SlideShare une entreprise Scribd logo
1  sur  26
Télécharger pour lire hors ligne
06/04/35
1
EEET 426
ELECTRICAL DISTRIBUTION
TECHNOLOGY
Dr.A.Arunagiri
Distribution System Planning
Chapter 1
06/04/35
2
Chapter Outline
Introduction
Factors affecting distribution system planning
Present distribution system planning techniques
Distribution system planning models
Computer central role in distribution planning
Impact of dispersed storage and generation
Renewable resources of generation
Dr.A.Arunagiri
Introduction
Dr.A.Arunagiri
The electrical power system is very complex system.
Distribution is about 50% of the capital cost of the power system.
The power system consists of three main parts Generation plants,
Transmission and Distribution.
The electrical distribution system is a part of the system between
the transmission and the consumer service point.
The electrical distribution system is divided into primary and secondary
distribution.
06/04/35
3
Typical Electrical Power System
Dr.A.Arunagiri
The electrical distribution systems consists of:
Dr.A.Arunagiri
1.Sub transmission
2.Distribution substation
3.Primary feeders
4.Distribution transformers
5.Secondary circuits
6.Service drops
06/04/35
4
Distribution System
Dr.A.Arunagiri
Sub-transmission
Dr.A.Arunagiri
The sub-transmission is an electrical network designed to supply the
electrical power from the bulk power source (Transmission line) to the
distribution sub-station at a voltage ranging from 33 to 220 kV. May be over
head or underground cables.
There are six types of sub-transmission are:
• Radial system.
• Primary Loop System.
• Primary Selective.
•Secondary selective
• Spot Network
• Grid Network
06/04/35
5
Radial Systems
Dr.A.Arunagiri
Dr.A.Arunagiri
06/04/35
6
Primary Loop System
Dr.A.Arunagiri
PrimarySelective System
Dr.A.Arunagiri
06/04/35
7
Secondary Selective System
Dr.A.Arunagiri
Spot Network
Dr.A.Arunagiri
06/04/35
8
Grid Network
Dr.A.Arunagiri
Electrical Power System
Dr.A.Arunagiri
06/04/35
9
Dr.A.Arunagiri
Dr.A.Arunagiri
06/04/35
10
(b)Single Wire Earth Return
(SWER)
Dr.A.Arunagiri
Dr.A.Arunagiri
06/04/35
11
Dr.A.Arunagiri
Dr.A.Arunagiri
06/04/35
12
Dr.A.Arunagiri
Types of Distribution System
(a) Single Phase
Dr.A.Arunagiri
06/04/35
13
(C ) Three phase Three Wire
Dr.A.Arunagiri
(d) Three Phase four Wire
Dr.A.Arunagiri
06/04/35
14
Basic Distribution Systems
• Radial
• Primary Loop
• Primary Selective
• Secondary Selective
• Spot Network
• Grid Network
Dr.A.Arunagiri
Factors Affecting Distribution System
Planning
 Load demand and load
characteristics
 Voltage level at the
customer point
 Type of secondary
circuits
 Size and location of
distribution transformer
 Types of primary
distribution system
 Loads at primary
distribution level
 Size and location of
distribution substation
 Routing and capacity of
associated sub-
transmission lines
Dr.A.Arunagiri
06/04/35
15
Factors Affecting Distribution System
Planning…….
 Restrictions such as
 Permissible voltage deviations
 Voltage dip and flicker
 Service continuity and reliability
 Types of protection to be
employed
 Choice of circuit breakers,
reclosers and sectionalizers
 Requirement of capacitors
for power factor correction
and loss minimization
 Requirement of voltage
regulators
 Types of transformers and
availability of space for
transformers
 Insulation levels
Dr.A.Arunagiri
Distribution system Planning Technique
 Load flow programs
 Radial or loop load flow
programs
 Short-circuit programs
 Voltage drop calculation
programs
 Total system impedance
calculation programs
 Load forecasting programs
 Voltage regulation and
regulator setting programs
 Capacitor planning
programs
 Substation optimal sitting
and sizing programs
 Reliability programs
Dr.A.Arunagiri
06/04/35
16
However, in general, the overall concept of
automatically using output of each program as
input for the next program is not in use.
Engineering judgment and trial and error method
are used in system planning. In this chapter, we
shall discuss some of the distribution planning and
operation techniques.
Dr.A.Arunagiri
Future Distribution System Planning
Components
Vision:
A clear vision for the future
communicates a sense of the kind of
organization, power utility needs to
become, and outlines the kind of
results it must achieve. The vision
provides a continuing focus and
constantly reminds the employees
and consumers of what the company
trying to change.
 Mission:
For particular task there can be a
mission statement such as Electricity
for all KSA by the end of next decade
 Values:
The power utility leadership must
create values such as consumer
satisfaction, environmental
responsibility.
Dr.A.Arunagiri
06/04/35
17
Distribution system planning models
Traditional-Least cost
model:
It is a process by which utilities
minimize the cost of supplying a
given amount of power. The
existing system inadequacies are
identified as:
• Poor voltage regulation
• Higher system loss
• Higher equipment
failure/breakdown
• Bad quality of power supply
• No scope for future growth.
Dr.A.Arunagiri
The initial system improvement can be very cost effective in
removing the above system inadequacies as compared to the other
alternatives of laying a new extended system.
Thus there are two options:
 System improvement
 Expansion of the existing network
Dr.A.Arunagiri
06/04/35
18
(a) System Improvement
Augmentation and strengthening of the existing system
Improving the reliability and quality of supply
Reduction of commercial and technical loss and / or
Dr.A.Arunagiri
b)Expansion of the existing network
When augmentation and strengthening of existing system are
involved the benefits of saving in losses (kw and energy), net
revenue increase due to additional sale of power and energy
after adjusting the expenditure incurred on generation of the
additional energy must be maximized.
Dr.A.Arunagiri
06/04/35
19
2. Demand Side Planning(DSP)
It is the process by which power utilities quantify and assess the
programmes to alter the load pattern and level of their consumer’s
demand for electricity.
This is planning at the consumer level and often has a long planning
period, much longer than distribution system planning. It can take years
