Panchayat and Rural Development Department
        Government Of Madhya Pradesh


                 MGNREGS in MP
   Presentation before the Empowered Committee
          Ministry of Rural Development
                Government of India

                 19th March, 2012
MGNREGS in Madhya Pradesh

From Wage
Employment
                …… to
Livelihoods
Structure of Presentation
•   Structured Implementation Strategy- MP Model
•   Progress so far
•   Incomplete Works
•   Financial Inclusion
•   Complaints
•   Social Audit
•   Proposal 2012-13
•   Issues for discussion
                                               3
State Profile
      Area              3,08,245 Sq km
Revenue Division              10
    Districts                 50
     Blocks                   313
  Tribal Blocks               89
Village Panchayats           23,040
     Villages                54,903
   Population            7,25,97,565
Rural Population         5,25,37,899
    Literacy                 70.6%
MGNREGS in Madhya Pradesh



 In tune with the provisions of the Act, main
  aim is enhancement of livelihood security of
  rural households. Accordingly structured
  and planned implementation through
  convergence of MGNREGS with other
  Government schemes.

                                           5
Scheme Focus
     As per Item No 1 of Schedule I of NGNREGS Act 2005, the scheme focus
                             on the following works

i.   Water Conservation and harvesting – Management of Natural
     Resources
ii. Draught proofing (i/c Plantation) - Management of Natural
     Resources
iii. Micro and Minor works and Irrigation canals – Rural
     Infrastructure
iv. Irrigation facility to individual farmers (SC/ST etc) – Livelihood
     Enhancement
v. Renovation of water bodies (i/c desilting of Tanks)-Management
     of Natural Resources
vi. Land Development – Livelihood Enhancement
vii. Flood control and drainage - Management of Natural Resources
                                                                   6
viii.Rural connectivity – Rural Infrastructure
Convergence
Convergence with funds from MGNREGS and other sources on
the following pre-conditions:

 •   Convergence resorted to only for achieving goals of the Act.
 •   MGNREGS component implemented and accounted
     separately as per provisions of the Act.
 •   60:40 ratio maintained and contractors not permitted
 •   Labour replacing machinery not permitted.
 •   MIS, Muster rolls and accounting as per MGNREGS.
 •   Only works permitted under MGNREGS act are taken up.
 •   Component related to non MGNREGS funds implemented
     as per relevant guidelines

     Convergence is being done with State funds, Funds from
     BRGF, MLA LADS, Panchayat funds from Stamp Duty etc 7
Structured Implementation of MGNREGS

                Convergence
               for Livelihood
               Enhancement -              Livelihood
                 Item 1(iv),(vi)*



             Convergence for
             Natural Resource             Convergence for
              Management                       Rural
              Item 1(i),(ii),(v),(vii)*    Infrastructure
                                          Item 1 (iii),(viii)*




                                                                 8
* Shedule-1 of MGNREGS Act, 2005
Structured Implementation of
                    MGNREGS in Madhya Pradesh
           Irrigation Wells                                  Watershed
                                                            Development
    Horticulture
                                                       Narmada Valley
                                                         Watershed
     Fisheries                                          Development

 Development of                  Livelihood
 Forest Dwellers'               Enhancement                  Community
       land                                                  Afforestation

 Land Development
                                                               Internal
                                                                Roads
Gravel Roads
                                                                Leach Pit
   Rural         Water Course                  Cremation           and
Playground                       Drinking                       Plantation
                  and Field                     Ground
                                Water Wells                            9
                  Channels                    Development
Progress in Madhya Pradesh
                                            Financial Year
                   2006-07   2007-08    2008-09    2009-10   2010-11       2011- 12
     Item                                                                (Jan. 2013)
 Districts under     18        31         50         50        50               50
  MGNREGS
  Households         28        43         52       47.22      43.84            34.11
Demanded Work
     (Lakh)
Mandays (Crore)     19.81    27.53       29.46     26.23      22.04            13.78
    Families        5.32      9.12       9.79       7.31      4.65             1.35
 Completed 100
   days work
     Total         1862.69 2892.67      3551.67   3779.71    3641.79      2602.83
  Expenditure
                                       Total Expenditure             18831.36
                                       (Rs. Crore)
      Since inception of
                                       Mandays (Crore)                138.85     10
         MGNREGS
Irrigation Wells
    3.24 Lakh Hectare additional
    irrigation under MGNREGS

   3.70 Lakh Wells Sanctioned
   2.21 Lakh Wells Completed
   2387 Crore Expenditure

Convergence for Water Lifting Devices
    from SGSY and State Funds
Land
           Development


   2.58 Lakh Beneficiaries
    Covered
   630 Crore Expenditure
   Very popular sub-scheme in
    tribal dominated Districts.




                                  12
Horticulture
            Development

   31988 Farms Covered
   100.00 Crore Expenditure

Convergence with SGSY, NHM, NRLM
          and State Funds




                                   13
Watershed
         Development
    11.81 Lakh Hectare Covered
    178 Crore Expenditure

    Convergence with IWMP and State
                Funds




                                      14
Drinking Water
             Wells


   23600 Wells Completed
   517 Crore Expenditure




                            15
Leaching Pits and
    Court-yard Plantation
    1.20 Lakh Households Covered
    246 Crore Expenditure

      Convergence with TSC and
       Horticulture Department




                                    16
Single Connectivity
    through Convergence
    Earthwork completed in 2700
     road works having 3850 km
     length.
    Expenditure 165.50 Cr.



     Single Connectivity - Embankment Construction through MGNREGS




                                                                17
Convergence
       Single Connectivity through Gravel Roads
 9,019 Habitation below PMGSY Connectivity norms covered
  under this Sub-Scheme
 7,575 Roads having 19,386 km length proposed for completion
 Rs. 3,634 Crore Total estimated Expenditure
    Convergence of MGNREGS, BRGF, Mandi Funds and State Funds

      State Funds Component                – Rs. 2,486 Crore
      MGNREGS Component                    – Rs. 495 Crore
      Mandi Fund Component                 – Rs. 350 Crore
      BRGF Component                       – Rs. 303 Crore
      Total estimated expenditure          – Rs. 3,634 Crore

Earth Work in Embankment being taken up through MGNREGS
 only in those districts, where Job Card holders are available for
                           unskilled work                      18
Base Course Gravel/CD Construction through Other Schemes




