for high
accumulation of inventory is the method of production in large batch sizes.
(b) TAKT time calculation
Weekly demand = 5000	units
Available working day in a week = 6 days
Demand per day =
ହ଴଴଴
଺
= 833	units
TAKT	Time =
Net	available	time	per	day
	Customer	demand	per	day
International Journal of Managing Value and Supply Chains (IJMVSC) Vol. 6, No. 2, June 2015
32
																												=
79200
833
= 95	seconds
Figure- 3 Comparison between Cycle time and Takt time
7. FUTURE STATE MAP
The future state map is draw to give propose suggestions and recommendations for improvement
in the current position of the company.
0
20
40
60
80
100
120
140
Timeinsecondes
Processes
Cycle time
Takt time
International Journal of Managing Value and Supply Chains (IJMVSC) Vol. 6, No. 2, June 2015
33
Figure- 4 Future state map
In future state map the total work station is 5.Supermarket is used for storage of WIP in future for
storage of WIP, this reduces the excessive WIP at annealing. Production kanban is also used
which give the storage information to the work cell (Bar cutting, Upsetting, Piercing) for
maintaining the production. A warehouse is introduced in the future map for storage of raw
material. Whenever there is requirement, raw material is available so inventory reduced at first
work station. The capacity of annealing furnace will be increased to double so cycle times reduce
to half. At CNC machining work station it is proposed to have one more CNC machine. The WIP
at CNC machining reduced. After that there is another work cell which combines Drilling and
threading process. The no of operator will reduce at this work cell. At last work station the no of
operator increased to two which reduce the WIP at Inspection & Packing.
8. RESULTS & SUGGESTIONS
Comparative study show the significant reduction occurs in WIP and Production Lead Time.
Value stream mapping technique was used to draw maps and after applying some tools and
giving somesuggestions for the product.
International Journal of Managing Value and Supply Chains (IJMVSC) Vol. 6, No. 2, June 2015
34
Table- 3 Reduction in work in process of different processes
Processes
WIP in
Current map
WIP in
Future map
%
Reduction
Annealing 2000 610 69.7 %
CNC Machining 1200 600 50 %
Drilling &
Threading
1790 580 67.6 %
Inspection &
Packing
880 305 65.4 %
Table- 4 Reduction in production lead time
Time Current state
map
Future state
map
% reduction
Production Lead Time 7.3 days 3.8 days 48 %
Total Processing Time 409 seconds 344 seconds 15.9 %
Value stream mapping analysis at TEI gives the areas which have different types of wastes and
require a lot of improvement. So following suggestions are advised to TEI regarding the shop
floor activities improvement.
I. As shown in current state map there was no proper place for the storage. A warehouse
can be there for storage purpose. It improves the handling of raw material.
II. As shown in current state map the drilling and threading operation carried out on first
floor which results in unnecessary motion. So it is advised to TEI that these operations can
continue with CNC machining on ground floor.
III. For easy flow of work in process inventory supermarket can be used in between the
processes. It results in pull system in the production line.
IV. There was no free space for finished product or shipping product at the end. Management
suggested that 5S lean technique can be used to improve the working environment.
V. It is necessary that cycle time should be near about takt time. It can be achieved by
balancing the production line.
CONCLUSION
This research study describes how the value mapping can be used to visualize graphically the
flow of material and flow of information from customer order to finish product. With this
approach (VSM) wastes in the company can be reduced.
The measure of success of value stream mapping in this research was address on how one could
reduce the wastes identified through the value stream mapping. The results indicate that TEI
should be incorporate production kanban, pull system and supermarket wherever possible
according to the customer satisfaction.
International Journal of Managing Value and Supply Chains (IJMVSC) Vol. 6, No. 2, June 2015
35
It can be concluded that VSM study has been able to highlight a number of unnecessary activities
in the process of manufacturing of bearing components. These activities have been connected to
waste such as WIP, storage and longer Production lead time etc.
REFERENCES
[1] J. P. Womack, D. T. Jones, and D. Ross, The machine that changed the world. New York: Harper
Collins Publishers, 1991.
[2] M. Rother and J. Shook, Learning to see: Value stream mapping to add value and eliminate muda,
2nd ed. Brookline, MA: The Lean Enterprise Institute Inc, 1999.
[3] M. Rother and J. Shook, Learning to See: Value Stream Mapping to create value and eliminate muda.
Brrokline, USA: The Lean Enterprise Institute, 1999.
[4] Hines P, Taylor D. Going lean. Cardiff, UK: Lean Enterprise Research Centre Cardiff Business
School, 2000.
[5] D. Rajendrakumar and R. Gowtham Shankar, "Analyzing the Benefits of Lean Tools: A Consumar
Durables Manufacturing Company Case study," International Journal of Engineering, 2011.
[6] K. P. Paranitharan, "Redesinging an Automotive Assembly Line Through Lean Strategy,"
International Journal of Lean thinking, 2011.
[7] R.M. Belokar and Vikas Kumar, " An Application of Value Stream Mapping In Automotive Industry:
A Case Study," International Journal of Innovative Technology and Exploring Engineering, 2012.
[8] D. Rajenthirakumar & S.G. Harikarthik, "Process Cycle Efficiency Improvement through Lean: A
Case Study," International Journal of Lean Thinking, 2011.
[9] Meng B, D. Mingyao, Research on the Lean Process Reengineering Based on Value Stream Mapping.
Management Science and Engineering, Vol. 6, No. 2, 2012, pp. 103-106, 2012.
[10] D. Rajenthirakumar,P.R. Thyla, Transformation to Lean Manufacturing By an Automative
Component Manufacturing Company. International Journal of Lean Thinking Volume 2, Issue 2,
2011.
[11] D. Rajenthirakumar, P. R. Thyla & John Paul Ajay, Implementation of Lean Assembly Line: A Case
Study, International Journal of Engineering, tome VIII, Fascicule 3, 2010.
[12] Singh, B., and Sharma, S. K. , “Value stream mapping as a versatile tool for lean implementation: an
Indian case study of a manufacturing firm”, Measuring Business Excellence, Vol. 13, No. 3, pp. 58-
68,2009.
[13] Brunt, D. From current state to future state: Mapping the steel to component supply chain.
International Journal of Logistics: Research and Applications, 3, (3), 259-271, 2000.
[14] Ritesh R. Bhat and Prof. S. Shivakumar, “Improving the Productivity using Value Stream Mapping
and Kanban Approach”, International Journal of Scientific & Engineering Research Volume 2, Issue
8, August-2011.