of slow progress to obtain meaningful levels of participation.
Dr.A.Arunagiri
The low cost demand side option can be :
Implementing energy conservation programmes
Providing vigilance and detection of theft.
Dr.A.Arunagiri
06/04/35
20
DSM programmes generally fall into three main
categories:
1 Conservation programmes
Reduce energy use with programmes to improve the efficiency of the
equipments (like lighting and motors), buildings and industrial
processes as per the energy conservation act.
2 load management programmes:
Redistribute energy demands to spread it more evenly throughout
the day. Some way of doing this are:
Load shifting programmes ( shifting some of the loads during
peak period to off peak period)
Time -of –use ( Charging more for electricity during peak
demand)
Interruptible rates( providing rate discounts in exchange for
the right to reduce consumers electricity allocation each year
during few hours when electricity demand is the highest
Types of DSM
Dr.A.Arunagiri
3. Strategic load growth programmes:
Increase energy use during some periods, (Encourage cost
effective electrical technologies that operate primarily
during periods of low electricity demand.)
The following approaches can be used.
 General information programmes to inform consumers about generic
energy efficientoptions
 Site – specific information programmes that provide information
about specific DSM measures appropriate for a particular industry ,
agricultureor home.
 Financing programmes to assist consumers to pay for DSM measures
includingloans, rebates, and shared savings programmes
Dr.A.Arunagiri
06/04/35
21
 Direct installation programmes that provide complete
services to design, finance and install a package of efficiency
measures.
 Alternative tariff programmes including time-of-use tariff,
interruptible tariff, and load shifting tariff. ( These programmes
usually do not save energy but they are effective ways to shift
loads to off peak periods.
 Bidding programmes in which utility solicits bids from
consumers and energy service companies.
 Load limiters are effective in demand side management , as
they limit the maximum power that the consumer draws from
the supply.
Dr.A.Arunagiri
The process of designing and implementing DSM programmes
generally consists of the following steps.
 Identifying the sectors, end -uses and efficiency
measures to target
 Developing programme design
 Conducting cost-effective screening
 Preparing an implementation plan
 Implementing programmes and
 Evaluating programmes.
Dr.A.Arunagiri
06/04/35
22
Benefits of DSM
• Reduces consumers energy bills
• Reduces the need for the new
plant, transmission and distribution
construction
• Stimulates economic development
• Creates long time jobs that benefits
the economy
• Increases the competitiveness of the
local enterprises
• Can reduce maintenance and
equipment replacement cost
• Reduces local air pollution
• Reduces emission s that contribute
to national and international
environmental problems such as acid
rain and global warming
• Enhances national security by easing
dependence on foreign energy
sources
Dr.A.Arunagiri
Computer central role in distribution planning
 Software needs:
generally is selected on the basis of the
least life cycle cost or least ownership
costs (hiring or purchase + training +
maintenance costs). The software must
be.
– Bestoverallperformance
– Bestsolution
– Bestopen architecture system
 Analysis of the system
computer aided power flow studies in
improving the performance of the existing
sub-transmission and distribution systems
and proposed expansion of network up to
the meter point (Consumers). Studies
will provide
– Active and reactive power flows as
well as the locations of capacitors
– Voltage variation (at each node or
bus, percent variation)
– Peak power losses and energy losses
– Computation of commercial losses of
feeder
– Overloading of transformers
:
Dr.A.Arunagiri
06/04/35
23
Computer central role in distribution planning
 Data:
success of any information
technology system is highly
dependent on the accurate, up to
date field data for improvement in
the network and system.
Information must be clear and up-
dated on:
Nodes
Single line diagram
Distribution substation
Primary feeder
Distribution transformer
and secondary feeder
Consumer data
Load data
Dr.A.Arunagiri
Elements of the distribution system
 Distribution Transformer
 Primary distribution feeder
 Secondary distribution
feeder
 Protection devices and
instrumentation
Dr.A.Arunagiri
06/04/35
24
Dispersed Generation
Dr.A.Arunagiri
Impact of dispersed storage and generation
• This is When the generating plant is connected to a distribution
network capable of supplying power to the consumer load directly .
• This enhances the reliability and the quality of power supply.
• The expectations of the reliability especially for data centers, call
centers, computer controlled critical process/businesses, continuous
process industries, petro chemical refineries are four nines
(99.99%).
Dr.A.Arunagiri
06/04/35
25
Impact of dispersed generation….
For dispersed generations line losses will be nominal since there is
no transmission system is required.
Dispersed generation with local radial distribution network will
play an important role in the 21st century.
Dispersed generation is generally from local renewable sources.
This saves environment degradation compared to conventional
thermal generation.
Dr.A.Arunagiri
Renewable resources of generation
 Fuel cells
 Solar photovoltaic
 Wind energy
 Tidal wave energy from
ocean
 Small hydro (up to 25 MW
capacity, pumped
storage)
 Geo-thermal
 Bio-mass
 Municipal and industrial
west
Dr.A.Arunagiri
06/04/35
26
Net Metering
The kilo watt hour meter(import – export meter) can be used to
accurately register the flow of electricity in either direction. This
means the ‘netting’ process associated with net metering happens
automatically
Dr.A.Arunagiri
Assignment 1
Q.1
Draw the one line diagram of the electrical power system
available in KSA.. Indicate the voltage levels for
Generation
Transmission
Sub transmission
Primary Feeder
Secondary Feeder
Q2
Mention and discuss the different types of the renewable resources of
generation available in the KSA.
Dr.A.Arunagiri

