Benefits of the Solar / BESS
• Solar
– Pollution Free and No Greenhouse Gasses
– Reduced Dependency on Oil and other Fossil Fuels –
Can save for use by Nigeria Thermal Units
– Renewable Clean Power – Every Day – Even Cloudy
days
• Battery Energy Storage Systems
– Speeding up the replacement of Fossil Fuels
– Less dependent on Electrical Grid
– Match Perfectly with Solar Systems
– Great to match supply with demand
– Great when sun isn’t shining (night) and wind isn’t
blowing
Basis of BESS Estimate
• Assume 3.84 GW / 15.36 GWhr
• Need
– Civil
– Foundations
– Materials
– Controls
– Battery Management
– Metering
– Compartment Cooling
– Substation Interconnection
– Transformers
– Fire Protection
• Engineering – Preliminary Design, Detailed Design
• Construction
• Commissioning
• Training
3 Battery Modules - Backs
Exposed
Basis of BESS Estimate
• US Market - $1500-1700 / kW
• Assume $1600
• $6.144 B
2 Rows of Batteries Racks – Top
and Bottom (2 of Many)
Basis of Solar Estimate
• Assume 60 sq miles of land (buildable)
• 38,400 acres of land
• Assume 50 MW / 500 Acres = 1 MW / 10
acres
• 3,840 MW (3.84 GW) of buildable solar
• Assume 300 solar panels / acre
• 11,520,000 solar panels total
• Still require:
– Infrastructure – Substation, Transformers, Inverters,
Cabling, Weather Station, Switchgear, Control and
Communications
– Engineering Support – Civil Site Prep, concrete, steel
– SCADA
– Engineering – Preliminary Design, Detailed Design
– Construction
– Commissioning
– Training
Solar Panels – 300
panels per Acre
Basis of Solar Estimate
• Cost – Ranges between $1000 -
$3000 (US Market) – Assume
$2000 / kw installed
• 3,840,000 kw
• $7.68 B
• Note, most projects are smaller.
75-100 MW range and smaller.
• Probably would phase in with a
number of smaller programs in
lieu of all 3.84 GW
One of Several Weather
Stations
Other Required Infrastructure
• BESS
– Civil / Structural
– HVAC
– Fire Protection
– Power Conversion
– Fire Detection (VESDA)
• Solar
– Substation
– HV Switchgear
– Cabling
– Weather Stations
– Controls and Communication
Inverter and Transformer shown, HVAC
Chiller units behind (see ducts into building)

Contenu connexe

Similaire à Nigeria Solar and BESS Cost Estimate.ppt

Wind Energy For Geoscience Students
Wind Energy For Geoscience Students Wind Energy For Geoscience Students
Wind Energy For Geoscience Students
Keshav Letourneau
 
1115161Wind Power Now, Tomorrow C.P. (Case) .docx
1115161Wind Power Now, Tomorrow  C.P. (Case) .docx1115161Wind Power Now, Tomorrow  C.P. (Case) .docx
1115161Wind Power Now, Tomorrow C.P. (Case) .docx
paynetawnya
 

Similaire à Nigeria Solar and BESS Cost Estimate.ppt (20)

Concerntatini solar plant ppt
Concerntatini solar plant pptConcerntatini solar plant ppt
Concerntatini solar plant ppt
 
Wind Energy For Geoscience Students
Wind Energy For Geoscience Students Wind Energy For Geoscience Students
Wind Energy For Geoscience Students
 
Introduction and Present Status of Renewable Energies.ppt
Introduction and Present Status of Renewable Energies.pptIntroduction and Present Status of Renewable Energies.ppt
Introduction and Present Status of Renewable Energies.ppt
 
Unit 5
Unit 5Unit 5
Unit 5
 
Solar PV Codes and Standards
Solar PV Codes and StandardsSolar PV Codes and Standards
Solar PV Codes and Standards
 
final design
final designfinal design
final design
 
Rebecca mills-securing-the-n ts-energy-future
Rebecca mills-securing-the-n ts-energy-futureRebecca mills-securing-the-n ts-energy-future
Rebecca mills-securing-the-n ts-energy-future
 
OffTheGrid
OffTheGridOffTheGrid
OffTheGrid
 
Solar PV Codes and Standards
Solar PV Codes and StandardsSolar PV Codes and Standards
Solar PV Codes and Standards
 
Intro to wind energy
Intro to wind energyIntro to wind energy
Intro to wind energy
 
A Praposal For Installation of 10 mw solar thermal power plant.
A Praposal For Installation of 10 mw solar thermal power plant.A Praposal For Installation of 10 mw solar thermal power plant.
A Praposal For Installation of 10 mw solar thermal power plant.
 
