SlideShare une entreprise Scribd logo
1  sur  49
Télécharger pour lire hors ligne
Photovoltaic Systems Training

Session 2 ‐ Execution and 
Commissioning



Javier Relancio & Luis Recuero
Generalia Group

September 16th 2010



 http://www.leonardo-energy.org/training-pv-systems-design-
          construction-operation-and-maintenance
PHOTOVOLTAIC SYSTEM
       Design, Execution, Operation & Maintenance



         EXECUTION AND COMMISSIONING

                                                       Javier Relancio. Generalia Group.  16/09/2010
                                                                                    www.generalia.es
2
    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
INDEX

    Civil works. Infrastructure preparation

    Mechanical works

    Electrical works

    Environmental issues

    Quality. Critical issues during execution

    Safety & Labor risks

    Commissioning tests. Key points

3
               http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
INDEX

    Civil works. Infrastructure preparation

    Mechanical works

    Electrical works

    Environmental issues

    Quality. Critical issues during execution

    Safety & Labor risks

    Commissioning tests. Key points

4
               http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Civil Works: Infrastructure preparation


Rooftop projects
    We may find little civil works, but it will be reduced to the trench
    opening for the connection of the inverters and the meters


Ground projects
    Civil works are very important
    A good definition for the civil works could mean an important
    saving in the project.


    Main civil works are:
         Terrain leveling
         Accesses and inside roads/paths
         Trench opening (AC & DC)




5
                     http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Terrain leveling



    It might be avoided as much as possible in order to reduce the environmental impact
    Only required works should be done:


     Selecting a flat terrain may avoid its leveling
     Selecting a structure type which can be fixed to the terrain by a “ground anchor”, instead
     of a concrete base
     Depending on the solution design, the choice between fixed or suntracking project can be
     determinant




     Source: QHOELET



6
                       http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Internal roads & paths



    It is recommended to use already existing paths
    We must take into account that the roads or paths have to allow the circulation of
    trucks. Truck turning radius must be considered:

                                                                       Length Minimum radius for Minimum radius
Vehicle Type                Nomenclature    Height   Width   Length   between   external front-  for internal back-
                                                                        axis        wheel               wheel
Light vehicle                    VL         1,30     2,10     5,80      3,40           7,30                4,20
2-Axis Omnibus                   B2         4,10     2,60     9,10      6,10           12,80               8,50
3-Axis Omnibus                   B3         4,10     2,60    12,10      7,60           12,80               7,40
2-Axis simple truck              C2         4,10     2,60     9,10      6,10           12,80               8,50
3-Axis simple truck           C3 / C4       4,10     2,60    12,20       7.6           12,80               7,40
                                                                       4,00 /
Trailer (Semi)              T2S1/ 2 / 3     4,10 *   2,60    15,20                     12,20               5,80
                                                                        7,00
                                                                       4,90 /
Trailer (Semi)              T3S1 / 2 / 3    4,10     2,60    16,70                     13,70               5,90
                                                                        7,90
                                                                       3,80 /
2 Axis trailer + 1 Double    C2 - R2 / 3    4,10     2,60    19,90     6,10 /          13,70               6,80
                                                                        6,40
                                                                       3,80 /
                            C3 - R2 / 3 /
3 Axis trailer + 1 Double                   4,10     2,60    19,90      6,10           13,70               6,80
                                  4
                                                                       /6,40


7
                      http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Internal roads & paths



Once the installation has been commissioned, internal paths & roads will not be used too
much, so a 25 cm depth path of a mixture 75% gravel, 25 % river sand, may be enough.



                   Minimal turning radius for
                   B3/C3 vehicles



                                                           Accesses and roads/paths detail
                                                                              75% gravel, 25 % river sand




                                                          Natural terrain




8
                 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Trenches



    In a PV project, all the cable must be buried underground
    Each 40 meters or each direction change, a manhole will be placed to ease the cable
    laying
    The project design might try to use the same section for all the trenches




9
                 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Trenches




     The trenches will have:

       A river sand base

       Space for the pipes

       Backfill of sifted soil and soft sand

       Cable caution tape

       In the case it is a vehicle passing
       area, it will have a concrete layer
       at the top




10
                     http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
INDEX

     Civil works. Infrastructure preparation

     Mechanical works

     Electrical works

     Environmental issues

     Quality. Critical issues during execution

     Safety & Labor risks

     Commissioning tests. Key points

11
                http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Mechanical works