Contenu connexe

Tendances

Power system protection_lecture_notes
Power system protection_lecture_notesPower system protection_lecture_notes
Power system protection_lecture_noteslcm3766l
 
Directional over current relay
Directional over current relayDirectional over current relay
Directional over current relayCS V
 
Ppt of ehv ac transmission
Ppt of ehv ac transmissionPpt of ehv ac transmission
Ppt of ehv ac transmissionSumit Kumar
 
Series & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs DevicesSeries & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs Deviceskhemraj298
 
Distribution systems
Distribution systemsDistribution systems
Distribution systemsSURAJ PRASAD
 
Power Transformer Protection
Power Transformer ProtectionPower Transformer Protection
Power Transformer ProtectionAng Sovann
 
Harmonics: Causes and Effects
Harmonics: Causes and EffectsHarmonics: Causes and Effects
Harmonics: Causes and EffectsLeonardo ENERGY
 
FUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTIONFUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTIONPower System Operation
 
Principles of Cable Sizing
Principles of Cable SizingPrinciples of Cable Sizing
Principles of Cable SizingLeonardo ENERGY
 
Load forecasting
Load forecastingLoad forecasting
Load forecastingsushrut p
 
Unit 03 Protective relays
Unit  03 Protective relaysUnit  03 Protective relays
Unit 03 Protective relaysPremanandDesai
 
Load curve
Load curveLoad curve
Load curveboromama
 
Basics of AC transmission
Basics of AC transmissionBasics of AC transmission
Basics of AC transmissionSonuKumarBairwa
 
Distribution System Voltage Drop and Power Loss Calculation
Distribution System Voltage Drop and Power Loss CalculationDistribution System Voltage Drop and Power Loss Calculation
Distribution System Voltage Drop and Power Loss CalculationAmeen San
 
Distribution System Planning and Design
Distribution System Planning and DesignDistribution System Planning and Design
Distribution System Planning and DesignAdithya Ballaji
 

Tendances (20)

Power system protection_lecture_notes
Power system protection_lecture_notesPower system protection_lecture_notes
Power system protection_lecture_notes
 
Directional over current relay
Directional over current relayDirectional over current relay
Directional over current relay
 
Load forecasting
Load forecastingLoad forecasting
Load forecasting
 
Facts controller
Facts controllerFacts controller
Facts controller
 
Ppt of ehv ac transmission
Ppt of ehv ac transmissionPpt of ehv ac transmission
Ppt of ehv ac transmission
 
Series & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs DevicesSeries & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs Devices
 
Distribution systems
Distribution systemsDistribution systems
Distribution systems
 
Power Transformer Protection
Power Transformer ProtectionPower Transformer Protection
Power Transformer Protection
 
Harmonics: Causes and Effects
Harmonics: Causes and EffectsHarmonics: Causes and Effects
Harmonics: Causes and Effects
 
Two area system
Two area systemTwo area system
Two area system
 
Spinning reserve
Spinning reserveSpinning reserve
Spinning reserve
 
PPT ON POWER SYSTEM STABILITY
PPT ON POWER SYSTEM STABILITYPPT ON POWER SYSTEM STABILITY
PPT ON POWER SYSTEM STABILITY
 
FUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTIONFUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTION
 
Principles of Cable Sizing
Principles of Cable SizingPrinciples of Cable Sizing
Principles of Cable Sizing
 
Load forecasting
Load forecastingLoad forecasting
Load forecasting
 
Unit 03 Protective relays
Unit  03 Protective relaysUnit  03 Protective relays
Unit 03 Protective relays
 
Load curve
Load curveLoad curve
Load curve
 
Basics of AC transmission
Basics of AC transmissionBasics of AC transmission
Basics of AC transmission
 
Distribution System Voltage Drop and Power Loss Calculation
Distribution System Voltage Drop and Power Loss CalculationDistribution System Voltage Drop and Power Loss Calculation
Distribution System Voltage Drop and Power Loss Calculation
 
Distribution System Planning and Design
Distribution System Planning and DesignDistribution System Planning and Design
Distribution System Planning and Design
 

En vedette

Electrical Power Distribution Systems Design
Electrical Power Distribution Systems DesignElectrical Power Distribution Systems Design
Electrical Power Distribution Systems DesignCurrent Solutions PC
 