Contenu connexe

Tendances

IRJET- Optimization of Machining Facility Layout by using Simulation: Cas...
IRJET-  	  Optimization of Machining Facility Layout by using Simulation: Cas...IRJET-  	  Optimization of Machining Facility Layout by using Simulation: Cas...
IRJET- Optimization of Machining Facility Layout by using Simulation: Cas...IRJET Journal
 
Agent-Based Modeling: Methods and Techniques for Scheduling Industrial Machin...
Agent-Based Modeling: Methods and Techniques for Scheduling Industrial Machin...Agent-Based Modeling: Methods and Techniques for Scheduling Industrial Machin...
Agent-Based Modeling: Methods and Techniques for Scheduling Industrial Machin...ijtsrd
 
Capacity resource planning and production scheduling
Capacity resource planning and production schedulingCapacity resource planning and production scheduling
Capacity resource planning and production schedulingdutconsult
 
Process Design and Development of Engine Block
Process Design and Development of Engine BlockProcess Design and Development of Engine Block
Process Design and Development of Engine Blockpaperpublications3
 
Facility Layout/Production Planning & Control(PPC)/ Method Study/ Capacity Pl...
Facility Layout/Production Planning & Control(PPC)/ Method Study/ Capacity Pl...Facility Layout/Production Planning & Control(PPC)/ Method Study/ Capacity Pl...
Facility Layout/Production Planning & Control(PPC)/ Method Study/ Capacity Pl...viveksangwan007
 
Production And Operation Materials
Production And Operation MaterialsProduction And Operation Materials
Production And Operation Materialspikuoec
 
Software Solution for Production Planning and Scheduling
Software Solution for Production Planning and SchedulingSoftware Solution for Production Planning and Scheduling
Software Solution for Production Planning and SchedulingIRJET Journal
 
Suggestions on the Methodology of Parameters in Fused Deposition Modeling Pro...
Suggestions on the Methodology of Parameters in Fused Deposition Modeling Pro...Suggestions on the Methodology of Parameters in Fused Deposition Modeling Pro...
Suggestions on the Methodology of Parameters in Fused Deposition Modeling Pro...IRJESJOURNAL
 
PRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMP
PRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMPPRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMP
PRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMPmeijjournal
 
Productivity improvement by using value stream mapping in stainless steel ut...
Productivity improvement by using value stream mapping in  stainless steel ut...Productivity improvement by using value stream mapping in  stainless steel ut...
Productivity improvement by using value stream mapping in stainless steel ut...vivatechijri
 
M.tech (Production and Industrial Engineering) Thesis Presentation
M.tech (Production and Industrial Engineering) Thesis PresentationM.tech (Production and Industrial Engineering) Thesis Presentation
M.tech (Production and Industrial Engineering) Thesis PresentationSanchit Jain
 
IRJET- Production Plan and Control
IRJET- Production Plan and ControlIRJET- Production Plan and Control
IRJET- Production Plan and ControlIRJET Journal
 
Industrial Engineering unit 4.Production planning and control Notes by badebhau.
Industrial Engineering unit 4.Production planning and control Notes by badebhau.Industrial Engineering unit 4.Production planning and control Notes by badebhau.
Industrial Engineering unit 4.Production planning and control Notes by badebhau.Er. Bade Bhausaheb
 

Tendances (20)

IRJET- Optimization of Machining Facility Layout by using Simulation: Cas...
IRJET-  	  Optimization of Machining Facility Layout by using Simulation: Cas...IRJET-  	  Optimization of Machining Facility Layout by using Simulation: Cas...
IRJET- Optimization of Machining Facility Layout by using Simulation: Cas...
 