Designing Solar PV Systems ( Utility Scale)
Designing Solar PV Systems ( Utility Scale)Designing Solar PV Systems ( Utility Scale)
Designing Solar PV Systems ( Utility Scale)
 
introduction on high voltage engineering
introduction on high voltage engineeringintroduction on high voltage engineering
introduction on high voltage engineering
 
Planning a successful microgrid
Planning a successful microgridPlanning a successful microgrid
Planning a successful microgrid
 
ECBC
ECBCECBC
ECBC
 
Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...
Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...
Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...
 
Boopaledit.pptx
Boopaledit.pptxBoopaledit.pptx
Boopaledit.pptx
 
1115161Wind Power Now, Tomorrow C.P. (Case) .docx
1115161Wind Power Now, Tomorrow  C.P. (Case) .docx1115161Wind Power Now, Tomorrow  C.P. (Case) .docx
1115161Wind Power Now, Tomorrow C.P. (Case) .docx
 
1159 voronka[1]
1159 voronka[1]1159 voronka[1]
1159 voronka[1]
 
Dynamic modelling of a parabolic trough solar power plant
Dynamic modelling of a parabolic trough solar power plant Dynamic modelling of a parabolic trough solar power plant
Dynamic modelling of a parabolic trough solar power plant
 

Dernier

Tales from a Passkey Provider Progress from Awareness to Implementation.pptx
Tales from a Passkey Provider  Progress from Awareness to Implementation.pptxTales from a Passkey Provider  Progress from Awareness to Implementation.pptx
Tales from a Passkey Provider Progress from Awareness to Implementation.pptx
FIDO Alliance
 
“Iamnobody89757” Understanding the Mysterious of Digital Identity.pdf
“Iamnobody89757” Understanding the Mysterious of Digital Identity.pdf“Iamnobody89757” Understanding the Mysterious of Digital Identity.pdf
“Iamnobody89757” Understanding the Mysterious of Digital Identity.pdf
Muhammad Subhan
 

Dernier (20)

Continuing Bonds Through AI: A Hermeneutic Reflection on Thanabots
Continuing Bonds Through AI: A Hermeneutic Reflection on ThanabotsContinuing Bonds Through AI: A Hermeneutic Reflection on Thanabots
Continuing Bonds Through AI: A Hermeneutic Reflection on Thanabots
 
How we scaled to 80K users by doing nothing!.pdf
How we scaled to 80K users by doing nothing!.pdfHow we scaled to 80K users by doing nothing!.pdf
How we scaled to 80K users by doing nothing!.pdf
 
2024 May Patch Tuesday
2024 May Patch Tuesday2024 May Patch Tuesday
2024 May Patch Tuesday
 
Tales from a Passkey Provider Progress from Awareness to Implementation.pptx
Tales from a Passkey Provider  Progress from Awareness to Implementation.pptxTales from a Passkey Provider  Progress from Awareness to Implementation.pptx
Tales from a Passkey Provider Progress from Awareness to Implementation.pptx
 
Working together SRE & Platform Engineering
Working together SRE & Platform EngineeringWorking together SRE & Platform Engineering
Working together SRE & Platform Engineering
 
UiPath manufacturing technology benefits and AI overview
UiPath manufacturing technology benefits and AI overviewUiPath manufacturing technology benefits and AI overview
UiPath manufacturing technology benefits and AI overview
 
Event-Driven Architecture Masterclass: Integrating Distributed Data Stores Ac...
Event-Driven Architecture Masterclass: Integrating Distributed Data Stores Ac...Event-Driven Architecture Masterclass: Integrating Distributed Data Stores Ac...
Event-Driven Architecture Masterclass: Integrating Distributed Data Stores Ac...
 
ChatGPT and Beyond - Elevating DevOps Productivity
ChatGPT and Beyond - Elevating DevOps ProductivityChatGPT and Beyond - Elevating DevOps Productivity
ChatGPT and Beyond - Elevating DevOps Productivity
 
Google I/O Extended 2024 Warsaw
Google I/O Extended 2024 WarsawGoogle I/O Extended 2024 Warsaw
Google I/O Extended 2024 Warsaw
 
JavaScript Usage Statistics 2024 - The Ultimate Guide
JavaScript Usage Statistics 2024 - The Ultimate GuideJavaScript Usage Statistics 2024 - The Ultimate Guide
JavaScript Usage Statistics 2024 - The Ultimate Guide
 
Cyber Insurance - RalphGilot - Embry-Riddle Aeronautical University.pptx
Cyber Insurance - RalphGilot - Embry-Riddle Aeronautical University.pptxCyber Insurance - RalphGilot - Embry-Riddle Aeronautical University.pptx
Cyber Insurance - RalphGilot - Embry-Riddle Aeronautical University.pptx
 