9.3 transformers
9.3 transformers9.3 transformers
9.3 transformerspixelcowboy
 
Electrical Control Panels | Variable Frequency Drives | Hazardous Location Pa...
Electrical Control Panels | Variable Frequency Drives | Hazardous Location Pa...Electrical Control Panels | Variable Frequency Drives | Hazardous Location Pa...
Electrical Control Panels | Variable Frequency Drives | Hazardous Location Pa...Jazz Matharu
 
39 alfred a. mello - 5910878 - method and apparatus for protecting electric...
39   alfred a. mello - 5910878 - method and apparatus for protecting electric...39   alfred a. mello - 5910878 - method and apparatus for protecting electric...
39 alfred a. mello - 5910878 - method and apparatus for protecting electric...Mello_Patent_Registry
 
Electrical devices
Electrical  devicesElectrical  devices
Electrical devicesshubifareek
 
Public Distribution System
Public Distribution SystemPublic Distribution System
Public Distribution SystemSneha J Chouhan
 
electrical distribution system ppt/13b61a0221
electrical distribution system ppt/13b61a0221electrical distribution system ppt/13b61a0221
electrical distribution system ppt/13b61a0221saikrishna kandhikatla
 
Power Cable Fault Location - Medium & High Voltage Cables
Power Cable Fault Location - Medium & High Voltage CablesPower Cable Fault Location - Medium & High Voltage Cables
Power Cable Fault Location - Medium & High Voltage CablesThorne & Derrick International
 
Power System Protection (Primary & Backup)
Power System Protection (Primary & Backup)Power System Protection (Primary & Backup)
Power System Protection (Primary & Backup)Kamran Gillani
 
Preventive Maintenance Strategies for Power Distribution Systems- Charles Alvis
Preventive Maintenance Strategies for Power Distribution Systems- Charles AlvisPreventive Maintenance Strategies for Power Distribution Systems- Charles Alvis
Preventive Maintenance Strategies for Power Distribution Systems- Charles AlvisSchneider Electric
 
Electrical distribution system
Electrical distribution system Electrical distribution system
Electrical distribution system Ankush Bharti
 
Electricity distribution system in india
Electricity distribution system in indiaElectricity distribution system in india
Electricity distribution system in indiaJasgt Singh
 

En vedette (15)

Electrical Power Distribution Systems Design
Electrical Power Distribution Systems DesignElectrical Power Distribution Systems Design
Electrical Power Distribution Systems Design
 
9.3 transformers
9.3 transformers9.3 transformers
9.3 transformers
 
Electrical Control Panels | Variable Frequency Drives | Hazardous Location Pa...
Electrical Control Panels | Variable Frequency Drives | Hazardous Location Pa...Electrical Control Panels | Variable Frequency Drives | Hazardous Location Pa...
Electrical Control Panels | Variable Frequency Drives | Hazardous Location Pa...
 
39 alfred a. mello - 5910878 - method and apparatus for protecting electric...
39   alfred a. mello - 5910878 - method and apparatus for protecting electric...39   alfred a. mello - 5910878 - method and apparatus for protecting electric...
39 alfred a. mello - 5910878 - method and apparatus for protecting electric...
 
Electrical devices
Electrical  devicesElectrical  devices
Electrical devices
 
Public Distribution System
Public Distribution SystemPublic Distribution System
Public Distribution System
 
electrical distribution system ppt/13b61a0221
electrical distribution system ppt/13b61a0221electrical distribution system ppt/13b61a0221
electrical distribution system ppt/13b61a0221
 
Control Panel
Control PanelControl Panel
Control Panel
 
Earthing
EarthingEarthing
Earthing
 
Panel designing
Panel designingPanel designing
Panel designing
 
Power Cable Fault Location - Medium & High Voltage Cables
Power Cable Fault Location - Medium & High Voltage CablesPower Cable Fault Location - Medium & High Voltage Cables
Power Cable Fault Location - Medium & High Voltage Cables
 
Power System Protection (Primary & Backup)
Power System Protection (Primary & Backup)Power System Protection (Primary & Backup)
Power System Protection (Primary & Backup)
 
Preventive Maintenance Strategies for Power Distribution Systems- Charles Alvis
Preventive Maintenance Strategies for Power Distribution Systems- Charles AlvisPreventive Maintenance Strategies for Power Distribution Systems- Charles Alvis
Preventive Maintenance Strategies for Power Distribution Systems- Charles Alvis
 
Electrical distribution system
Electrical distribution system Electrical distribution system
Electrical distribution system
 
Electricity distribution system in india
Electricity distribution system in indiaElectricity distribution system in india
Electricity distribution system in india
 

Similaire à ELECTRICAL DISTRIBUTION TECHNOLOGY

Papai projet
Papai projetPapai projet
Papai projetpapai13
 
Energy audit, conservation and power factor
Energy audit, conservation and power factorEnergy audit, conservation and power factor
Energy audit, conservation and power factoreSAT Publishing House
 
Dsm and technical, non technical losses
Dsm and technical, non technical lossesDsm and technical, non technical losses
Dsm and technical, non technical lossesFareed Ahmed Shaikh
 