Integration of process planning and scheduling comparison of models approach
Integration of process planning and scheduling comparison of models approachIntegration of process planning and scheduling comparison of models approach
Integration of process planning and scheduling comparison of models approach
 
Agent-Based Modeling: Methods and Techniques for Scheduling Industrial Machin...
Agent-Based Modeling: Methods and Techniques for Scheduling Industrial Machin...Agent-Based Modeling: Methods and Techniques for Scheduling Industrial Machin...
Agent-Based Modeling: Methods and Techniques for Scheduling Industrial Machin...
 
Value stream mapping
Value stream mappingValue stream mapping
Value stream mapping
 
Ppc 2 m and 16m
Ppc 2 m and 16mPpc 2 m and 16m
Ppc 2 m and 16m
 
Capacity resource planning and production scheduling
Capacity resource planning and production schedulingCapacity resource planning and production scheduling
Capacity resource planning and production scheduling
 
Process Design and Development of Engine Block
Process Design and Development of Engine BlockProcess Design and Development of Engine Block
Process Design and Development of Engine Block
 
Facility Layout/Production Planning & Control(PPC)/ Method Study/ Capacity Pl...
Facility Layout/Production Planning & Control(PPC)/ Method Study/ Capacity Pl...Facility Layout/Production Planning & Control(PPC)/ Method Study/ Capacity Pl...
Facility Layout/Production Planning & Control(PPC)/ Method Study/ Capacity Pl...
 
Report
ReportReport
Report
 
Ppc 2mark answer
Ppc 2mark answerPpc 2mark answer
Ppc 2mark answer
 
Production And Operation Materials
Production And Operation MaterialsProduction And Operation Materials
Production And Operation Materials
 
Lead Time Reduction of Power Control Center (Pcc) Electric Panel by Lean Phil...
Lead Time Reduction of Power Control Center (Pcc) Electric Panel by Lean Phil...Lead Time Reduction of Power Control Center (Pcc) Electric Panel by Lean Phil...
Lead Time Reduction of Power Control Center (Pcc) Electric Panel by Lean Phil...
 
Software Solution for Production Planning and Scheduling
Software Solution for Production Planning and SchedulingSoftware Solution for Production Planning and Scheduling
Software Solution for Production Planning and Scheduling
 
Suggestions on the Methodology of Parameters in Fused Deposition Modeling Pro...
Suggestions on the Methodology of Parameters in Fused Deposition Modeling Pro...Suggestions on the Methodology of Parameters in Fused Deposition Modeling Pro...
Suggestions on the Methodology of Parameters in Fused Deposition Modeling Pro...
 
PRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMP
PRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMPPRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMP
PRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMP
 
Productivity improvement by using value stream mapping in stainless steel ut...
Productivity improvement by using value stream mapping in  stainless steel ut...Productivity improvement by using value stream mapping in  stainless steel ut...
Productivity improvement by using value stream mapping in stainless steel ut...
 
M.tech (Production and Industrial Engineering) Thesis Presentation
M.tech (Production and Industrial Engineering) Thesis PresentationM.tech (Production and Industrial Engineering) Thesis Presentation
M.tech (Production and Industrial Engineering) Thesis Presentation
 
IRJET- Production Plan and Control
IRJET- Production Plan and ControlIRJET- Production Plan and Control
IRJET- Production Plan and Control
 
Industrial Engineering unit 4.Production planning and control Notes by badebhau.
Industrial Engineering unit 4.Production planning and control Notes by badebhau.Industrial Engineering unit 4.Production planning and control Notes by badebhau.
Industrial Engineering unit 4.Production planning and control Notes by badebhau.
 
IE
IEIE
IE
 

En vedette

Eşkenar Üçgen-Yıldızlı soru
Eşkenar Üçgen-Yıldızlı soruEşkenar Üçgen-Yıldızlı soru
Eşkenar Üçgen-Yıldızlı soruosman
 
How to double_your_income_in_12_months_tip_8
How to double_your_income_in_12_months_tip_8How to double_your_income_in_12_months_tip_8
How to double_your_income_in_12_months_tip_8Shonda Miles
 
Om0010 operations management
Om0010 operations managementOm0010 operations management
Om0010 operations managementconsult4solutions
 
How do business organizations manage change, why is it usually resisted
How do business organizations manage change, why is it usually resistedHow do business organizations manage change, why is it usually resisted
How do business organizations manage change, why is it usually resistedSirajo Danhassan
 
Sperry Van Ness #CRE National Sales Meeting 11-10-14
Sperry Van Ness #CRE National Sales Meeting 11-10-14Sperry Van Ness #CRE National Sales Meeting 11-10-14
Sperry Van Ness #CRE National Sales Meeting 11-10-14SVN International Corp.
 