     Structure type                 Weight                 Anticorrosion protection           Mechanical  
                                                                                              performance
     Galvanized steel               Resistant rooftops     8 years (non salty atmosphere)     Good
     Hot galvanized steel           Resistant rooftops     More than 25 years                 Good
     Anodizing Aluminum             Light rooftops         More than 20 years                 Medium
     No structure                   Light rooftops         ‐                                  ‐



For fixed installations, the structure can be set parallel to the surface
where it is to be installed (flat), or with the optimum tilt for each
latitude (Tilted)

     Flat                                 Tilted
     No wind action                       Important wind action

     Worse cooling                        Best natural cooling

     Lower cost (Both for structure &     Higher cost (Both for structure & 
     mounting)                            mounting)

                                                                                  Photo: Krannich

12
                        http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Mechanical works



The structure anchor for a ground installation may
have the following possibilities:


     Ground anchor
         These screws have an average length
         between 1 -1,6 meters
         Easy to be dismounted
         They can be adapted to the terrain orography
                                                                                Source: Conectavol
         They can’t be used in a rocky terrain


     Concrete basement
         Above or under the ground
         It requires a flat surface
         Easy to be dismounted (if it is above the
         ground)


13
                     http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Roof anchorage



                               Metal roof anchors:
                                   We have two options:
                                             Direct to purlins anchorage
                                             Specially designed anchors to be fixed directly to the roof
                                             sheathing


                                   It is recommended to use the direct to purlin anchorage. If
                                   tilted structure is being used, other choice could be risky.


                               Tile roof anchorage:
                                          A typical solution is using a “U” shaped piece which is
                                          anchored directly to the roof, avoiding to drill the tile
                                             It is necessary to move the tiles (danger of leaks)
                                          With a special piece we can go through the tile
                                             Danger to break the tile
     Source: SoportesSolares

14
                         http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
PV Roofs




     Roof state:
The following aspects are to be evaluated:
          Safety
                We have to verify if the roof is safe. If not, we may install “lifeline”, “skylight
                network”
          Roof type
                Asbestos (Uralita) roofs are the most difficult ones, as it may be cracked by
                stepping on it, producing leaks, or it could even be broken, being really risky for
                the installers. In this case, it is recommended to change the whole roof to metal
                roof.
           Sealing
                It is important to use the most indicated sealing to avoid
                leaking. This sealers must have great elasticity and good
                mechanical resistance. They may be complemented by
                EPDM* bands

15      * a type of synthetic rubber (ethylene propylene diene Monomer)
PV Roofs


 Loads on the roof


     Material weight (average weight by square meter)

                               Element                              Weight

                              Structure                               2KG

                          Crystalline panels                         15KG

                      Thin film glass‐glass panel                    22KG

                      Thin film laminated panel                      6KG


     Wind effect
          During the design, both panel height and exposed surface must be considered
     Extra loads during the execution: such us tools, workers, materials…
     Accesses: The accesses will be distributed all along the roof surface, guaranteeing the
     worker safety and allowing them to carry up small materials and tools


16
                   http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
INDEX

     Civil works. Infrastructure preparation

     Mechanical works

     Electrical works

     Environmental issues

     Quality. Critical issues during execution

     Safety & Labor risks

     Commissioning tests. Key points

17
                http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Electrical works




     Cable for the panel strings


     •   We usually use the cable included by the panel manufacturers.
     Important to confirm with the manufacturer that this cable is included
          •   This cable are composed of copper: 4mm; 0,6/1kV
          •   This cables usually are ended in “fast connectors”: Multicontact,
              Tyco, etc




                                                       Source: Eastech Solar




18
                  http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Electrical works



     Roof installations



     Cable canalization might be done under hot galvanized cable tray or tubular conduit

     Cable tray canalization simplifies mounting works, and eases the maintenance tasks.

      Indoor, plastic(or metallic) cable tray might be used, as well as halogen-free cable




19
                    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Electrical works



     Ground installations


      Electrical works will be done in the trenches, so the cable must be designed for this use.
     It is recommended to use anti-mice cable, inside a tubular conduit.

                                                        Cable trenches might be really long, so the
                                                        trench design, number of cables by pipeline,
                                                        extra space by pipeline, manholes, etc.. could
                                                        be decisive to optimize the electrical works
                                                        duration
                                                        The cable should be previously marked in order
                                                        to avoid connecting issues
                                                        It is important to avoid corners or any element
                                                        which may cause any damage in the cable
                                                        isolation.