Energy audit, conservation and power factor improvement for bmsit campus
Energy audit, conservation and power factor improvement for bmsit campusEnergy audit, conservation and power factor improvement for bmsit campus
Energy audit, conservation and power factor improvement for bmsit campuseSAT Journals
 
Energy Audit of a Food Industry
Energy Audit of a Food IndustryEnergy Audit of a Food Industry
Energy Audit of a Food IndustryIJMER
 
Finding financing for industrial energy efficiency & chp
Finding financing for industrial energy efficiency & chpFinding financing for industrial energy efficiency & chp
Finding financing for industrial energy efficiency & chpTNenergy
 
IRJET- Analysis of Demand Side Management of Distribution Systems
IRJET-  	  Analysis of Demand Side Management of Distribution SystemsIRJET-  	  Analysis of Demand Side Management of Distribution Systems
IRJET- Analysis of Demand Side Management of Distribution SystemsIRJET Journal
 
15325008%2 e2014%2e1002589
15325008%2 e2014%2e100258915325008%2 e2014%2e1002589
15325008%2 e2014%2e1002589rehman1oo
 
IRJET- Demand Response Optimization using Genetic Algorithm and Particle Swar...
IRJET- Demand Response Optimization using Genetic Algorithm and Particle Swar...IRJET- Demand Response Optimization using Genetic Algorithm and Particle Swar...
IRJET- Demand Response Optimization using Genetic Algorithm and Particle Swar...IRJET Journal
 
Electricity_Reliability_031611 Galvin Power ORG
Electricity_Reliability_031611 Galvin Power ORGElectricity_Reliability_031611 Galvin Power ORG
Electricity_Reliability_031611 Galvin Power ORGRonnie Waterman
 
17_ACaseStudy.pdf
17_ACaseStudy.pdf17_ACaseStudy.pdf
17_ACaseStudy.pdfpurushukpc1
 
Decision Support System for Energy Saving Analysis in Manufacturing Industry
Decision Support System for Energy Saving Analysis in Manufacturing IndustryDecision Support System for Energy Saving Analysis in Manufacturing Industry
Decision Support System for Energy Saving Analysis in Manufacturing IndustryIJRES Journal
 
IRJET- An Energy Conservation Scheme based on Tariff Moderation
IRJET- An Energy Conservation Scheme based on Tariff ModerationIRJET- An Energy Conservation Scheme based on Tariff Moderation
IRJET- An Energy Conservation Scheme based on Tariff ModerationIRJET Journal
 
Distribution Automation Challenges
Distribution Automation ChallengesDistribution Automation Challenges
Distribution Automation ChallengesMohammad Abdullah
 
Energy Conservation By Mehfooz Qazi
Energy Conservation By Mehfooz QaziEnergy Conservation By Mehfooz Qazi
Energy Conservation By Mehfooz QaziIEEEP Karachi
 
Energy Management Systems: Recommendations for decision makers
Energy Management Systems: Recommendations for decision makersEnergy Management Systems: Recommendations for decision makers
Energy Management Systems: Recommendations for decision makersGimélec
 
Energy management &amp & audit
Energy management &amp & auditEnergy management &amp & audit
Energy management &amp & auditSagar Joshi
 
Pay-As-You-Go Energy Meter with GSM Module
Pay-As-You-Go Energy Meter with GSM ModulePay-As-You-Go Energy Meter with GSM Module
Pay-As-You-Go Energy Meter with GSM ModuleIRJET Journal
 

Similaire à ELECTRICAL DISTRIBUTION TECHNOLOGY (20)

Papai projet
Papai projetPapai projet
Papai projet
 
Energy audit, conservation and power factor
Energy audit, conservation and power factorEnergy audit, conservation and power factor
Energy audit, conservation and power factor
 
Dsm and technical, non technical losses
Dsm and technical, non technical lossesDsm and technical, non technical losses
Dsm and technical, non technical losses
 
Energy audit, conservation and power factor improvement for bmsit campus
Energy audit, conservation and power factor improvement for bmsit campusEnergy audit, conservation and power factor improvement for bmsit campus
Energy audit, conservation and power factor improvement for bmsit campus
 
Energy Management
Energy ManagementEnergy Management
Energy Management
 
Energy Audit of a Food Industry
Energy Audit of a Food IndustryEnergy Audit of a Food Industry
Energy Audit of a Food Industry
 
Finding financing for industrial energy efficiency & chp
Finding financing for industrial energy efficiency & chpFinding financing for industrial energy efficiency & chp
Finding financing for industrial energy efficiency & chp
 
IRJET- Analysis of Demand Side Management of Distribution Systems
IRJET-  	  Analysis of Demand Side Management of Distribution SystemsIRJET-  	  Analysis of Demand Side Management of Distribution Systems
IRJET- Analysis of Demand Side Management of Distribution Systems
 
15325008%2 e2014%2e1002589
15325008%2 e2014%2e100258915325008%2 e2014%2e1002589
15325008%2 e2014%2e1002589
 
IRJET- Demand Response Optimization using Genetic Algorithm and Particle Swar...
IRJET- Demand Response Optimization using Genetic Algorithm and Particle Swar...IRJET- Demand Response Optimization using Genetic Algorithm and Particle Swar...
IRJET- Demand Response Optimization using Genetic Algorithm and Particle Swar...
 