                                                           19
Completed Works




         20
Completed and Ongoing Works 2011-12
             Carry
                        New Works Works      Carried Over
 Year     Forward from
                        Sanctioned Completed to Next Year
          Previous Year
2008-09        -        5,63,033   28,546      5,34,487
2009-10     5,34,487    1,73,825   57,987      6,50,325
2010-11     6,50,325    1,65,669   1,42,963    6,73,031
                                                7,20,154
2011-12     6,73,031    1,51,535   1,04,412    (2,44,485
                                              completed)
Completed and Ongoing Works 2011-12

• Total no. of works                         :8,24,566

• Completed & MIS done                       :1,04,412 (Jan, 12)

• Completed & MIS pending                    :2,44,485 (Jan, 12)

• Likely carry over to next year             :4,75,669
• Average Number of works per GP             :20 nos.
(Including beneficiary oriented works like TSC, Irrigation wells,
Land and Farm development)
Completed and Ongoing Works 2011-12

• Special drive to MIS completed works to be
  launched this year (July-August)

• Boost received in 2011 after Government of India
  allowed partial closure.

• A large no. of 5 year plantation projects
  completing in 2012-13

• Induction of GRS & JE will boost CC formalities
  & MIS.
Financial Inclusion I

• Massive exercise to completely map the entire State
  w.r.t. FI.
• District wise villages in shadow area identified &
  planned for FI.
• Plans discussed in DLCC & SLBC by October, 2011.
  Total Village                :      52012
  Having FI within 5 km        :      37,245
  Shadow Villages              :      14,767
Financial Inclusion II

• For Normal Villages : Service Area Approach
• For Shadow Villages :Multi pronged approach
                       a)   Business Correspondent BC
                       b)   Mobile Banking
                       c)   Kiosk / ATM
                       d)   e- panchayat (proposed)
                       e)   Brick & Mortar Branches
Financial Inclusion III
                E-Panchayat Programme

• Ambitious plan for 23012 Panchayats
• Availability of
   a)   Building
   b)   Connectivity
   c)   Trained manpower
   d)   Hardware
   e)   Power
• Banks are welcome to use these facilities.
• Already operational in 2500 GP’s
Financial Inclusion IV

Plan of Concurrent Audit in GP’s
• One qualified fulltime auditor for a cluster of 7-10
  Gram Panchayats.
• Concurrent audit as well as basic record keeping &
  MIS handholding.
• Outsourced with support & monitoring from CAG
  & LFA offices.
• Senior team for Block & District level.
Delay in Payments
• Steps          : Recruitment of vacant JE’s.
                 :Strengthening MIS systems
                 :Appraisal Committee at State level
• IEC efforts    :Wage disbursement camps.
                 :Toll Free Call Centre
                 :Panchayat Puraskar Yojna
• ICT efforts    :On line demand tracking
                 :Pilots for e-MB
                 :Pilots for e-Panchayats
                 :SMS demand tracking
Issues with the Ministry

• New 330 proposed branches must be in
 shadow villages only.
• Shift from Population norms to geographical
 norms.
• Rs. 80/- per account for BC should be over &
 above admin. expenditure.
Complaint I

1. Grievance Redressal Mechanisms.
   • Rules to be notified.
   • 63 State Level quality monitors.
   • Toll Free Call Centre.
   • ‘Jan Sunvai’ every Tuesday all levels.
   • Active involvement of divisional
       commissioners.
   • Quarterly      review      in appraisal
       committee at State level.          30
Complaints II
                    Status of GoI Complaints

  Category       Year       Received Disposed Pending
    VIP         2008-09        2         2       0
                2009-10        7         6       1
                2010-11        41       25      16
                2011-12        11        3       8
   Geneal       2008-09        1         1       0
                2009-10        43       31      12
                2010-11        51       37      14
                2011-12        49        7      42
                                          Total 93
* 7 Complaints in VIP category & 13 Complaints in General category
    are missing/not received.                                31
Complaints III

 At the State level, action taken against the
  following officials:
  • 02 Collectors and 06 CEOs of District
     Panchayats
  • 133 CEOs of Janpad Panchayat
  • 07 Executive Engineers
  • 70 AEs, 216 Junior Engineers and 22 other
     officials
 FIR registered against 160 officials and Sarpanchs.
 Action taken against 746 Sarpanchs and 908
  Panchayat Secretaries.                          32
Social Audit I

• Mandatory Gram Sabha at Least 4 times in a
  year (26 Jan, 14 April, 15 August, 2 October)
• Nodal Officer for each Gram Sabha.
• 15 days prior notice.
• ATR of previous social audit compulsory.
• Many instances of action for not conducting
  Gram Shabha & social audit.
• 100% MIS of social audit for 2011-12 done.
                                                33
Social Audit II


• Constitution of an independent SAU is under
  process.
• Pilot project in Dhar district with partner
  NGO.
• PRI & NGO personals visited & trained in
  NIRD Hyderabad.
• Online software to enter observations.
                                                34
MPR V/S MIS

• Madhya Pradesh as a whole : 94%
• 28 out of 50 districts are      : 100%
• 17 out of 50 districts between : 90% & 100%
• 5 out of 50 districts are below : 90%
   Monthly review by CS in VC “Parakh”
   Active & competent State MIS cell to resolve
     issued.
   Continuous efforts to improve connectivity in
     remote districts.
                                                    35
The Proposal
 Year 2012-13


    Past Trends
    Demand
    Justification
                     36
Trends -Mandays and Expenditure
40.00                                                                            6000


35.00
                                                                                 5000

30.00                           29.47       26.23
                    27.53
                                                                    3800.00      4000
                                                        22.04
25.00                         3531.67
                                           3779.72
         19.81     2892.67                             3641.80
20.00                                                                 17.59      3000


15.00
        1862.69                                                                  2000

10.00
                                                                                 1000
 5.00

 0.00                                                                            0
        2006-07    2007-08    2008-09      2009-10     2010-11       2011-12
        Rs 63.00   Rs 85.00    Rs 91.00    Rs 100.00   Rs 100.00   (Projected)
                                                                     Rs 122.00
          Mandays (in Crore)            Expenditure (in Rs. Crore)
Sector-wise Expenditure Trends
   Land
Development
Rs. 1336 Cr.




                                  Rural
    Micro Irrigation           Connectivity
     + Irrigation              Rs. 6041 Cr.
      facility to
       Formers
     Rs. 4718 Cr.




