Unit: Surveying
Lesson: Differential Leveling
Ag Structures
Mr. Dieckhoff
PowerPoint adopted from California State
Ag Mechanics Curriculum
Differential Leveling
A. Importance of Leveling
1. The determination of elevations is called leveling
2. Measuring relative elevations changes is a comparatively
simply process
3. Precise and accurate control of relative elevations are critical
to most construction projects
Differential Leveling
B. The Level
1. A level consist of a high-powered telescope
2. The level is attached to a spirit or bubble level that keeps
the line of sight of the telescope horizontal
Differential Leveling
3. Level Instrument
4.50
Differential Leveling
Level Instrument
4.60
4.55
4.51
4.52
4.53
4.54
Differential Leveling
C. Definitions
Starting point
(elevation 100.00 ft)
Point A
Point B
BS = 6.32 ft HI = 106.32 ft FS = 3.10 ft
Elevation = 103.22 ft
Differential Leveling
Definitions
1. Bench mark (BM) - relatively permanent
point of known elevation
FS = 3.10 ft
Starting point
(elevation 100.00 ft)
Point A
Point B
BS = 6.32 ft HI = 106.32 ft FS = 3.10 ft
Elevation = 103.22 ft
Differential Leveling
Definitions
2. Backsight (BS) - a sight taken to the level
rod held at a point of known elevation
(either a BM or TP)
Starting point
(elevation 100.00 ft)
Point A
Point B
BS = 6.32 ft HI = 106.32 ft FS = 3.10 ft
Elevation = 103.22 ft
Differential Leveling
Definitions
3. Height of instrument (HI) - the elevation
of the line of sight of the telescope
Starting point
(elevation 100.00 ft)
Point A
Point B
BS = 6.32 ft HI = 106.32 ft FS = 3.10 ft
Elevation = 103.22 ft
Differential Leveling
Definitions
4. Foresight (FS) - a sight taken on any point
to determine its elevation
Starting point
(elevation 100.00 ft)
Point A
Point B
BS = 6.32 ft HI = 106.32 ft FS = 3.10 ft
Elevation = 103.22 ft
Differential Leveling
D. Computation of Elevations
Elevation 100.00
BS
12.64
Point
BM1
Elevation
BS HI FS
BM1
12.64 112.64 100.00
1. BS + Elevation = HI
Differential Leveling
Computation of Elevations
Elevation 100.00
BS
12.64
FS
3.11
Point
BM1
TP1
Elevation
BS HI FS
TP1
BM1
12.64 112.64
3.11 109.53
2. HI - FS = Elevation
100.00
Differential Leveling
Computation of Elevations
Elevation 100.00
BS
12.64
FS
3.11
Point
BM1
TP1
Elevation
BS HI FS
TP1
BM1
12.64 112.64
3.11 109.53
BS
10.88
10.88 120.41
100.00
Differential Leveling
Computation of Elevations
Elevation 100.00
BS
12.64
FS
3.11
Point
BM1
TP1
Elevation
BS HI FS
TP1
BM1
12.64 112.64
3.11 109.53
BS
10.88
10.88 120.41
FS
2.56
TP2
2.56
TP2 117.85
100.00
Differential Leveling
Computation of Elevations
Elevation 100.00
BS
12.64
FS
3.11
Point
BM1
TP1
Elevation
BS HI FS
TP1
BM1
12.64 112.64
3.11 109.53
BS
10.88
10.88 120.41
FS
2.56
TP2
2.56
TP2 117.85
BS
9.72
9.72 127.57
100.00
Differential Leveling
Computation of Elevations
Elevation 100.00
BS
12.64
FS
3.11
Point
BM1
TP1
Elevation
BS HI FS
TP1
BM1
12.64 112.64
3.11 109.53
BS
10.88
10.88 120.41
FS
2.56
TP2
2.56
TP2 117.85
BS
9.72
9.72 127.57
BM2
FS
3.10
BM2 3.10 124.47
100.00
Differential Leveling
Computation of Elevations
Elevation 100.00
BS
12.64
FS
3.11
Point
BM1
TP1
Elevation
BS HI FS
TP1
BM1
12.64 112.64
3.11 109.53
BS
10.88
10.88 120.41
FS
2.56
TP2
2.56
TP2 117.85
BS
9.72
9.72 127.57
BM2
FS
3.10
BM2 3.10 124.47
100.00
Differential Leveling
Computation of Elevations
3. Change in elevation- summation of the backsight and
the foresight then subtract
+33.24 -8.77
Change in elevation = 33.24 -8.77 =24.47
Point
BM1
TP1
Elevation
BS HI FS
12.64 112.64
3.11 109.53
10.88 120.41
2.56
TP2 117.85
9.72 127.57
BM2 3.10 124.47
100.00
Differential Leveling
4. The initial backsight (BS) is taken to a point of
known elevation
5. The backsight reading is added to the elevation of
the known point to compute the height of the
instrument (HI)
6. The level may be moved to a temporary point called a
turning point (TP)
7. The elevation of a point is the height of the
instrument (HI) minus the foresight (FS)
Differential Leveling
Computation of Elevations - Group Problem
 Prepare a set of level notes for the survey illustrated
below. What are the elevations of points TP1 and TP2?
BS
1.27
FS
4.91
TP1
BM
BS
2.33
FS
6.17
TP2
Elevation 356.68
Differential Leveling
Computation of Elevations - Group Problem
BS
1.27
FS
4.91
TP1
BM
BS
2.33
FS
6.17
TP2
Elevation 356.68
1.27 357.95
4.91 353.04
2.33 355.37
6.17
Point
BM1
TP1
Elevation
BS HI FS
TP2 349.20
356.68
+3.60 -11.08 -7.48
Differential Leveling
E. Common Mistakes
1. Misreading the rod - reading
3.54 instead of 3.45
2. Moving the turning point - use a
well–defined TP
3. Field note mistakes - work within
your group to check you records
4. Mistakes with extended rod - make
sure the leveling rod is fully
extended
Differential Leveling
Common Mistakes
5. Level rod not vertical
6. Settling of leveling rod
7. Leveling rod not fully extended or
incorrect length
8. Level instrument not level
9. Instrument out of adjustment
10. Environment - wind and heat
Differential Leveling
F. Suggestions for Good Leveling
1. Anchor tripod legs firmly
2. Check the bubble level before and after each reading
3. Take as little time as possible between BS and FS
4. Try to keep the distance to the BS and the FS equal
5. Provide the rodperson with a level for the rod
Practice Set 1
Differential Leveling Review
1. Why is differential leveling called
differential?
2. What does B.M. , B.S., H.I., and F.S. stand for
in surveying?
3. If you know the starting elevation and the
B.S., how do you calculate the H.I.?
4. How do you calculate the evaluation of a T.P.?
5. What common error of leveling do you think
will be made the most in this class and why?