RogerDauzatReferenceLetter
RogerDauzatReferenceLetterRogerDauzatReferenceLetter
RogerDauzatReferenceLetterCurtis Brown
 
Navy and Marine Corps Achievement Medal
Navy and Marine Corps Achievement MedalNavy and Marine Corps Achievement Medal
Navy and Marine Corps Achievement MedalYegor Zubarev
 
Wardell+Odom+Jr.doc1
Wardell+Odom+Jr.doc1Wardell+Odom+Jr.doc1
Wardell+Odom+Jr.doc1Wardell Odom
 

En vedette (11)

Eşkenar Üçgen-Yıldızlı soru
Eşkenar Üçgen-Yıldızlı soruEşkenar Üçgen-Yıldızlı soru
Eşkenar Üçgen-Yıldızlı soru
 
Tugas mtk 4
Tugas mtk 4Tugas mtk 4
Tugas mtk 4
 
Meeting overview context, aims, challenges
Meeting overview context, aims, challengesMeeting overview context, aims, challenges
Meeting overview context, aims, challenges
 
How to double_your_income_in_12_months_tip_8
How to double_your_income_in_12_months_tip_8How to double_your_income_in_12_months_tip_8
How to double_your_income_in_12_months_tip_8
 
Om0010 operations management
Om0010 operations managementOm0010 operations management
Om0010 operations management
 
How do business organizations manage change, why is it usually resisted
How do business organizations manage change, why is it usually resistedHow do business organizations manage change, why is it usually resisted
How do business organizations manage change, why is it usually resisted
 
Dss64 2
Dss64 2Dss64 2
Dss64 2
 
Sperry Van Ness #CRE National Sales Meeting 11-10-14
Sperry Van Ness #CRE National Sales Meeting 11-10-14Sperry Van Ness #CRE National Sales Meeting 11-10-14
Sperry Van Ness #CRE National Sales Meeting 11-10-14
 
RogerDauzatReferenceLetter
RogerDauzatReferenceLetterRogerDauzatReferenceLetter
RogerDauzatReferenceLetter
 
Navy and Marine Corps Achievement Medal
Navy and Marine Corps Achievement MedalNavy and Marine Corps Achievement Medal
Navy and Marine Corps Achievement Medal
 
Wardell+Odom+Jr.doc1
Wardell+Odom+Jr.doc1Wardell+Odom+Jr.doc1
Wardell+Odom+Jr.doc1
 

Similaire à Iss 9

IRJET - Analysis of Process Re-Engineering to Reduce Lead Time in Apparel Ind...
IRJET - Analysis of Process Re-Engineering to Reduce Lead Time in Apparel Ind...IRJET - Analysis of Process Re-Engineering to Reduce Lead Time in Apparel Ind...
IRJET - Analysis of Process Re-Engineering to Reduce Lead Time in Apparel Ind...IRJET Journal
 
Application of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryApplication of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryijmech
 
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump IndustryManufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump IndustryIRJET Journal
 
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...PERUMALSAMY M
 
IRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
IRJET-Productivity Improvement in a Pressure Vessel using Lean PrinciplesIRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
IRJET-Productivity Improvement in a Pressure Vessel using Lean PrinciplesIRJET Journal
 
Line Balancing and facility optimization of Machine Shop with Work Study and ...
Line Balancing and facility optimization of Machine Shop with Work Study and ...Line Balancing and facility optimization of Machine Shop with Work Study and ...
Line Balancing and facility optimization of Machine Shop with Work Study and ...IRJET Journal
 
IRJET- Enhance the Capacity of Outer Tube Machining Cell
IRJET-  	  Enhance the Capacity of Outer Tube Machining CellIRJET-  	  Enhance the Capacity of Outer Tube Machining Cell
IRJET- Enhance the Capacity of Outer Tube Machining CellIRJET Journal
 
Improvement of Productivity Using Value Stream Mapping
Improvement of Productivity Using Value Stream MappingImprovement of Productivity Using Value Stream Mapping
Improvement of Productivity Using Value Stream Mappingijsrd.com
 
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing FacilityIRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing FacilityIRJET Journal
 