               WC+Renovation
                   of WB                      Flood Control,
                Rs. 4537 Cr.                  DP and Misc.
                                               Rs. 1617 Cr.
Year-wise Expenditure on Various Work
                 Categories (Rs. Crore)
                                         Water
                             Flood    Conservation
                 Rural                              Micro Irri. +       Land
                            Control +  and Water
#     FY       Connectivi                          Irri. facility to Developmen
                            Drought Harv. + Reno.
                  ty                                ind. formers          t
                            Proofing    of Trad.
                                      Water Bodies
1  2006-07       795.92      140.43      688.77         141.2           61.67
2  2007-08      1137.03       255.6      780.31        525.87          128.42
3  2008-09      1102.26      353.08      836.43       1249.91           231.4
4  2009-10       983.44      366.19      698.52       1398.37          273.37
5  2010-11      1202.93      384.68      611.29       1089.31          351.39
   2011-12
                 819.67      117.74       921.96          314         290.04
6 ( Jan.,12)
  Total         6041.25     1617.72       4537.28       4718.66      1336.29
Year-Wise Quarterly Performance
                                                        (Expenditure in Rs. Crore
                                                           Mandays in Lakh)
               2008-09            2009-10              2010-11               2011-12
 Qtr
          Mandays    Exp.     Mandays    Exp.     Mandays    Exp.     Mandays      Exp.

I Qtr     1007.00   1308.65    927.00   1264.75    683.24   1019.70    412.00     887.89

II Qtr     452.00   706.63     277.00   598.28     308.56   691.94     445.00     750.06

III Qtr    464.00   368.25     758.00   920.12     396.72   509.85     343.00     660.45

IV Qtr    1024.00   1168.14    661.00   996.57     815.48   1420.30      -             -

 Total    2947.00   3551.67   2623.00   3779.72 2204.00     3641.80      -             -
Mandays and Expenditure
       FY 2008-09
                    Expenditure in Rs. Crore
                       Mandays in Lakh
Mandays and Expenditure
       FY 2009-10
                    Expenditure in Rs. Crore
                       Mandays in Lakh
Mandays and Expenditure
       FY 2010-11
                    Expenditure in Rs. Crore
                       Mandays in Lakh
Mandays and Expenditure
   FY 2011-12 (January)
                      Expenditure in Rs. Crore
                         Mandays in Lakh
Demand for 2012-13


• Total Mandays       : 29.19 Crore
• Total Expenditure   : Rs. 6,305 Crore
• No. Of HH Likely to demand
 employment           : 45 Lakh
• No. Of HH Likely to complete 100 days
                      : 9.89 Lakh
Month-wise Labour Projection 2012-13
               Number of
                                Number of Total       Estimated Total   Number of Households
            Households likely
   Month                      Person-days likely to   Expenditure (in   likely to complete 100
               to demand
                                  be generated            Lakhs)                days in
              employment
April         13,20,595          3,05,62,951             66,186                   0
May           16,35,633          5,81,59,489            1,25,815                180
June          19,87,138          8,37,19,094            1,81,485               22,924
July          21,05,828          9,87,82,741            2,14,329               78,797
August        22,09,939          11,10,28,591           2,40,737              1,24,217
September     26,52,280          12,90,10,580           2,79,423              1,55,128
October       30,14,545          14,99,80,056           3,20,113              2,13,202
November      33,94,378          17,62,49,627           3,82,795              3,12,824
December      37,94,219          20,46,84,503           4,43,183              4,18,124
January       41,50,363          23,21,70,246           5,02,637              5,51,804
February      43,59,376          28,00,06,515           5,69,183              7,96,378
                                                                                         46
March        45,55,188         29,19,24,000            6,30,556              9,89,437
Project Proposals for 2012-13
• Development of Land allotted to forest dwellers:
  – Total identified families               -1.50 Lakh
  – Families to be covered during 2012-13 - 65,000
  – Construction of irrigation wells and land
    development proposed.                    - Rs 2100Cr.
  – Person-days                              - 9.70 Cr
• Irrigation Wells for individual beneficiaries:
  – Beneficiaries to be covered            - 20,000
  – Estimated Cost                         - Rs 600 Cr.
  – Person-days                            - 2.80 Cr
                                                      47
Project Proposals for 2012-13
• Land development of individual formers:
  – Beneficiaries to be covered            – 1,00,000
  – Estimated Cost                         – Rs 500 Cr.
  – Person-days                            – 2.30 Cr.
• Horticulture development for individual formers
  and Afforestation:
  – Beneficiaries to be covered 10,000 hect – Rs 200 Cr
  – Afforestation 40,000 Hect               – Rs 550 Cr.
  – Person-days                             – 3.50 Cr

                                                      48
Project Proposals for 2012-13
• Construction of Water Courses:
  – Construction of Water Courses and Field Channels in
    Command area of NVDA
  – Estimated Cost                        – Rs 250 Cr.
  – Person-days                           - 2.40 Cr.
• TSC Toilets:
  – About 10 Lakh House holds to be covered
  – Estimated Cost                       - Rs 80 Cr.
  – Person–days @ 6 per unit             -0.60 Cr.
                                                    49
Project Proposals for 2012-13
• Single Connectivity with Convergence: Earth
  work on Roads providing connectivity to villages
  below PMGSY norms
  – Estimated Cost                    - Rs 300 Cr.
  – Person-days                       - 1.40 Cr.
• Multi Connectivity:
  – Estimated Cost                    - Rs 220 Cr.
  – Person-days                       - 1.00 Cr


                                                 50
Project Proposals for 2012-13
• Construction of Drinking Water Wells:
  – Estimated Cost                         - Rs. 300 Cr.
  – Person-days                            - 1.40 Cr.
• Water Shed Development:
  – 317 Cluster Selected, estimated Cost   - Rs 150 Cr.
  – Person-days                            - 0.70 Cr.
• Carry-over and Miscellaneous Works:
  – Estimated Cost                         - Rs 1055 Cr
  – Person-days                            - 3.40 Cr.
                                                      51
Issues

• Labour Cess on MGNREGA

• Demand for Houses for beneficiary

• Clarification on Ombudsman

• Participation in RSBY

• Convergence with MPLADS

                                      52
Thank you for your time




                          53

Contenu connexe

Tendances

Dieter Nill "20 years of watershed management in Niger: Approaches, impacts a...
Dieter Nill "20 years of watershed management in Niger: Approaches, impacts a...Dieter Nill "20 years of watershed management in Niger: Approaches, impacts a...
Dieter Nill "20 years of watershed management in Niger: Approaches, impacts a...
Global Risk Forum GRFDavos
 
Rpdm chapter10
Rpdm chapter10Rpdm chapter10
Rpdm chapter10
vtkannan
 
Presentation for outreach series final 10.25.11
Presentation for outreach series final 10.25.11Presentation for outreach series final 10.25.11
Presentation for outreach series final 10.25.11
thetomorrowplan
 

Tendances (15)

Dieter Nill "20 years of watershed management in Niger: Approaches, impacts a...
Dieter Nill "20 years of watershed management in Niger: Approaches, impacts a...Dieter Nill "20 years of watershed management in Niger: Approaches, impacts a...
Dieter Nill "20 years of watershed management in Niger: Approaches, impacts a...
 