Frisco Automating Purchase Orders with MuleSoft IDP- May 10th, 2024.pptx.pdf
Frisco Automating Purchase Orders with MuleSoft IDP- May 10th, 2024.pptx.pdfFrisco Automating Purchase Orders with MuleSoft IDP- May 10th, 2024.pptx.pdf
Frisco Automating Purchase Orders with MuleSoft IDP- May 10th, 2024.pptx.pdf
 
Extensible Python: Robustness through Addition - PyCon 2024
Extensible Python: Robustness through Addition - PyCon 2024Extensible Python: Robustness through Addition - PyCon 2024
Extensible Python: Robustness through Addition - PyCon 2024
 
ERP Contender Series: Acumatica vs. Sage Intacct
ERP Contender Series: Acumatica vs. Sage IntacctERP Contender Series: Acumatica vs. Sage Intacct
ERP Contender Series: Acumatica vs. Sage Intacct
 
1111 ChatGPT Prompts PDF Free Download - Prompts for ChatGPT
1111 ChatGPT Prompts PDF Free Download - Prompts for ChatGPT1111 ChatGPT Prompts PDF Free Download - Prompts for ChatGPT
1111 ChatGPT Prompts PDF Free Download - Prompts for ChatGPT
 
“Iamnobody89757” Understanding the Mysterious of Digital Identity.pdf
“Iamnobody89757” Understanding the Mysterious of Digital Identity.pdf“Iamnobody89757” Understanding the Mysterious of Digital Identity.pdf
“Iamnobody89757” Understanding the Mysterious of Digital Identity.pdf
 
The Metaverse: Are We There Yet?
The  Metaverse:    Are   We  There  Yet?The  Metaverse:    Are   We  There  Yet?
The Metaverse: Are We There Yet?
 
WebAssembly is Key to Better LLM Performance
WebAssembly is Key to Better LLM PerformanceWebAssembly is Key to Better LLM Performance
WebAssembly is Key to Better LLM Performance
 
Human Expert Website Manual WCAG 2.0 2.1 2.2 Audit - Digital Accessibility Au...
Human Expert Website Manual WCAG 2.0 2.1 2.2 Audit - Digital Accessibility Au...Human Expert Website Manual WCAG 2.0 2.1 2.2 Audit - Digital Accessibility Au...
Human Expert Website Manual WCAG 2.0 2.1 2.2 Audit - Digital Accessibility Au...
 
Top 10 CodeIgniter Development Companies
Top 10 CodeIgniter Development CompaniesTop 10 CodeIgniter Development Companies
Top 10 CodeIgniter Development Companies
 

Nigeria Solar and BESS Cost Estimate.ppt

  • 1. Benefits of the Solar / BESS • Solar – Pollution Free and No Greenhouse Gasses – Reduced Dependency on Oil and other Fossil Fuels – Can save for use by Nigeria Thermal Units – Renewable Clean Power – Every Day – Even Cloudy days • Battery Energy Storage Systems – Speeding up the replacement of Fossil Fuels – Less dependent on Electrical Grid – Match Perfectly with Solar Systems – Great to match supply with demand – Great when sun isn’t shining (night) and wind isn’t blowing
  • 2. Basis of BESS Estimate • Assume 3.84 GW / 15.36 GWhr • Need – Civil – Foundations – Materials – Controls – Battery Management – Metering – Compartment Cooling – Substation Interconnection – Transformers – Fire Protection • Engineering – Preliminary Design, Detailed Design • Construction • Commissioning • Training 3 Battery Modules - Backs Exposed
  • 3. Basis of BESS Estimate • US Market - $1500-1700 / kW • Assume $1600 • $6.144 B 2 Rows of Batteries Racks – Top and Bottom (2 of Many)
  • 4. Basis of Solar Estimate • Assume 60 sq miles of land (buildable) • 38,400 acres of land • Assume 50 MW / 500 Acres = 1 MW / 10 acres • 3,840 MW (3.84 GW) of buildable solar • Assume 300 solar panels / acre • 11,520,000 solar panels total • Still require: – Infrastructure – Substation, Transformers, Inverters, Cabling, Weather Station, Switchgear, Control and Communications – Engineering Support – Civil Site Prep, concrete, steel – SCADA – Engineering – Preliminary Design, Detailed Design – Construction – Commissioning – Training Solar Panels – 300 panels per Acre
  • 5. Basis of Solar Estimate • Cost – Ranges between $1000 - $3000 (US Market) – Assume $2000 / kw installed • 3,840,000 kw • $7.68 B • Note, most projects are smaller. 75-100 MW range and smaller. • Probably would phase in with a number of smaller programs in lieu of all 3.84 GW One of Several Weather Stations
  • 6. Other Required Infrastructure • BESS – Civil / Structural – HVAC – Fire Protection – Power Conversion – Fire Detection (VESDA) • Solar – Substation – HV Switchgear – Cabling – Weather Stations – Controls and Communication Inverter and Transformer shown, HVAC Chiller units behind (see ducts into building)