PALCO INDUSTRY USING VALUE STREAM MAPPING
PALCO INDUSTRY USING VALUE STREAM MAPPINGPALCO INDUSTRY USING VALUE STREAM MAPPING
PALCO INDUSTRY USING VALUE STREAM MAPPINGFuratAj
 
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
IRJET-  	  Efficiency Enhancement by Reducing Production and Machining TimeIRJET-  	  Efficiency Enhancement by Reducing Production and Machining Time
IRJET- Efficiency Enhancement by Reducing Production and Machining TimeIRJET Journal
 
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A ReviewIRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A ReviewIRJET Journal
 
Improvement of supply chain process using Maynard Operation Sequence Techniqu...
Improvement of supply chain process using Maynard Operation Sequence Techniqu...Improvement of supply chain process using Maynard Operation Sequence Techniqu...
Improvement of supply chain process using Maynard Operation Sequence Techniqu...IRJET Journal
 
Analysis and Reduction of Production Waste in the Process of Production of Fr...
Analysis and Reduction of Production Waste in the Process of Production of Fr...Analysis and Reduction of Production Waste in the Process of Production of Fr...
Analysis and Reduction of Production Waste in the Process of Production of Fr...IRJET Journal
 
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...IRJET Journal
 
IRJET- Improving Productivity in a Mechanical Industry using Industrial Engin...
IRJET- Improving Productivity in a Mechanical Industry using Industrial Engin...IRJET- Improving Productivity in a Mechanical Industry using Industrial Engin...
IRJET- Improving Productivity in a Mechanical Industry using Industrial Engin...IRJET Journal
 
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...Karina Islam
 
Value Analysis of A Rubber Hose Moulding and Assembly Line: A Case Study
Value Analysis of A Rubber Hose Moulding and Assembly Line: A Case StudyValue Analysis of A Rubber Hose Moulding and Assembly Line: A Case Study
Value Analysis of A Rubber Hose Moulding and Assembly Line: A Case StudyIRJET Journal
 
applicationof vsm
applicationof vsmapplicationof vsm
applicationof vsmAro Ephrem
 
Application Of Lean Manufacturing Tools And Techniques A Case Study In A Man...
Application Of Lean Manufacturing Tools And Techniques  A Case Study In A Man...Application Of Lean Manufacturing Tools And Techniques  A Case Study In A Man...
Application Of Lean Manufacturing Tools And Techniques A Case Study In A Man...Anna Landers
 

Similaire à Iss 9 (20)

IRJET - Analysis of Process Re-Engineering to Reduce Lead Time in Apparel Ind...
IRJET - Analysis of Process Re-Engineering to Reduce Lead Time in Apparel Ind...IRJET - Analysis of Process Re-Engineering to Reduce Lead Time in Apparel Ind...
IRJET - Analysis of Process Re-Engineering to Reduce Lead Time in Apparel Ind...
 
Application of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryApplication of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industry
 
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump IndustryManufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
 
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...
 
IRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
IRJET-Productivity Improvement in a Pressure Vessel using Lean PrinciplesIRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
IRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
 
Line Balancing and facility optimization of Machine Shop with Work Study and ...
Line Balancing and facility optimization of Machine Shop with Work Study and ...Line Balancing and facility optimization of Machine Shop with Work Study and ...
Line Balancing and facility optimization of Machine Shop with Work Study and ...
 
IRJET- Enhance the Capacity of Outer Tube Machining Cell
IRJET-  	  Enhance the Capacity of Outer Tube Machining CellIRJET-  	  Enhance the Capacity of Outer Tube Machining Cell
IRJET- Enhance the Capacity of Outer Tube Machining Cell
 
Improvement of Productivity Using Value Stream Mapping
Improvement of Productivity Using Value Stream MappingImprovement of Productivity Using Value Stream Mapping
Improvement of Productivity Using Value Stream Mapping
 
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing FacilityIRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
 
PALCO INDUSTRY USING VALUE STREAM MAPPING
PALCO INDUSTRY USING VALUE STREAM MAPPINGPALCO INDUSTRY USING VALUE STREAM MAPPING
PALCO INDUSTRY USING VALUE STREAM MAPPING
 
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
IRJET-  	  Efficiency Enhancement by Reducing Production and Machining TimeIRJET-  	  Efficiency Enhancement by Reducing Production and Machining Time
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
 
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A ReviewIRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
 
Improvement of supply chain process using Maynard Operation Sequence Techniqu...
Improvement of supply chain process using Maynard Operation Sequence Techniqu...Improvement of supply chain process using Maynard Operation Sequence Techniqu...
Improvement of supply chain process using Maynard Operation Sequence Techniqu...
 
Analysis and Reduction of Production Waste in the Process of Production of Fr...
Analysis and Reduction of Production Waste in the Process of Production of Fr...Analysis and Reduction of Production Waste in the Process of Production of Fr...
Analysis and Reduction of Production Waste in the Process of Production of Fr...
 