Electricity_Reliability_031611 Galvin Power ORG
Electricity_Reliability_031611 Galvin Power ORGElectricity_Reliability_031611 Galvin Power ORG
Electricity_Reliability_031611 Galvin Power ORG
 
17_ACaseStudy.pdf
17_ACaseStudy.pdf17_ACaseStudy.pdf
17_ACaseStudy.pdf
 
Decision Support System for Energy Saving Analysis in Manufacturing Industry
Decision Support System for Energy Saving Analysis in Manufacturing IndustryDecision Support System for Energy Saving Analysis in Manufacturing Industry
Decision Support System for Energy Saving Analysis in Manufacturing Industry
 
IRJET- An Energy Conservation Scheme based on Tariff Moderation
IRJET- An Energy Conservation Scheme based on Tariff ModerationIRJET- An Energy Conservation Scheme based on Tariff Moderation
IRJET- An Energy Conservation Scheme based on Tariff Moderation
 
Distribution Automation Challenges
Distribution Automation ChallengesDistribution Automation Challenges
Distribution Automation Challenges
 
Dr.pptx1
Dr.pptx1Dr.pptx1
Dr.pptx1
 
Energy Conservation By Mehfooz Qazi
Energy Conservation By Mehfooz QaziEnergy Conservation By Mehfooz Qazi
Energy Conservation By Mehfooz Qazi
 
Energy Management Systems: Recommendations for decision makers
Energy Management Systems: Recommendations for decision makersEnergy Management Systems: Recommendations for decision makers
Energy Management Systems: Recommendations for decision makers
 
Energy management &amp & audit
Energy management &amp & auditEnergy management &amp & audit
Energy management &amp & audit
 
Pay-As-You-Go Energy Meter with GSM Module
Pay-As-You-Go Energy Meter with GSM ModulePay-As-You-Go Energy Meter with GSM Module
Pay-As-You-Go Energy Meter with GSM Module
 

Plus de Ameen San

Application of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage RegulationApplication of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage RegulationAmeen San
 
Load Characteristics
Load CharacteristicsLoad Characteristics
Load CharacteristicsAmeen San
 
Stepper motor
Stepper motor Stepper motor
Stepper motor Ameen San
 
PLC application
PLC applicationPLC application
PLC applicationAmeen San
 
PLC arithmatic functions
PLC arithmatic functionsPLC arithmatic functions
PLC arithmatic functionsAmeen San
 
PLC data types and addressing
PLC data types and addressingPLC data types and addressing
PLC data types and addressingAmeen San
 
PLC Counters
PLC CountersPLC Counters
PLC CountersAmeen San
 
PLC Traffic Light Control
PLC Traffic Light ControlPLC Traffic Light Control
PLC Traffic Light ControlAmeen San
 
PLC Internal Relays
PLC Internal RelaysPLC Internal Relays
PLC Internal RelaysAmeen San
 
PLC Intro to programming
PLC Intro to programmingPLC Intro to programming
PLC Intro to programmingAmeen San
 
PLC Logic Circuits
PLC Logic CircuitsPLC Logic Circuits
PLC Logic CircuitsAmeen San
 
PLC input and output devices
PLC input and output devices PLC input and output devices
PLC input and output devices Ameen San
 
PLC Applications
PLC ApplicationsPLC Applications
PLC ApplicationsAmeen San
 
Protection Devices and the Lightning
Protection Devices and the LightningProtection Devices and the Lightning
Protection Devices and the LightningAmeen San
 
Circuit Breakers
Circuit BreakersCircuit Breakers
Circuit BreakersAmeen San
 
Engineering Economy
Engineering EconomyEngineering Economy
Engineering EconomyAmeen San
 
Accounting & financial decisions
Accounting & financial decisionsAccounting & financial decisions
Accounting & financial decisionsAmeen San
 

Plus de Ameen San (20)

Application of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage RegulationApplication of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage Regulation
 
Load Characteristics
Load CharacteristicsLoad Characteristics
Load Characteristics
 
Stepper motor
Stepper motor Stepper motor
Stepper motor
 
PLC application
PLC applicationPLC application
PLC application
 
PLC arithmatic functions
PLC arithmatic functionsPLC arithmatic functions
PLC arithmatic functions
 
PLC data types and addressing
PLC data types and addressingPLC data types and addressing
PLC data types and addressing
 
PLC Counters
PLC CountersPLC Counters
PLC Counters
 
PLC Traffic Light Control
PLC Traffic Light ControlPLC Traffic Light Control
PLC Traffic Light Control
 
PLC Timers
PLC TimersPLC Timers
PLC Timers
 
PLC Internal Relays
PLC Internal RelaysPLC Internal Relays
PLC Internal Relays
 
PLC Intro to programming
PLC Intro to programmingPLC Intro to programming
PLC Intro to programming
 
PLC Logic Circuits
PLC Logic CircuitsPLC Logic Circuits
PLC Logic Circuits
 
PLC input and output devices
PLC input and output devices PLC input and output devices
PLC input and output devices
 
PLC Applications
PLC ApplicationsPLC Applications
PLC Applications
 
Protection Devices and the Lightning
Protection Devices and the LightningProtection Devices and the Lightning
Protection Devices and the Lightning
 