20
                     http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Electrical cabinets


Depending on its location, a different IP may be required
• For outdoor installations, at least IP 65 will be required
• For indoor installations, IP 21 could be enough (except for special conditions: water,
powder…)
It is really important to pay attention at the element connections, and the
identification of each cable & component in the project documentation
The thermal study of the cabinet is also important, verifying the minimal required volume
for the heat dissipation, and raising additional solutions as the incorporation of a heat
resistance in case of outdoor installations in very cold zones




21
Earthing system


The following elements must be earth connected


        PV panel frameworks
        Structure
        Metal cable tray
        Metal elements in electrical cabinets
        PV inverters


     For small facilities, the earthing system would be quite
simple: 2 – 3 pegs, depending on the soil resistivity

     For bigger facilities, a cable grid is usually implemented,
using the trench already opened for the energy cables, placing
an uncovered copper cable below the energy cables.                                  EARTH
                                                                                    CABLE


The section of this cable is to be calculated during the design

22
                       http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
INDEX

     Civil works. Infrastructure preparation

     Mechanical works

     Electrical works

     Environmental issues

     Quality. Critical issues during execution

     Safety & Labor risks

     Commissioning tests. Key points

23
                http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Our solar facility and the environment


     Nowadays we can find


       A change in the social sensibility for the environmental impacts. The society begins to
       have a greater conscience and a harder implication.


       This will be the real engine for the new environmental initiatives to be managed in a
       suitable way.


       The ISO Certification 14001, allows us to take and to show the others, our
       environmental commitment.


       For all this, the solar power companies should demonstrate the coherence with their
       ecological message, developing a good environmental policy




24
                   http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Environmental aspects & impacts



     Definitions (ISO 14001):


     Environmental aspect: Any element of the activities, products or services that is
         causing some type of impact on the environment can be considered as an
         environmental aspect.


     Environmental impact: Any change in the environment, either adverse or beneficial,
         resulting from the activities, products and services of an Organization.


     Residue: Any substance or object from which his holder detaches or has the obligation
         to become detached following the European rules & standards




25
                   http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Environmental aspects & impacts


     We must take into account the environmental management of our solar facility


     a. To know the in force legislation
     b. To know the environmental aspects that concern our business
     c. To evaluate the impact that has on the environment
     d. To propose indicators that give us a tangible evidence about the measured aspects,
          and their impacts, and to use them to develop new preventive and corrective
          measures
     e. To have an emergency plan derived from the knowledge of the different environmental
          aspects
     f.   To do the suitable management of the generated residues



The environmental management becomes necessary in the execution, as well as the operation
of the solar plant, therefore, an individual analysis of every project will be required




26
                     http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Example: Environmental management during
the project execution

 1. List of aspects and impacts

           Activity                      Aspect                 N/E                    Impact

                                                                            Atmospheric contaminations
                              Electric energy consumption       N
                                                                                   Visual Impacts
     PV installations (and           Fuel consumption           N               Atmospheric pollution
     Suntrackers, in case         Powder generation             N               Atmospheric pollution
        of being used)           Residues generation            N               Space in the dumpsite
                                                                                Atmospheric pollution
                                           Fire                  E
                                                                            Impact on the fauna & flora.
                                                                                N: Normal;     E: Extraordinary

 2. Emergency classification

                                                                                             Significant
         Aspect                  P                          S               A
                                                                                          YES=Y; NO=N

           Fire                  2                          4               8                    Y

     P: Probability; S: Seriousness; A: Assessment

27
                      http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Example: Environmental management during
the project execution


     3. Aspect classification (Normal aspects)


                                                                                             SIGNIFICANT
                      ASPECTS                          F         S         C        A
                                                                                               YES/ NO
            Electrical energy consumption              5         2         2        20           YES
           Dangerous residues generation               3         2         2        12           NO
             Urban residues generation                 4         1         2        12           NO
                  Noise generation                     3         1         1        6            NO
                 Fuel consumption                      3         2         2        12           NO
                 Powder generation                     3         1         1        6            NO
                 Paper consumption                     5         1         2        15           YES
                      Packages                         4         1         2        12           NO




     F: Frequency; S: Seriousness; C: Consequence; A: Assessment


28
                     http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Example: Environmental management during
the project execution