Contenu connexe

Similaire à 428096368-Lesson-3-Differnetial-Leveling-1.ppt

Ss report 1
Ss report 1Ss report 1
Ss report 1Shen Sin
 
Project 1- Levelling
Project 1- Levelling Project 1- Levelling
Project 1- Levelling seenyee
 
Levelling final
Levelling finalLevelling final
Levelling finalseenyee
 
Site Surveying Report 1 (Levelling)
Site Surveying Report 1 (Levelling)Site Surveying Report 1 (Levelling)
Site Surveying Report 1 (Levelling)Haziq1511
 
Levelling_1.pptx
Levelling_1.pptxLevelling_1.pptx
Levelling_1.pptxKvsghgd
 
Ge 105 lecture 1 (LEAST SQUARES ADJUSTMENT) by: Broddett B. Abatayo
Ge 105 lecture 1 (LEAST SQUARES ADJUSTMENT) by: Broddett B. AbatayoGe 105 lecture 1 (LEAST SQUARES ADJUSTMENT) by: Broddett B. Abatayo
Ge 105 lecture 1 (LEAST SQUARES ADJUSTMENT) by: Broddett B. AbatayoBPA ABATAYO Land Surveying Services
 
chapter 3 up to booking method.pdf
chapter 3 up to booking method.pdfchapter 3 up to booking method.pdf
chapter 3 up to booking method.pdfLeulDamtew
 
engineering survey 1 report levelling
engineering survey 1 report levellingengineering survey 1 report levelling
engineering survey 1 report levellingYASMINE HASLAN
 
Fieldwork 1 (leveling)
Fieldwork 1 (leveling)Fieldwork 1 (leveling)
Fieldwork 1 (leveling)Enoch Wong
 
Assignment 1 - Levelling
Assignment 1 - LevellingAssignment 1 - Levelling
Assignment 1 - LevellingKai Yun Pang
 
Site survey Fieldwork1 (levelling)
Site survey Fieldwork1 (levelling)Site survey Fieldwork1 (levelling)
Site survey Fieldwork1 (levelling)Sheng Zhe
 