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
 
IRJET- Improving Productivity in a Mechanical Industry using Industrial Engin...
IRJET- Improving Productivity in a Mechanical Industry using Industrial Engin...IRJET- Improving Productivity in a Mechanical Industry using Industrial Engin...
IRJET- Improving Productivity in a Mechanical Industry using Industrial Engin...
 
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
 
Value Analysis of A Rubber Hose Moulding and Assembly Line: A Case Study
Value Analysis of A Rubber Hose Moulding and Assembly Line: A Case StudyValue Analysis of A Rubber Hose Moulding and Assembly Line: A Case Study
Value Analysis of A Rubber Hose Moulding and Assembly Line: A Case Study
 
applicationof vsm
applicationof vsmapplicationof vsm
applicationof vsm
 
Application Of Lean Manufacturing Tools And Techniques A Case Study In A Man...
Application Of Lean Manufacturing Tools And Techniques  A Case Study In A Man...Application Of Lean Manufacturing Tools And Techniques  A Case Study In A Man...
Application Of Lean Manufacturing Tools And Techniques A Case Study In A Man...
 

Iss 9

  • 1. International Journal of Managing Value and Supply Chains (IJMVSC) Vol. 6, No. 2, June 2015 DOI: 10.5121/ijmvsc.2015.6203 27 REDUCTION OF WORK IN PROCESS INVENTORY AND PRODUCTION LEAD TIME IN A BEARING INDUSTRY USING VALUE STREAM MAPPING TOOL Praveen Saraswat1 , Deepak Kumar2 and Manoj Kumar Sain3 1 Senior Lecturer, 2,3 Associate Professor 1,3 Swami Keshvanand Institute of Technology, Jaipur 2 Poornima College of Engineering, Jaipur ABSTRACT Manufacturers always face cost-reduction and efficiency challenges in their operations. Industries require improvement in Production Lead Times, costs and customer service levels to survive. Because of this, companies have become more customers focused. The result is that companies have been putting in significant effort to improve their efficiency. In this paper Value Stream Mapping (VSM) tool is used in bearing manufacturing industry by focusing both on processes and their cycle times for a product UC- 208 INNER which is used in plumber block. In order to use the value stream mapping, relevant data has been collected and analyzed. After collecting the data customer need was identified. Current state map was draw by defining the resources and activities needed to manufacture, deliver the product. The study of current state map shows the areas for improvement and identifying the different types of wastes. From the current state map, it was noticeable that Annealing and CNC Machining processing have higher cycle time and work in process. The lean principles and techniques implemented or suggested and future state map was created and the total lead time was reduced from 7.3 days to 3.8 days. The WIP at each work station has also been reduced. The production lead time was reduced from 409 seconds to 344 seconds. KEYWORDS Lean Principles, Value Stream Mapping, Wastes, Work in Process, Production Lead Time 1. INTRODUCTION Industries upset more capital and resources to improve their productivity. It is necessary to optimize their capital, time and working environment. Industries needed improvements tools to optimize its processes to attain more capable results. Many improvement techniques and tools were developed and adapted to work in the different types of business. Now day’s industries focused on more production with higher efficiency in less lead time. The companies focused mainly on customer satisfaction. In an increasingly competitive environment,
  • 2. International Journal of Managing Value and Supply Chains (IJMVSC) Vol. 6, No. 2, June 2015 28 many manufacturing firms are looking for a winning card over their competition. Manufacturers have to understand that the conventional production system has to connect with the lean tools and techniques. Lean manufacturing system was developed by Toyota, Japan. 2. VALUE STREAM MAPPING Value Stream Mapping (VSM) tool shows all the activities, from supply to final product through the different processing steps.. In other words it is a sketch of a production line [1]. Value stream map is the techniques that bring the all processing steps at one place. It shows the big picture of shop floor rather than individual processes and improving the each area at the production line. It is used to draw attention to different wastes and eliminating them in future state map. It is necessary that every process as closely as possible produces only what its customers need when they need it. The existing processes have some types the waste in a production line which is the result of product design and machinery 3. LITERATURE REVIEW Value Stream Mapping (VSM) is used to define and analyze the current state for a product value stream and design a future state focused on reducing waste, improving lead-time, and improving workflow [2].A value stream map provides a blueprint for implementing lean manufacturing concepts by illustrating how the flow of information and materials should operate [3]. VSM is divided into two components: big picture mapping and detailed mapping [4]. Rajenthirakumar and R.G. Shankar reported a noticeable reduction in cycle time and increase in cycle efficiency with an application of value stream mapping (VSM). The production flow was optimized thus minimizing several non-value added activities/times such as bottleneck time, waiting time, material handling time, etc. [5]. K. P. Paranitharan provide useful platform for research in implementation of lean tools in any manufacturing unit. Their results show a significant improvement in productivity, reduction of Production Lead Time and reduction in inventory. These can be achieved by creating flow by layout modification and balance to TAKT time [6].R.M. Belokar reported a case study of application of VSM in an automobile industry where they achieved nearly 67% improvement in cycle time by improvement in value adding activities [7]. The conclusion of literature review is shown in below table.