     4. Emergency plan

      EVENT/ EMERGENCY:                                                FIRE
       Preventive measures       Adaptation to the electrical and construction regulations. Fire‐extinguishers.
                                 • The work manager is the person in charge of the extinction of fire. 
                                 • In case of non‐controllable emergency, the work manager will take charge of 
                                   warning the external emergency services. 
         Actuation plan
                                 • The work responsible is the person in charge of giving the alarm and 
                                   controlling the evacuation of the whole staff. He must check that the 
                                   evacuation has been completed
             Practice            Fire
                                 The response time will be measured for the following aspects:
                                 • The fire warning.
       Practice description   
                                 • Staff evacuation.
                                 • The checking that the evacuation has been completed.
           Frequency             Yearly

29
                        http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Example: Environmental management during
the project execution

     5. Residue management general process:


     In every moment, we must:
       To develop a study of the residues that are being produced, in the execution and the
       operation of the solar power facility;


       To quantify the quantity of each one, and to do a management of the residue
       according to its type.

                         Urban residues                                Dangerous residues

                              Paper                                Toner with metallic components


                              Plastic                                         Batteries


                            Tins & Cans                                     Fluorescents


                 Toner without metallic components                     Oils (Vehicles / Motors)




30
                    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
INDEX

     Civil works. Infrastructure preparation

     Mechanical works

     Electrical works

     Environmental issues

     Quality. Critical issues during execution

     Safety & Labor risks

     Commissioning tests. Key points

31
                http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Quality: Critical aspects



The critical aspects referred to quality in the phase of execution are:


Materials
     Checking that we have received the goods that have been requested
     Inspection of the goods at their arrival to check possible material faults/defects
     This process will be developed for a certain number of samples previously defined by the
     quality department
     The checking of the electrical and mechanical parameters of the material, to avoid early
     breakdowns


Work execution
     Correct planning of the work: in order to avoid delays, dead times of the workers,
     managing the activities in “critical way”
     Updated documentation for the works: It is important to check that the workers have the
     latest edition of the information


32
                    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Quality: Critical aspects



                                               Work
                                               Manager


                                 1.Checking that the ordered material fits
                                   with the projects real requirements
                                 2.Checking that the real project conditions
                                   matched with the project design
                                 3.Managing the material administration and
                                   reception


            Material Administration                                                      Material Reception



 1.Checking that the items indicated in                                      1.Checking that the items that have
     the delivery notes corresponds with                                       arrived correspond to the items of
     the ordered ones                                                          the delivery note
 2. Checking any lacking item in the                                         2.Visual checking
     order and claiming for it                                               3.Checking of electrical and
 3. Checking the payments                                                      mechanical characteristics


33
                        http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Quality: Critical aspects




                  Work Manager



     1. Fulfillment of the planning deadlines
     2. Checking the documentation of the
        work orders
     3. Checking the quality in the
        intermediate milestones of the project                                  Worker
     4. Checking the management of the
        residues during and at the end of the
        project                                           1.   Work execution according to the

     5. Final checking of the work                             work order
                                                          2.   To notify incidents in the
                                                               accomplishment of the works
                                                          3.    Accomplishment of the checking
                                                               indicated in the work order




34
                      http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Panel inspections



        Samples
        selection
                               VISUAL                          ELECTRICAL                         THERMAL


                        Packages
        OF                                                     Panel arrays                       Panels
                        Panels




                                                           The electrical
                    • Frame defects                        characteristics differ from          Cell defects

                    • Glass defects                        the technical specs, used            Hot spots
     DETECTION
                    • Connection box defects               for the design and they              Cell bubbles
        OF
                    • Cable & connector defects            are out of the required
                                                           range


Although it might be true that the panels are the most expensive element in
the installation, a similar table should be done for the rest of the elements
35
                        http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Thermography




     The Thermography is a simple method to detect defaults in the solar panels

     The checking of the installation is developed in a rapid and visual form

      It saves time, as it identifies directly the problematic panel without having to do
     complex checks in the different strings




36
                     http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
INDEX

     Civil works. Infrastructure preparation

     Mechanical works

     Electrical works

     Environmental issues

     Quality. Critical issues during execution

     Safety & Labor risks

     Commissioning tests. Key points

37
                http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Labor risks evaluation plan



     1. Introduction


     Within every company it is obligatory to have a labor risk evaluation plan.
     Even in the case that we subcontract other companies, it is necessary to check that each
     company has its labor risk evaluation plan adapted to our activity.