Similaire à 428096368-Lesson-3-Differnetial-Leveling-1.ppt (14)

Ss report 1
Ss report 1Ss report 1
Ss report 1
 
Project 1- Levelling
Project 1- Levelling Project 1- Levelling
Project 1- Levelling
 
Levelling final
Levelling finalLevelling final
Levelling final
 
Ss report 1
Ss report 1Ss report 1
Ss report 1
 
Site Surveying Report 1 (Levelling)
Site Surveying Report 1 (Levelling)Site Surveying Report 1 (Levelling)
Site Surveying Report 1 (Levelling)
 
Levelling_1.pptx
Levelling_1.pptxLevelling_1.pptx
Levelling_1.pptx
 
Site surveying
Site surveying Site surveying
Site surveying
 
Ge 105 lecture 1 (LEAST SQUARES ADJUSTMENT) by: Broddett B. Abatayo
Ge 105 lecture 1 (LEAST SQUARES ADJUSTMENT) by: Broddett B. AbatayoGe 105 lecture 1 (LEAST SQUARES ADJUSTMENT) by: Broddett B. Abatayo
Ge 105 lecture 1 (LEAST SQUARES ADJUSTMENT) by: Broddett B. Abatayo
 
chapter 3 up to booking method.pdf
chapter 3 up to booking method.pdfchapter 3 up to booking method.pdf
chapter 3 up to booking method.pdf
 
GEODETIC Least Square with fx 991-es plus
GEODETIC Least Square with fx 991-es plusGEODETIC Least Square with fx 991-es plus
GEODETIC Least Square with fx 991-es plus
 
engineering survey 1 report levelling
engineering survey 1 report levellingengineering survey 1 report levelling
engineering survey 1 report levelling
 
Fieldwork 1 (leveling)
Fieldwork 1 (leveling)Fieldwork 1 (leveling)
Fieldwork 1 (leveling)
 
Assignment 1 - Levelling
Assignment 1 - LevellingAssignment 1 - Levelling
Assignment 1 - Levelling
 
Site survey Fieldwork1 (levelling)
Site survey Fieldwork1 (levelling)Site survey Fieldwork1 (levelling)
Site survey Fieldwork1 (levelling)
 

Dernier

Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 

Dernier (20)

Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 

428096368-Lesson-3-Differnetial-Leveling-1.ppt

  • 1. Unit: Surveying Lesson: Differential Leveling Ag Structures Mr. Dieckhoff PowerPoint adopted from California State Ag Mechanics Curriculum
  • 2. Differential Leveling A. Importance of Leveling 1. The determination of elevations is called leveling 2. Measuring relative elevations changes is a comparatively simply process 3. Precise and accurate control of relative elevations are critical to most construction projects
  • 3. Differential Leveling B. The Level 1. A level consist of a high-powered telescope 2. The level is attached to a spirit or bubble level that keeps the line of sight of the telescope horizontal
  • 6. Differential Leveling C. Definitions Starting point (elevation 100.00 ft) Point A Point B BS = 6.32 ft HI = 106.32 ft FS = 3.10 ft Elevation = 103.22 ft
  • 7. Differential Leveling Definitions 1. Bench mark (BM) - relatively permanent point of known elevation FS = 3.10 ft Starting point (elevation 100.00 ft) Point A Point B BS = 6.32 ft HI = 106.32 ft FS = 3.10 ft Elevation = 103.22 ft
  • 8. Differential Leveling Definitions 2. Backsight (BS) - a sight taken to the level rod held at a point of known elevation (either a BM or TP) Starting point (elevation 100.00 ft) Point A Point B BS = 6.32 ft HI = 106.32 ft FS = 3.10 ft Elevation = 103.22 ft
  • 9. Differential Leveling Definitions 3. Height of instrument (HI) - the elevation of the line of sight of the telescope Starting point (elevation 100.00 ft) Point A Point B BS = 6.32 ft HI = 106.32 ft FS = 3.10 ft Elevation = 103.22 ft
  • 10. Differential Leveling Definitions 4. Foresight (FS) - a sight taken on any point to determine its elevation Starting point (elevation 100.00 ft) Point A Point B BS = 6.32 ft HI = 106.32 ft FS = 3.10 ft Elevation = 103.22 ft
  • 11. Differential Leveling D. Computation of Elevations Elevation 100.00 BS 12.64 Point BM1 Elevation BS HI FS BM1 12.64 112.64 100.00 1. BS + Elevation = HI
  • 12. Differential Leveling Computation of Elevations Elevation 100.00 BS 12.64 FS 3.11 Point BM1 TP1 Elevation BS HI FS TP1 BM1 12.64 112.64 3.11 109.53 2. HI - FS = Elevation 100.00
  • 13. Differential Leveling Computation of Elevations Elevation 100.00 BS 12.64 FS 3.11 Point BM1 TP1 Elevation BS HI FS TP1 BM1 12.64 112.64 3.11 109.53 BS 10.88 10.88 120.41 100.00
  • 14. Differential Leveling Computation of Elevations Elevation 100.00 BS 12.64 FS 3.11 Point BM1 TP1 Elevation BS HI FS TP1 BM1 12.64 112.64 3.11 109.53 BS 10.88 10.88 120.41 FS 2.56 TP2 2.56 TP2 117.85 100.00
  • 15. Differential Leveling Computation of Elevations Elevation 100.00 BS 12.64 FS 3.11 Point BM1 TP1 Elevation BS HI FS TP1 BM1 12.64 112.64 3.11 109.53 BS 10.88 10.88 120.41 FS 2.56 TP2 2.56 TP2 117.85 BS 9.72 9.72 127.57 100.00
  • 16. Differential Leveling Computation of Elevations Elevation 100.00 BS 12.64 FS 3.11 Point BM1 TP1 Elevation BS HI FS TP1 BM1 12.64 112.64 3.11 109.53 BS 10.88 10.88 120.41 FS 2.56 TP2 2.56 TP2 117.85 BS 9.72 9.72 127.57 BM2 FS 3.10 BM2 3.10 124.47 100.00
  • 17. Differential Leveling Computation of Elevations Elevation 100.00 BS 12.64 FS 3.11 Point BM1 TP1 Elevation BS HI FS TP1 BM1 12.64 112.64 3.11 109.53 BS 10.88 10.88 120.41 FS 2.56 TP2 2.56 TP2 117.85 BS 9.72 9.72 127.57 BM2 FS 3.10 BM2 3.10 124.47 100.00
  • 18. Differential Leveling Computation of Elevations 3. Change in elevation- summation of the backsight and the foresight then subtract +33.24 -8.77 Change in elevation = 33.24 -8.77 =24.47 Point BM1 TP1 Elevation BS HI FS 12.64 112.64 3.11 109.53 10.88 120.41 2.56 TP2 117.85 9.72 127.57 BM2 3.10 124.47 100.00
  • 19. Differential Leveling 4. The initial backsight (BS) is taken to a point of known elevation 5. The backsight reading is added to the elevation of the known point to compute the height of the instrument (HI) 6. The level may be moved to a temporary point called a turning point (TP) 7. The elevation of a point is the height of the instrument (HI) minus the foresight (FS)
  • 20. Differential Leveling Computation of Elevations - Group Problem  Prepare a set of level notes for the survey illustrated below. What are the elevations of points TP1 and TP2? BS 1.27 FS 4.91 TP1 BM BS 2.33 FS 6.17 TP2 Elevation 356.68
  • 21. Differential Leveling Computation of Elevations - Group Problem BS 1.27 FS 4.91 TP1 BM BS 2.33 FS 6.17 TP2 Elevation 356.68 1.27 357.95 4.91 353.04 2.33 355.37 6.17 Point BM1 TP1 Elevation BS HI FS TP2 349.20 356.68 +3.60 -11.08 -7.48
  • 22. Differential Leveling E. Common Mistakes 1. Misreading the rod - reading 3.54 instead of 3.45 2. Moving the turning point - use a well–defined TP 3. Field note mistakes - work within your group to check you records 4. Mistakes with extended rod - make sure the leveling rod is fully extended
  • 23. Differential Leveling Common Mistakes 5. Level rod not vertical 6. Settling of leveling rod 7. Leveling rod not fully extended or incorrect length 8. Level instrument not level 9. Instrument out of adjustment 10. Environment - wind and heat
  • 24. Differential Leveling F. Suggestions for Good Leveling 1. Anchor tripod legs firmly 2. Check the bubble level before and after each reading 3. Take as little time as possible between BS and FS 4. Try to keep the distance to the BS and the FS equal 5. Provide the rodperson with a level for the rod
  • 26. Differential Leveling Review 1. Why is differential leveling called differential? 2. What does B.M. , B.S., H.I., and F.S. stand for in surveying? 3. If you know the starting elevation and the B.S., how do you calculate the H.I.? 4. How do you calculate the evaluation of a T.P.? 5. What common error of leveling do you think will be made the most in this class and why?