Protection
ProtectionProtection
Protection
 
Relays
RelaysRelays
Relays
 
Circuit Breakers
Circuit BreakersCircuit Breakers
Circuit Breakers
 
Engineering Economy
Engineering EconomyEngineering Economy
Engineering Economy
 
Accounting & financial decisions
Accounting & financial decisionsAccounting & financial decisions
Accounting & financial decisions
 

Dernier

Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitterShivangiSharma879191
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniquesugginaramesh
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction managementMariconPadriquez1
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 

Dernier (20)

Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniques
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction management
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 

ELECTRICAL DISTRIBUTION TECHNOLOGY

  • 2. 06/04/35 2 Chapter Outline Introduction Factors affecting distribution system planning Present distribution system planning techniques Distribution system planning models Computer central role in distribution planning Impact of dispersed storage and generation Renewable resources of generation Dr.A.Arunagiri Introduction Dr.A.Arunagiri The electrical power system is very complex system. Distribution is about 50% of the capital cost of the power system. The power system consists of three main parts Generation plants, Transmission and Distribution. The electrical distribution system is a part of the system between the transmission and the consumer service point. The electrical distribution system is divided into primary and secondary distribution.
  • 3. 06/04/35 3 Typical Electrical Power System Dr.A.Arunagiri The electrical distribution systems consists of: Dr.A.Arunagiri 1.Sub transmission 2.Distribution substation 3.Primary feeders 4.Distribution transformers 5.Secondary circuits 6.Service drops
  • 4. 06/04/35 4 Distribution System Dr.A.Arunagiri Sub-transmission Dr.A.Arunagiri The sub-transmission is an electrical network designed to supply the electrical power from the bulk power source (Transmission line) to the distribution sub-station at a voltage ranging from 33 to 220 kV. May be over head or underground cables. There are six types of sub-transmission are: • Radial system. • Primary Loop System. • Primary Selective. •Secondary selective • Spot Network • Grid Network
  • 10. 06/04/35 10 (b)Single Wire Earth Return (SWER) Dr.A.Arunagiri Dr.A.Arunagiri
  • 12. 06/04/35 12 Dr.A.Arunagiri Types of Distribution System (a) Single Phase Dr.A.Arunagiri
  • 13. 06/04/35 13 (C ) Three phase Three Wire Dr.A.Arunagiri (d) Three Phase four Wire Dr.A.Arunagiri
  • 14. 06/04/35 14 Basic Distribution Systems • Radial • Primary Loop • Primary Selective • Secondary Selective • Spot Network • Grid Network Dr.A.Arunagiri Factors Affecting Distribution System Planning  Load demand and load characteristics  Voltage level at the customer point  Type of secondary circuits  Size and location of distribution transformer  Types of primary distribution system  Loads at primary distribution level  Size and location of distribution substation  Routing and capacity of associated sub- transmission lines Dr.A.Arunagiri
  • 15. 06/04/35 15 Factors Affecting Distribution System Planning…….  Restrictions such as  Permissible voltage deviations  Voltage dip and flicker  Service continuity and reliability  Types of protection to be employed  Choice of circuit breakers, reclosers and sectionalizers  Requirement of capacitors for power factor correction and loss minimization  Requirement of voltage regulators  Types of transformers and availability of space for transformers  Insulation levels Dr.A.Arunagiri Distribution system Planning Technique  Load flow programs  Radial or loop load flow programs  Short-circuit programs  Voltage drop calculation programs  Total system impedance calculation programs  Load forecasting programs  Voltage regulation and regulator setting programs  Capacitor planning programs  Substation optimal sitting and sizing programs  Reliability programs Dr.A.Arunagiri
  • 16. 06/04/35 16 However, in general, the overall concept of automatically using output of each program as input for the next program is not in use. Engineering judgment and trial and error method are used in system planning. In this chapter, we shall discuss some of the distribution planning and operation techniques. Dr.A.Arunagiri Future Distribution System Planning Components Vision: A clear vision for the future communicates a sense of the kind of organization, power utility needs to become, and outlines the kind of results it must achieve. The vision provides a continuing focus and constantly reminds the employees and consumers of what the company trying to change.  Mission: For particular task there can be a mission statement such as Electricity for all KSA by the end of next decade  Values: The power utility leadership must create values such as consumer satisfaction, environmental responsibility. Dr.A.Arunagiri
  • 17. 06/04/35 17 Distribution system planning models Traditional-Least cost model: It is a process by which utilities minimize the cost of supplying a given amount of power. The existing system inadequacies are identified as: • Poor voltage regulation • Higher system loss • Higher equipment failure/breakdown • Bad quality of power supply • No scope for future growth. Dr.A.Arunagiri The initial system improvement can be very cost effective in removing the above system inadequacies as compared to the other alternatives of laying a new extended system. Thus there are two options:  System improvement  Expansion of the existing network Dr.A.Arunagiri
  • 18. 06/04/35 18 (a) System Improvement Augmentation and strengthening of the existing system Improving the reliability and quality of supply Reduction of commercial and technical loss and / or Dr.A.Arunagiri b)Expansion of the existing network When augmentation and strengthening of existing system are involved the benefits of saving in losses (kw and energy), net revenue increase due to additional sale of power and energy after adjusting the expenditure incurred on generation of the additional energy must be maximized. Dr.A.Arunagiri