The Impacts of Dam Construction on Natural Resource Access and the Livelihood...
The Impacts of Dam Construction on Natural Resource Access and the Livelihood...The Impacts of Dam Construction on Natural Resource Access and the Livelihood...
The Impacts of Dam Construction on Natural Resource Access and the Livelihood...
 
Master plan gual pahari 2021
Master plan gual pahari 2021Master plan gual pahari 2021
Master plan gual pahari 2021
 
Halfmoon Exit 9 Linkage Study
Halfmoon Exit 9 Linkage StudyHalfmoon Exit 9 Linkage Study
Halfmoon Exit 9 Linkage Study
 
Cl rb outputs
Cl rb outputsCl rb outputs
Cl rb outputs
 
Rpdm chapter10
Rpdm chapter10Rpdm chapter10
Rpdm chapter10
 
January 26 Planning Committee Meeting Extract
January 26 Planning Committee Meeting ExtractJanuary 26 Planning Committee Meeting Extract
January 26 Planning Committee Meeting Extract
 
Sugarcane Agroecological Zoning for Ethanol and Sugar production in Brazil
Sugarcane Agroecological Zoning for Ethanol and Sugar production in BrazilSugarcane Agroecological Zoning for Ethanol and Sugar production in Brazil
Sugarcane Agroecological Zoning for Ethanol and Sugar production in Brazil
 
Civic masterplan sector1-preface
Civic masterplan sector1-prefaceCivic masterplan sector1-preface
Civic masterplan sector1-preface
 
Civic masterplan sector1-small
Civic masterplan sector1-smallCivic masterplan sector1-small
Civic masterplan sector1-small
 
Understanding the Impact of Growth Plan Reforms
Understanding the Impact of Growth Plan ReformsUnderstanding the Impact of Growth Plan Reforms
Understanding the Impact of Growth Plan Reforms
 
Jaypee greens kensington boulevards
Jaypee greens kensington boulevards Jaypee greens kensington boulevards
Jaypee greens kensington boulevards
 
Presentation for outreach series final 10.25.11
Presentation for outreach series final 10.25.11Presentation for outreach series final 10.25.11
Presentation for outreach series final 10.25.11
 
Patricio Mansilla - Project Finance in LA
Patricio Mansilla - Project Finance in LAPatricio Mansilla - Project Finance in LA
Patricio Mansilla - Project Finance in LA
 
優化土地供應策略專題討論 3︰在維港以外填海 Enhancing Land Supply Strategy Topical Discussion 3: R...
優化土地供應策略專題討論 3︰在維港以外填海 Enhancing Land Supply Strategy Topical Discussion 3: R...優化土地供應策略專題討論 3︰在維港以外填海 Enhancing Land Supply Strategy Topical Discussion 3: R...
優化土地供應策略專題討論 3︰在維港以外填海 Enhancing Land Supply Strategy Topical Discussion 3: R...
 

En vedette

Greenwood Management forestry investment report
Greenwood Management forestry investment reportGreenwood Management forestry investment report
Greenwood Management forestry investment report
Greenwood Management
 
Shelterwood system kishor aryal
Shelterwood system   kishor aryalShelterwood system   kishor aryal
Shelterwood system kishor aryal
sahl_2fast
 
Shelterwood system jyoti ghimire
Shelterwood system   jyoti ghimireShelterwood system   jyoti ghimire
Shelterwood system jyoti ghimire
sahl_2fast
 

En vedette (10)

Smart_City
Smart_CitySmart_City
Smart_City
 
Greenwood Management forestry investment report
Greenwood Management forestry investment reportGreenwood Management forestry investment report
Greenwood Management forestry investment report
 
Nrega Guidelines Hindi
Nrega Guidelines HindiNrega Guidelines Hindi
Nrega Guidelines Hindi
 
Lokadalath udupi 2
Lokadalath udupi 2Lokadalath udupi 2
Lokadalath udupi 2
 
Shelterwood system kishor aryal
Shelterwood system   kishor aryalShelterwood system   kishor aryal
Shelterwood system kishor aryal
 
Shelterwood system jyoti ghimire
Shelterwood system   jyoti ghimireShelterwood system   jyoti ghimire
Shelterwood system jyoti ghimire
 
Urban dev dec 2015
Urban dev dec 2015Urban dev dec 2015
Urban dev dec 2015
 
Building laws
Building lawsBuilding laws
Building laws
 
Makalah smart city
Makalah smart cityMakalah smart city
Makalah smart city
 
Smart city presentation
Smart city presentationSmart city presentation
Smart city presentation
 

Similaire à Mg nrega mp march 2012

Rural Roads as Infrastructure for Economic Development
Rural Roads as Infrastructure for Economic DevelopmentRural Roads as Infrastructure for Economic Development
Rural Roads as Infrastructure for Economic Development
Iram Aziz
 
Grameen sahara dbi
Grameen sahara dbiGrameen sahara dbi
Grameen sahara dbi
santy12832
 
karnataka state budget 2012-13 Presented by Bharat R S
 karnataka state budget 2012-13 Presented by Bharat R S karnataka state budget 2012-13 Presented by Bharat R S
karnataka state budget 2012-13 Presented by Bharat R S
Bharat Yashu
 
Shankaraiah N :Watershed Program Present
Shankaraiah N :Watershed Program  PresentShankaraiah N :Watershed Program  Present
Shankaraiah N :Watershed Program Present
shankaraiah, N
 
Groundwater Management: Experiences of WASSAN
Groundwater Management: Experiences of WASSANGroundwater Management: Experiences of WASSAN
Groundwater Management: Experiences of WASSAN
India Water Portal
 