  • 3. International Journal of Managing Value and Supply Chains (IJMVSC) Vol. 6, No. 2, June 2015 29 Table 1 Inventory and Lead time of different industries 4. RESEARCH METHODOLOGY The research objective is to reduce the production lead time and WIP in order to increase the production rate in TEI Company, Jaipur so that customer order demand can be fulfill. Batch processing in full capacity and bottlenecks in the production process are key contributors to long Production Lead Times. The results of the research would have direct impact on product Production Lead Time and WIP which would aid in reducing cost and meeting customer demand. Figure-1 Methodology Steps for Implementing Value Stream Mapping The following strategies were applied for achieving the methodology steps: • Detail of product, processes and other information obtained from company. • Time studies for finding the time duration & data collected from shop floor observation. • For drawing current and future state value map E draw software was used.
  • 4. International Journal of Managing Value and Supply Chains (IJMVSC) Vol. 6, No. 2, June 2015 30 The current information was collected directly from the company by talks and discussions with managers, owner, and production supervisors. Example of such information is customer demand, general process flow, supply of raw material etc. Time studies were conducted to get exact information regarding cycle time, changeover time within each processing steps. The time studies gave the observed value of time for individual processes. Information about cycle time, changeover time, and number of operators involved in each processing steps, amount of inventory and work-in progress between processes was determined. Current map was drawn which shows the material and information flow. Takt time was calculated and compared to average cycle time. The different areas were identified which needed improvement. Thereafter, future state map was developed followed by some suggestions. Lean tools and techniques were suggested for improvising the material and information flow. 5. PREPARATION OF CURRENT STATE VALUE STREAM MAP Current state VSM is used to map work processes, material flow, and information flow. For this project Edraw software is used to create current state and future state VSMs. E-Draw Max is a vector-based diagramming application with rich examples and templates. Easy to create flow charts, organizational charts, busi-ness process, UML diagrams, work flows, program structures, net-work diagrams, chart and graphics, mind map, directional maps and database diagrams. Table 2 Value Stream map input data Customer Order 5000 (one week) Working Hours Two shift with 12 hours per day Break One hour/shift Raw Material Weekly Working Day/ Week 6 days
  • 5. International Journal of Managing Value and Supply Chains (IJMVSC) Vol. 6, No. 2, June 2015 31 Figure- 2 Current state value stream map 6. ANALYSIS OF CURRENT STATE MAP (a)Identification of non value adding activities The actual value added time is 400 seconds and the lead time is 7.3 days so it is clear that the ratio of value added time to lead time is vey less. There is a transportation waste from CNC machining to Drilling process, it takes 3 minutes. CNC machining is done on ground floor while drilling & threading is done on first floor which leads to increase the unnecessary time between the processes. The furnace is a bottleneck for the CNC machining process. The capacity of the furnace is low due to which there is WIP worth of 1.3 days accumulates before it. The other reason for high accumulation of inventory is the method of production in large batch sizes. (b) TAKT time calculation Weekly demand = 5000 units Available working day in a week = 6 days Demand per day = ହ଴଴଴ ଺ = 833 units TAKT Time = Net available time per day Customer demand per day
  • 6. International Journal of Managing Value and Supply Chains (IJMVSC) Vol. 6, No. 2, June 2015 32 = 79200 833 = 95 seconds Figure- 3 Comparison between Cycle time and Takt time 7. FUTURE STATE MAP The future state map is draw to give propose suggestions and recommendations for improvement in the current position of the company. 0 20 40 60 80 100 120 140 Timeinsecondes Processes Cycle time Takt time
  • 7. International Journal of Managing Value and Supply Chains (IJMVSC) Vol. 6, No. 2, June 2015 33 Figure- 4 Future state map In future state map the total work station is 5.Supermarket is used for storage of WIP in future for storage of WIP, this reduces the excessive WIP at annealing. Production kanban is also used which give the storage information to the work cell (Bar cutting, Upsetting, Piercing) for maintaining the production. A warehouse is introduced in the future map for storage of raw material. Whenever there is requirement, raw material is available so inventory reduced at first work station. The capacity of annealing furnace will be increased to double so cycle times reduce to half. At CNC machining work station it is proposed to have one more CNC machine. The WIP at CNC machining reduced. After that there is another work cell which combines Drilling and threading process. The no of operator will reduce at this work cell. At last work station the no of operator increased to two which reduce the WIP at Inspection & Packing. 8. RESULTS & SUGGESTIONS Comparative study show the significant reduction occurs in WIP and Production Lead Time. Value stream mapping technique was used to draw maps and after applying some tools and giving somesuggestions for the product.