  • 19. 06/04/35 19 2. Demand Side Planning(DSP) It is the process by which power utilities quantify and assess the programmes to alter the load pattern and level of their consumer’s demand for electricity. This is planning at the consumer level and often has a long planning period, much longer than distribution system planning. It can take years of slow progress to obtain meaningful levels of participation. Dr.A.Arunagiri The low cost demand side option can be : Implementing energy conservation programmes Providing vigilance and detection of theft. Dr.A.Arunagiri
  • 20. 06/04/35 20 DSM programmes generally fall into three main categories: 1 Conservation programmes Reduce energy use with programmes to improve the efficiency of the equipments (like lighting and motors), buildings and industrial processes as per the energy conservation act. 2 load management programmes: Redistribute energy demands to spread it more evenly throughout the day. Some way of doing this are: Load shifting programmes ( shifting some of the loads during peak period to off peak period) Time -of –use ( Charging more for electricity during peak demand) Interruptible rates( providing rate discounts in exchange for the right to reduce consumers electricity allocation each year during few hours when electricity demand is the highest Types of DSM Dr.A.Arunagiri 3. Strategic load growth programmes: Increase energy use during some periods, (Encourage cost effective electrical technologies that operate primarily during periods of low electricity demand.) The following approaches can be used.  General information programmes to inform consumers about generic energy efficientoptions  Site – specific information programmes that provide information about specific DSM measures appropriate for a particular industry , agricultureor home.  Financing programmes to assist consumers to pay for DSM measures includingloans, rebates, and shared savings programmes Dr.A.Arunagiri
  • 21. 06/04/35 21  Direct installation programmes that provide complete services to design, finance and install a package of efficiency measures.  Alternative tariff programmes including time-of-use tariff, interruptible tariff, and load shifting tariff. ( These programmes usually do not save energy but they are effective ways to shift loads to off peak periods.  Bidding programmes in which utility solicits bids from consumers and energy service companies.  Load limiters are effective in demand side management , as they limit the maximum power that the consumer draws from the supply. Dr.A.Arunagiri The process of designing and implementing DSM programmes generally consists of the following steps.  Identifying the sectors, end -uses and efficiency measures to target  Developing programme design  Conducting cost-effective screening  Preparing an implementation plan  Implementing programmes and  Evaluating programmes. Dr.A.Arunagiri
  • 22. 06/04/35 22 Benefits of DSM • Reduces consumers energy bills • Reduces the need for the new plant, transmission and distribution construction • Stimulates economic development • Creates long time jobs that benefits the economy • Increases the competitiveness of the local enterprises • Can reduce maintenance and equipment replacement cost • Reduces local air pollution • Reduces emission s that contribute to national and international environmental problems such as acid rain and global warming • Enhances national security by easing dependence on foreign energy sources Dr.A.Arunagiri Computer central role in distribution planning  Software needs: generally is selected on the basis of the least life cycle cost or least ownership costs (hiring or purchase + training + maintenance costs). The software must be. – Bestoverallperformance – Bestsolution – Bestopen architecture system  Analysis of the system computer aided power flow studies in improving the performance of the existing sub-transmission and distribution systems and proposed expansion of network up to the meter point (Consumers). Studies will provide – Active and reactive power flows as well as the locations of capacitors – Voltage variation (at each node or bus, percent variation) – Peak power losses and energy losses – Computation of commercial losses of feeder – Overloading of transformers : Dr.A.Arunagiri
  • 23. 06/04/35 23 Computer central role in distribution planning  Data: success of any information technology system is highly dependent on the accurate, up to date field data for improvement in the network and system. Information must be clear and up- dated on: Nodes Single line diagram Distribution substation Primary feeder Distribution transformer and secondary feeder Consumer data Load data Dr.A.Arunagiri Elements of the distribution system  Distribution Transformer  Primary distribution feeder  Secondary distribution feeder  Protection devices and instrumentation Dr.A.Arunagiri
  • 24. 06/04/35 24 Dispersed Generation Dr.A.Arunagiri Impact of dispersed storage and generation • This is When the generating plant is connected to a distribution network capable of supplying power to the consumer load directly . • This enhances the reliability and the quality of power supply. • The expectations of the reliability especially for data centers, call centers, computer controlled critical process/businesses, continuous process industries, petro chemical refineries are four nines (99.99%). Dr.A.Arunagiri
  • 25. 06/04/35 25 Impact of dispersed generation…. For dispersed generations line losses will be nominal since there is no transmission system is required. Dispersed generation with local radial distribution network will play an important role in the 21st century. Dispersed generation is generally from local renewable sources. This saves environment degradation compared to conventional thermal generation. Dr.A.Arunagiri Renewable resources of generation  Fuel cells  Solar photovoltaic  Wind energy  Tidal wave energy from ocean  Small hydro (up to 25 MW capacity, pumped storage)  Geo-thermal  Bio-mass  Municipal and industrial west Dr.A.Arunagiri
  • 26. 06/04/35 26 Net Metering The kilo watt hour meter(import – export meter) can be used to accurately register the flow of electricity in either direction. This means the ‘netting’ process associated with net metering happens automatically Dr.A.Arunagiri Assignment 1 Q.1 Draw the one line diagram of the electrical power system available in KSA.. Indicate the voltage levels for Generation Transmission Sub transmission Primary Feeder Secondary Feeder Q2 Mention and discuss the different types of the renewable resources of generation available in the KSA. Dr.A.Arunagiri