Integrated watershed management programme at gunjala village – a case study
Integrated watershed management programme at gunjala village – a case studyIntegrated watershed management programme at gunjala village – a case study
Integrated watershed management programme at gunjala village – a case study
eSAT Journals
 
German KUST "Sustainable land management oriented projects in Tajikistan: exp...
German KUST "Sustainable land management oriented projects in Tajikistan: exp...German KUST "Sustainable land management oriented projects in Tajikistan: exp...
German KUST "Sustainable land management oriented projects in Tajikistan: exp...
Global Risk Forum GRFDavos
 
1. gujarat gw presentation wb_may-2014 7052014
1. gujarat gw presentation wb_may-2014 70520141. gujarat gw presentation wb_may-2014 7052014
1. gujarat gw presentation wb_may-2014 7052014
hydrologywebsite1
 

Similaire à Mg nrega mp march 2012 (20)

Recent Projects Implemented (L)
Recent Projects Implemented (L)Recent Projects Implemented (L)
Recent Projects Implemented (L)
 
BAIF-MITTRA N'Bar DBI
BAIF-MITTRA N'Bar DBIBAIF-MITTRA N'Bar DBI
BAIF-MITTRA N'Bar DBI
 
Rural Roads as Infrastructure for Economic Development
Rural Roads as Infrastructure for Economic DevelopmentRural Roads as Infrastructure for Economic Development
Rural Roads as Infrastructure for Economic Development
 
Regional planning in Urban Development and Governance
Regional planning in Urban Development and GovernanceRegional planning in Urban Development and Governance
Regional planning in Urban Development and Governance
 
Grameen sahara dbi
Grameen sahara dbiGrameen sahara dbi
Grameen sahara dbi
 
karnataka state budget 2012-13 Presented by Bharat R S
 karnataka state budget 2012-13 Presented by Bharat R S karnataka state budget 2012-13 Presented by Bharat R S
karnataka state budget 2012-13 Presented by Bharat R S
 
Watershed development (civil)
Watershed development (civil)Watershed development (civil)
Watershed development (civil)
 
Shankaraiah N :Watershed Program Present
Shankaraiah N :Watershed Program  PresentShankaraiah N :Watershed Program  Present
Shankaraiah N :Watershed Program Present
 
Groundwater Management: Experiences of WASSAN
Groundwater Management: Experiences of WASSANGroundwater Management: Experiences of WASSAN
Groundwater Management: Experiences of WASSAN
 
Harsha Trust
Harsha TrustHarsha Trust
Harsha Trust
 
Nirman odisha
Nirman odishaNirman odisha
Nirman odisha
 
Nirman odisha
Nirman odishaNirman odisha
Nirman odisha
 
CONNECTKaro 2015 - Land Management For Smart Cities - Naya Raipur
CONNECTKaro 2015 - Land Management For Smart Cities - Naya RaipurCONNECTKaro 2015 - Land Management For Smart Cities - Naya Raipur
CONNECTKaro 2015 - Land Management For Smart Cities - Naya Raipur
 
Integrated watershed management programme at gunjala village – a case study
Integrated watershed management programme at gunjala village – a case studyIntegrated watershed management programme at gunjala village – a case study
Integrated watershed management programme at gunjala village – a case study
 
IWRM in Karnataka India. Crafting a New Future
IWRM in Karnataka India. Crafting a New FutureIWRM in Karnataka India. Crafting a New Future
IWRM in Karnataka India. Crafting a New Future
 
German KUST "Sustainable land management oriented projects in Tajikistan: exp...
German KUST "Sustainable land management oriented projects in Tajikistan: exp...German KUST "Sustainable land management oriented projects in Tajikistan: exp...
German KUST "Sustainable land management oriented projects in Tajikistan: exp...
 
Harnessing VCMs for Agricultural Finance and Transitions - global stocktake
Harnessing VCMs for Agricultural Finance and Transitions - global stocktakeHarnessing VCMs for Agricultural Finance and Transitions - global stocktake
Harnessing VCMs for Agricultural Finance and Transitions - global stocktake
 
Wb final presentation
Wb final presentationWb final presentation
Wb final presentation
 
Mahatma Gandhi National Rural Employment Guarantee
Mahatma Gandhi National Rural Employment Guarantee Mahatma Gandhi National Rural Employment Guarantee
Mahatma Gandhi National Rural Employment Guarantee
 
1. gujarat gw presentation wb_may-2014 7052014
1. gujarat gw presentation wb_may-2014 70520141. gujarat gw presentation wb_may-2014 7052014
1. gujarat gw presentation wb_may-2014 7052014
 

Dernier

VIP Call Girl Service Andheri West ⚡ 9920725232 What It Takes To Be The Best ...
VIP Call Girl Service Andheri West ⚡ 9920725232 What It Takes To Be The Best ...VIP Call Girl Service Andheri West ⚡ 9920725232 What It Takes To Be The Best ...
VIP Call Girl Service Andheri West ⚡ 9920725232 What It Takes To Be The Best ...
dipikadinghjn ( Why You Choose Us? ) Escorts
 

Dernier (20)

Booking open Available Pune Call Girls Talegaon Dabhade 6297143586 Call Hot ...
Booking open Available Pune Call Girls Talegaon Dabhade  6297143586 Call Hot ...Booking open Available Pune Call Girls Talegaon Dabhade  6297143586 Call Hot ...
Booking open Available Pune Call Girls Talegaon Dabhade 6297143586 Call Hot ...
 
00_Main ppt_MeetupDORA&CyberSecurity.pptx
00_Main ppt_MeetupDORA&CyberSecurity.pptx00_Main ppt_MeetupDORA&CyberSecurity.pptx
00_Main ppt_MeetupDORA&CyberSecurity.pptx
 
Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...
Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...
Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...
 
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsHigh Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...
Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...
Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...
 
VIP Call Girl Service Andheri West ⚡ 9920725232 What It Takes To Be The Best ...
VIP Call Girl Service Andheri West ⚡ 9920725232 What It Takes To Be The Best ...VIP Call Girl Service Andheri West ⚡ 9920725232 What It Takes To Be The Best ...
VIP Call Girl Service Andheri West ⚡ 9920725232 What It Takes To Be The Best ...
 
VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...
VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...
VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...
 
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...
 