  • 8. International Journal of Managing Value and Supply Chains (IJMVSC) Vol. 6, No. 2, June 2015 34 Table- 3 Reduction in work in process of different processes Processes WIP in Current map WIP in Future map % Reduction Annealing 2000 610 69.7 % CNC Machining 1200 600 50 % Drilling & Threading 1790 580 67.6 % Inspection & Packing 880 305 65.4 % Table- 4 Reduction in production lead time Time Current state map Future state map % reduction Production Lead Time 7.3 days 3.8 days 48 % Total Processing Time 409 seconds 344 seconds 15.9 % Value stream mapping analysis at TEI gives the areas which have different types of wastes and require a lot of improvement. So following suggestions are advised to TEI regarding the shop floor activities improvement. I. As shown in current state map there was no proper place for the storage. A warehouse can be there for storage purpose. It improves the handling of raw material. II. As shown in current state map the drilling and threading operation carried out on first floor which results in unnecessary motion. So it is advised to TEI that these operations can continue with CNC machining on ground floor. III. For easy flow of work in process inventory supermarket can be used in between the processes. It results in pull system in the production line. IV. There was no free space for finished product or shipping product at the end. Management suggested that 5S lean technique can be used to improve the working environment. V. It is necessary that cycle time should be near about takt time. It can be achieved by balancing the production line. CONCLUSION This research study describes how the value mapping can be used to visualize graphically the flow of material and flow of information from customer order to finish product. With this approach (VSM) wastes in the company can be reduced. The measure of success of value stream mapping in this research was address on how one could reduce the wastes identified through the value stream mapping. The results indicate that TEI should be incorporate production kanban, pull system and supermarket wherever possible according to the customer satisfaction.
  • 9. International Journal of Managing Value and Supply Chains (IJMVSC) Vol. 6, No. 2, June 2015 35 It can be concluded that VSM study has been able to highlight a number of unnecessary activities in the process of manufacturing of bearing components. These activities have been connected to waste such as WIP, storage and longer Production lead time etc. REFERENCES [1] J. P. Womack, D. T. Jones, and D. Ross, The machine that changed the world. New York: Harper Collins Publishers, 1991. [2] M. Rother and J. Shook, Learning to see: Value stream mapping to add value and eliminate muda, 2nd ed. Brookline, MA: The Lean Enterprise Institute Inc, 1999. [3] M. Rother and J. Shook, Learning to See: Value Stream Mapping to create value and eliminate muda. Brrokline, USA: The Lean Enterprise Institute, 1999. [4] Hines P, Taylor D. Going lean. Cardiff, UK: Lean Enterprise Research Centre Cardiff Business School, 2000. [5] D. Rajendrakumar and R. Gowtham Shankar, "Analyzing the Benefits of Lean Tools: A Consumar Durables Manufacturing Company Case study," International Journal of Engineering, 2011. [6] K. P. Paranitharan, "Redesinging an Automotive Assembly Line Through Lean Strategy," International Journal of Lean thinking, 2011. [7] R.M. Belokar and Vikas Kumar, " An Application of Value Stream Mapping In Automotive Industry: A Case Study," International Journal of Innovative Technology and Exploring Engineering, 2012. [8] D. Rajenthirakumar & S.G. Harikarthik, "Process Cycle Efficiency Improvement through Lean: A Case Study," International Journal of Lean Thinking, 2011. [9] Meng B, D. Mingyao, Research on the Lean Process Reengineering Based on Value Stream Mapping. Management Science and Engineering, Vol. 6, No. 2, 2012, pp. 103-106, 2012. [10] D. Rajenthirakumar,P.R. Thyla, Transformation to Lean Manufacturing By an Automative Component Manufacturing Company. International Journal of Lean Thinking Volume 2, Issue 2, 2011. [11] D. Rajenthirakumar, P. R. Thyla & John Paul Ajay, Implementation of Lean Assembly Line: A Case Study, International Journal of Engineering, tome VIII, Fascicule 3, 2010. [12] Singh, B., and Sharma, S. K. , “Value stream mapping as a versatile tool for lean implementation: an Indian case study of a manufacturing firm”, Measuring Business Excellence, Vol. 13, No. 3, pp. 58- 68,2009. [13] Brunt, D. From current state to future state: Mapping the steel to component supply chain. International Journal of Logistics: Research and Applications, 3, (3), 259-271, 2000. [14] Ritesh R. Bhat and Prof. S. Shivakumar, “Improving the Productivity using Value Stream Mapping and Kanban Approach”, International Journal of Scientific & Engineering Research Volume 2, Issue 8, August-2011.