Presentation and interview with Peter de Jager at the Project Manager Success Summit about the Mythical Man-Month. Great lesson for PMs, Program Managers and team leaders. Host: Michael Charles, PMP of the PM Leadership Coach (www.pmleadershipcoach.com, http://www.projectmanagersuccesssummit.com)
To listen to the interview sign up free of charge at http://www.projectmanagersuccesssummit.com.
4. Published
1975
Tales
from
OS/360
Frederick
P.
Brooks
Jr.
–
Addison-‐Wesley
www.pmleadershipcoach.com
5. It
was
late
It
didn’t
meet
the
specs
It
exceeded
the
budget
It
didn’t
meet
expectations
www.pmleadershipcoach.com
6. The Man-Month is a fallacious
and dangerous Myth
...it implies that people and months
are interchangeable
www.pmleadershipcoach.com
7. Adding people
to a late
Project
makes it later…
www.pmleadershipcoach.com
8. Good cooking takes time.
If you are made to wait,
it is to serve you better,
and to please you.
Restaurant Antoine,
New Orleans
www.pmleadershipcoach.com
9. The Joy of learning
The Joy of Making things
The Pleasure of making things of value
The Fascination of making complex objects
The Delight of turning ideas into real world
www.pmleadershipcoach.com
10. One must perform
perfectly
Other people
set our objectives
The little details are just work
Debugging has a linear convergence
What you’re working on
is already obsolete
www.pmleadershipcoach.com
13. 1) We Estimate poorly
2) We Fallaciously confuse
effort with progress
3) We lack the ‘polite’
stubbornness of a Chef
4) We monitor Status poorly
5) When we fall behind,
we add more people
www.pmleadershipcoach.com
14. It takes 3 Cats…
3 Minutes…
to Catch 3 Mice
How many Cats…
Do we need to Catch
100 mice within 100 Minutes?
www.pmleadershipcoach.com
15. Which is it?
3 cats take100 Minutes...
1 Min/mouse
3 cats take102 Minutes...
3 Min/mouse
At 99 min? 99 mouses
www.pmleadershipcoach.com
31. Regenerative Schedule Disaster
12 man-month project + 3 workers? = 4 months.
But… it takes 2 months to reach first
monthly milestone… what to do?
www.pmleadershipcoach.com
32. Possible response? With 2 months calendar time
left?
-Assume estimate was sort of ‘correct’…
Of the original 12 mths? 9 months of effort
remain.
2 mths calendar left… Add 2 workers to the orig
3…
www.pmleadershipcoach.com
33. Possible response? With 2 months calendar time
left?
- Accept that original estimate was totally wrong.
18 mths of effort 2mth calendar left – add 6
to 3
www.pmleadershipcoach.com
34. Possible response? With 2 months calendar time
left?
Admit the promised deadline isn’t doable
Re-estimate the project based on what we know
www.pmleadershipcoach.com