(INDIRA) Call Girl Mumbai Call Now 8250077686 Mumbai Escorts 24x7
(INDIRA) Call Girl Mumbai Call Now 8250077686 Mumbai Escorts 24x7(INDIRA) Call Girl Mumbai Call Now 8250077686 Mumbai Escorts 24x7
(INDIRA) Call Girl Mumbai Call Now 8250077686 Mumbai Escorts 24x7
 
The Economic History of the U.S. Lecture 18.pdf
The Economic History of the U.S. Lecture 18.pdfThe Economic History of the U.S. Lecture 18.pdf
The Economic History of the U.S. Lecture 18.pdf
 
Best VIP Call Girls Noida Sector 18 Call Me: 8448380779
Best VIP Call Girls Noida Sector 18 Call Me: 8448380779Best VIP Call Girls Noida Sector 18 Call Me: 8448380779
Best VIP Call Girls Noida Sector 18 Call Me: 8448380779
 
02_Fabio Colombo_Accenture_MeetupDora&Cybersecurity.pptx
02_Fabio Colombo_Accenture_MeetupDora&Cybersecurity.pptx02_Fabio Colombo_Accenture_MeetupDora&Cybersecurity.pptx
02_Fabio Colombo_Accenture_MeetupDora&Cybersecurity.pptx
 
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service NashikHigh Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
 
Indore Real Estate Market Trends Report.pdf
Indore Real Estate Market Trends Report.pdfIndore Real Estate Market Trends Report.pdf
Indore Real Estate Market Trends Report.pdf
 
The Economic History of the U.S. Lecture 25.pdf
The Economic History of the U.S. Lecture 25.pdfThe Economic History of the U.S. Lecture 25.pdf
The Economic History of the U.S. Lecture 25.pdf
 
The Economic History of the U.S. Lecture 19.pdf
The Economic History of the U.S. Lecture 19.pdfThe Economic History of the U.S. Lecture 19.pdf
The Economic History of the U.S. Lecture 19.pdf
 
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure service
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure serviceCall US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure service
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure service
 
Call Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance Booking
 
The Economic History of the U.S. Lecture 17.pdf
The Economic History of the U.S. Lecture 17.pdfThe Economic History of the U.S. Lecture 17.pdf
The Economic History of the U.S. Lecture 17.pdf
 
(DIYA) Bhumkar Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(DIYA) Bhumkar Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(DIYA) Bhumkar Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(DIYA) Bhumkar Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

Mg nrega mp march 2012

  • 1. Panchayat and Rural Development Department Government Of Madhya Pradesh MGNREGS in MP Presentation before the Empowered Committee Ministry of Rural Development Government of India 19th March, 2012
  • 2. MGNREGS in Madhya Pradesh From Wage Employment …… to Livelihoods
  • 3. Structure of Presentation • Structured Implementation Strategy- MP Model • Progress so far • Incomplete Works • Financial Inclusion • Complaints • Social Audit • Proposal 2012-13 • Issues for discussion 3
  • 4. State Profile Area 3,08,245 Sq km Revenue Division 10 Districts 50 Blocks 313 Tribal Blocks 89 Village Panchayats 23,040 Villages 54,903 Population 7,25,97,565 Rural Population 5,25,37,899 Literacy 70.6%
  • 5. MGNREGS in Madhya Pradesh  In tune with the provisions of the Act, main aim is enhancement of livelihood security of rural households. Accordingly structured and planned implementation through convergence of MGNREGS with other Government schemes. 5
  • 6. Scheme Focus As per Item No 1 of Schedule I of NGNREGS Act 2005, the scheme focus on the following works i. Water Conservation and harvesting – Management of Natural Resources ii. Draught proofing (i/c Plantation) - Management of Natural Resources iii. Micro and Minor works and Irrigation canals – Rural Infrastructure iv. Irrigation facility to individual farmers (SC/ST etc) – Livelihood Enhancement v. Renovation of water bodies (i/c desilting of Tanks)-Management of Natural Resources vi. Land Development – Livelihood Enhancement vii. Flood control and drainage - Management of Natural Resources 6 viii.Rural connectivity – Rural Infrastructure
  • 7. Convergence Convergence with funds from MGNREGS and other sources on the following pre-conditions: • Convergence resorted to only for achieving goals of the Act. • MGNREGS component implemented and accounted separately as per provisions of the Act. • 60:40 ratio maintained and contractors not permitted • Labour replacing machinery not permitted. • MIS, Muster rolls and accounting as per MGNREGS. • Only works permitted under MGNREGS act are taken up. • Component related to non MGNREGS funds implemented as per relevant guidelines Convergence is being done with State funds, Funds from BRGF, MLA LADS, Panchayat funds from Stamp Duty etc 7
  • 8. Structured Implementation of MGNREGS Convergence for Livelihood Enhancement - Livelihood Item 1(iv),(vi)* Convergence for Natural Resource Convergence for Management Rural Item 1(i),(ii),(v),(vii)* Infrastructure Item 1 (iii),(viii)* 8 * Shedule-1 of MGNREGS Act, 2005
  • 9. Structured Implementation of MGNREGS in Madhya Pradesh Irrigation Wells Watershed Development Horticulture Narmada Valley Watershed Fisheries Development Development of Livelihood Forest Dwellers' Enhancement Community land Afforestation Land Development Internal Roads Gravel Roads Leach Pit Rural Water Course Cremation and Playground Drinking Plantation and Field Ground Water Wells 9 Channels Development
  • 10. Progress in Madhya Pradesh Financial Year 2006-07 2007-08 2008-09 2009-10 2010-11 2011- 12 Item (Jan. 2013) Districts under 18 31 50 50 50 50 MGNREGS Households 28 43 52 47.22 43.84 34.11 Demanded Work (Lakh) Mandays (Crore) 19.81 27.53 29.46 26.23 22.04 13.78 Families 5.32 9.12 9.79 7.31 4.65 1.35 Completed 100 days work Total 1862.69 2892.67 3551.67 3779.71 3641.79 2602.83 Expenditure Total Expenditure 18831.36 (Rs. Crore) Since inception of Mandays (Crore) 138.85 10 MGNREGS
  • 11. Irrigation Wells 3.24 Lakh Hectare additional irrigation under MGNREGS  3.70 Lakh Wells Sanctioned  2.21 Lakh Wells Completed  2387 Crore Expenditure Convergence for Water Lifting Devices from SGSY and State Funds
  • 12. Land Development  2.58 Lakh Beneficiaries Covered  630 Crore Expenditure  Very popular sub-scheme in tribal dominated Districts. 12
  • 13. Horticulture Development  31988 Farms Covered  100.00 Crore Expenditure Convergence with SGSY, NHM, NRLM and State Funds 13
  • 14. Watershed Development  11.81 Lakh Hectare Covered  178 Crore Expenditure Convergence with IWMP and State Funds 14
  • 15. Drinking Water Wells  23600 Wells Completed  517 Crore Expenditure 15
  • 16. Leaching Pits and Court-yard Plantation  1.20 Lakh Households Covered  246 Crore Expenditure Convergence with TSC and Horticulture Department 16
  • 17. Single Connectivity through Convergence  Earthwork completed in 2700 road works having 3850 km length.  Expenditure 165.50 Cr. Single Connectivity - Embankment Construction through MGNREGS 17
  • 18. Convergence Single Connectivity through Gravel Roads  9,019 Habitation below PMGSY Connectivity norms covered under this Sub-Scheme  7,575 Roads having 19,386 km length proposed for completion  Rs. 3,634 Crore Total estimated Expenditure Convergence of MGNREGS, BRGF, Mandi Funds and State Funds  State Funds Component – Rs. 2,486 Crore  MGNREGS Component – Rs. 495 Crore  Mandi Fund Component – Rs. 350 Crore  BRGF Component – Rs. 303 Crore  Total estimated expenditure – Rs. 3,634 Crore Earth Work in Embankment being taken up through MGNREGS only in those districts, where Job Card holders are available for unskilled work 18
  • 19. Base Course Gravel/CD Construction through Other Schemes 19
  • 21. Completed and Ongoing Works 2011-12 Carry New Works Works Carried Over Year Forward from Sanctioned Completed to Next Year Previous Year 2008-09 - 5,63,033 28,546 5,34,487 2009-10 5,34,487 1,73,825 57,987 6,50,325 2010-11 6,50,325 1,65,669 1,42,963 6,73,031 7,20,154 2011-12 6,73,031 1,51,535 1,04,412 (2,44,485 completed)
  • 22. Completed and Ongoing Works 2011-12 • Total no. of works :8,24,566 • Completed & MIS done :1,04,412 (Jan, 12) • Completed & MIS pending :2,44,485 (Jan, 12) • Likely carry over to next year :4,75,669 • Average Number of works per GP :20 nos. (Including beneficiary oriented works like TSC, Irrigation wells, Land and Farm development)
  • 23. Completed and Ongoing Works 2011-12 • Special drive to MIS completed works to be launched this year (July-August) • Boost received in 2011 after Government of India allowed partial closure. • A large no. of 5 year plantation projects completing in 2012-13 • Induction of GRS & JE will boost CC formalities & MIS.
  • 24. Financial Inclusion I • Massive exercise to completely map the entire State w.r.t. FI. • District wise villages in shadow area identified & planned for FI. • Plans discussed in DLCC & SLBC by October, 2011. Total Village : 52012 Having FI within 5 km : 37,245 Shadow Villages : 14,767
  • 25. Financial Inclusion II • For Normal Villages : Service Area Approach • For Shadow Villages :Multi pronged approach a) Business Correspondent BC b) Mobile Banking c) Kiosk / ATM d) e- panchayat (proposed) e) Brick & Mortar Branches
  • 26. Financial Inclusion III E-Panchayat Programme • Ambitious plan for 23012 Panchayats • Availability of a) Building b) Connectivity c) Trained manpower d) Hardware e) Power • Banks are welcome to use these facilities. • Already operational in 2500 GP’s
  • 27. Financial Inclusion IV Plan of Concurrent Audit in GP’s • One qualified fulltime auditor for a cluster of 7-10 Gram Panchayats. • Concurrent audit as well as basic record keeping & MIS handholding. • Outsourced with support & monitoring from CAG & LFA offices. • Senior team for Block & District level.
  • 28. Delay in Payments • Steps : Recruitment of vacant JE’s. :Strengthening MIS systems :Appraisal Committee at State level • IEC efforts :Wage disbursement camps. :Toll Free Call Centre :Panchayat Puraskar Yojna • ICT efforts :On line demand tracking :Pilots for e-MB :Pilots for e-Panchayats :SMS demand tracking
  • 29. Issues with the Ministry • New 330 proposed branches must be in shadow villages only. • Shift from Population norms to geographical norms. • Rs. 80/- per account for BC should be over & above admin. expenditure.
  • 30. Complaint I 1. Grievance Redressal Mechanisms. • Rules to be notified. • 63 State Level quality monitors. • Toll Free Call Centre. • ‘Jan Sunvai’ every Tuesday all levels. • Active involvement of divisional commissioners. • Quarterly review in appraisal committee at State level. 30
  • 31. Complaints II Status of GoI Complaints Category Year Received Disposed Pending VIP 2008-09 2 2 0 2009-10 7 6 1 2010-11 41 25 16 2011-12 11 3 8 Geneal 2008-09 1 1 0 2009-10 43 31 12 2010-11 51 37 14 2011-12 49 7 42 Total 93 * 7 Complaints in VIP category & 13 Complaints in General category are missing/not received. 31
  • 32. Complaints III  At the State level, action taken against the following officials: • 02 Collectors and 06 CEOs of District Panchayats • 133 CEOs of Janpad Panchayat • 07 Executive Engineers • 70 AEs, 216 Junior Engineers and 22 other officials  FIR registered against 160 officials and Sarpanchs.  Action taken against 746 Sarpanchs and 908 Panchayat Secretaries. 32
  • 33. Social Audit I • Mandatory Gram Sabha at Least 4 times in a year (26 Jan, 14 April, 15 August, 2 October) • Nodal Officer for each Gram Sabha. • 15 days prior notice. • ATR of previous social audit compulsory. • Many instances of action for not conducting Gram Shabha & social audit. • 100% MIS of social audit for 2011-12 done. 33
  • 34. Social Audit II • Constitution of an independent SAU is under process. • Pilot project in Dhar district with partner NGO. • PRI & NGO personals visited & trained in NIRD Hyderabad. • Online software to enter observations. 34
  • 35. MPR V/S MIS • Madhya Pradesh as a whole : 94% • 28 out of 50 districts are : 100% • 17 out of 50 districts between : 90% & 100% • 5 out of 50 districts are below : 90%  Monthly review by CS in VC “Parakh”  Active & competent State MIS cell to resolve issued.  Continuous efforts to improve connectivity in remote districts. 35
  • 36. The Proposal Year 2012-13  Past Trends  Demand  Justification 36
  • 37. Trends -Mandays and Expenditure 40.00 6000 35.00 5000 30.00 29.47 26.23 27.53 3800.00 4000 22.04 25.00 3531.67 3779.72 19.81 2892.67 3641.80 20.00 17.59 3000 15.00 1862.69 2000 10.00 1000 5.00 0.00 0 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12 Rs 63.00 Rs 85.00 Rs 91.00 Rs 100.00 Rs 100.00 (Projected) Rs 122.00 Mandays (in Crore) Expenditure (in Rs. Crore)
  • 38. Sector-wise Expenditure Trends Land Development Rs. 1336 Cr. Rural Micro Irrigation Connectivity + Irrigation Rs. 6041 Cr. facility to Formers Rs. 4718 Cr. WC+Renovation of WB Flood Control, Rs. 4537 Cr. DP and Misc. Rs. 1617 Cr.
  • 39. Year-wise Expenditure on Various Work Categories (Rs. Crore) Water Flood Conservation Rural Micro Irri. + Land Control + and Water # FY Connectivi Irri. facility to Developmen Drought Harv. + Reno. ty ind. formers t Proofing of Trad. Water Bodies 1 2006-07 795.92 140.43 688.77 141.2 61.67 2 2007-08 1137.03 255.6 780.31 525.87 128.42 3 2008-09 1102.26 353.08 836.43 1249.91 231.4 4 2009-10 983.44 366.19 698.52 1398.37 273.37 5 2010-11 1202.93 384.68 611.29 1089.31 351.39 2011-12 819.67 117.74 921.96 314 290.04 6 ( Jan.,12) Total 6041.25 1617.72 4537.28 4718.66 1336.29
  • 40. Year-Wise Quarterly Performance (Expenditure in Rs. Crore Mandays in Lakh) 2008-09 2009-10 2010-11 2011-12 Qtr Mandays Exp. Mandays Exp. Mandays Exp. Mandays Exp. I Qtr 1007.00 1308.65 927.00 1264.75 683.24 1019.70 412.00 887.89 II Qtr 452.00 706.63 277.00 598.28 308.56 691.94 445.00 750.06 III Qtr 464.00 368.25 758.00 920.12 396.72 509.85 343.00 660.45 IV Qtr 1024.00 1168.14 661.00 996.57 815.48 1420.30 - - Total 2947.00 3551.67 2623.00 3779.72 2204.00 3641.80 - -
  • 41. Mandays and Expenditure FY 2008-09 Expenditure in Rs. Crore Mandays in Lakh
  • 42. Mandays and Expenditure FY 2009-10 Expenditure in Rs. Crore Mandays in Lakh
  • 43. Mandays and Expenditure FY 2010-11 Expenditure in Rs. Crore Mandays in Lakh
  • 44. Mandays and Expenditure FY 2011-12 (January) Expenditure in Rs. Crore Mandays in Lakh
  • 45. Demand for 2012-13 • Total Mandays : 29.19 Crore • Total Expenditure : Rs. 6,305 Crore • No. Of HH Likely to demand employment : 45 Lakh • No. Of HH Likely to complete 100 days : 9.89 Lakh
  • 46. Month-wise Labour Projection 2012-13 Number of Number of Total Estimated Total Number of Households Households likely Month Person-days likely to Expenditure (in likely to complete 100 to demand be generated Lakhs) days in employment April 13,20,595 3,05,62,951 66,186 0 May 16,35,633 5,81,59,489 1,25,815 180 June 19,87,138 8,37,19,094 1,81,485 22,924 July 21,05,828 9,87,82,741 2,14,329 78,797 August 22,09,939 11,10,28,591 2,40,737 1,24,217 September 26,52,280 12,90,10,580 2,79,423 1,55,128 October 30,14,545 14,99,80,056 3,20,113 2,13,202 November 33,94,378 17,62,49,627 3,82,795 3,12,824 December 37,94,219 20,46,84,503 4,43,183 4,18,124 January 41,50,363 23,21,70,246 5,02,637 5,51,804 February 43,59,376 28,00,06,515 5,69,183 7,96,378 46 March 45,55,188 29,19,24,000 6,30,556 9,89,437
  • 47. Project Proposals for 2012-13 • Development of Land allotted to forest dwellers: – Total identified families -1.50 Lakh – Families to be covered during 2012-13 - 65,000 – Construction of irrigation wells and land development proposed. - Rs 2100Cr. – Person-days - 9.70 Cr • Irrigation Wells for individual beneficiaries: – Beneficiaries to be covered - 20,000 – Estimated Cost - Rs 600 Cr. – Person-days - 2.80 Cr 47
  • 48. Project Proposals for 2012-13 • Land development of individual formers: – Beneficiaries to be covered – 1,00,000 – Estimated Cost – Rs 500 Cr. – Person-days – 2.30 Cr. • Horticulture development for individual formers and Afforestation: – Beneficiaries to be covered 10,000 hect – Rs 200 Cr – Afforestation 40,000 Hect – Rs 550 Cr. – Person-days – 3.50 Cr 48
  • 49. Project Proposals for 2012-13 • Construction of Water Courses: – Construction of Water Courses and Field Channels in Command area of NVDA – Estimated Cost – Rs 250 Cr. – Person-days - 2.40 Cr. • TSC Toilets: – About 10 Lakh House holds to be covered – Estimated Cost - Rs 80 Cr. – Person–days @ 6 per unit -0.60 Cr. 49
  • 50. Project Proposals for 2012-13 • Single Connectivity with Convergence: Earth work on Roads providing connectivity to villages below PMGSY norms – Estimated Cost - Rs 300 Cr. – Person-days - 1.40 Cr. • Multi Connectivity: – Estimated Cost - Rs 220 Cr. – Person-days - 1.00 Cr 50
  • 51. Project Proposals for 2012-13 • Construction of Drinking Water Wells: – Estimated Cost - Rs. 300 Cr. – Person-days - 1.40 Cr. • Water Shed Development: – 317 Cluster Selected, estimated Cost - Rs 150 Cr. – Person-days - 0.70 Cr. • Carry-over and Miscellaneous Works: – Estimated Cost - Rs 1055 Cr – Person-days - 3.40 Cr. 51
  • 52. Issues • Labour Cess on MGNREGA • Demand for Houses for beneficiary • Clarification on Ombudsman • Participation in RSBY • Convergence with MPLADS 52
  • 53. Thank you for your time 53