             Knowledge of the particularities 
                of the company activities

                                                               Risk analysis for each activity


             Actions depending on the risks




38
                     http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Labor risks evaluation plan


      2. Activitie characteristics

                PV on the roof                        PV on the ground (Fix)              PV on the ground (Suntracking)

     Small facilities: From 2‐3 KW to 100KW 
                                                     Larger facilities: >100 KW               Larger facilities: >100 KW
                (Or even more)

            Working at great heights                  Working on the ground                    Working on the ground


            Different types of roofs                     Earth movements                          Earth movements


             Different tilts of roofs                    Trench openings                          Trench openings

       Sharing the work with the industry 
                                                    Larger number of workers                 Larger number of workers
           where our plant is located

         Electrical cabling and inverter                                              Usage of cranes to fix the panel structure 
                                                     Possibility of using cranes
                commissioning                                                                     to the Suntrackers

                                                   Electrical cabling and inverter          Electrical cabling and inverter 
                                                          commissioning                            commissioning


39
                             http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Labor risks evaluation plan



     3. Activity risks




              PV on the roof                    PV on the ground (Fix)                PV on the ground (Suntracking)


             Falls from the roof                   Falls into trenches                       Falls into trenches

      Accidents due to material falling    To be run over by working vehicles        To be run over by working vehicles

     Risk from the industry where the 
                                                   Electrocution risk                        Electrocution risk
              plant is located

             Electrocution risk             Accidents due to material falling         Accidents due to material falling

                                                                                Accident due to collision with the suntracker




40
                           http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Labor risks evaluation plan



     4. Activitie summary


        To analyze the photovoltaic activities, to know and to evaluate the risks of every job
        inside every activity.


        To train the staff on the risks depending on their job or workstation


        To distribute the equipments of individual protection adapted to every workstation


        To designate a person in charge of checking the correct execution of the prevention
        plans


        To develop an emergency and evacuation plan




41
                    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
INDEX

     Civil works. Infrastructure preparation

     Mechanical works

     Electrical works

     Environmental issues

     Quality. Critical issues during execution

     Safety & Labor risks

     Commissioning tests. Key points

42
                http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Project commissioning




                                              Technical documentation
          Project design


 Plans                                                                                  Operation &
 Engineering                                                                            Maintenance
 Technical datasheets
 Equipment manuals                                                               Preventive maintenance plan
 Suntracker manual                                                               Corrective maintenance plan
                                                Commissioning                    Monitoring system manual




            Execution
                                                  Commissioning checklist
                                                  Plant production checking
Project modification                              Generator production checking
Done inspections                                  Inverter production checking
Element identification



43
                     http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Plant production checking


     As the aim that we pretend is to maximize the productive capacity of the photovoltaic solar
     plant, we need to check, from time to time, a test of the plant productive capacity (i.e. every
     three years)


          If the plant is very large, it could be worthy to do a test every year


     The plant performance can be measured up by the instantaneous response to:
          Cell temperature (Depending on the outdoor temperature, wind, irradiance)
          Irradiance



We will evaluate:
         The power, in alternating current at the plant output (meter)
         Global and direct irradiance in a calibrated cell (from a similar technology to the one used
         for the generator and parallel with it)
         Cell temperature: sticking a thermal sensor to the calibrated cell

44
                    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Plant production checking




                            Outdoor temperature                          For the capture of the indicated
                            (Optional)
                                                                         variables we will need to have:

                                Irradiance
                                                                               A meteorological station
                                                                               where the information of
                                                                               Temperature and irradiance
                                                                               will be registered


Source: Geonica                                                                A meter (with integrated
                                                                               communications) from which

AC Power (at the                                                               we can read the output
meter output)                                                                  power


                                            TEMP. PANEL FV



45
                   http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Plant production checking


     In the case of using suntrackers, we have to verify the equipment performance every
     hour by testing the shadow projected by a rod perpendicular to the plane of the
     generator


     Minimal measure period: 5 consecutive days dawn - dusk


     Condition: The minimal period of irradiance over 600W/m2 must be at least 12 hours


     Periodicity of the measure of output power - irradiance-temperature: 10 mins


     The obtained measures of output power-irradiance-temperature are compared to the
     expected ones and the deviations between both are analyzed


     If the legislation allows it in the future, the modernization or extension of the plant for
     repowering might be recommended


46
                  http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Testing of PV Generator electrical
characteristics


         Objective: To determine the electrical characteristics under
         the “Standard metering conditions”, defined by:
           • Irradiance: G = 1000 W/m2
           • Cell temperature: CT=25ºC.

     We obtain the C-V curve from the generator and the
                                                                             I
     one from a standard module, and both are compared
     under the conditions above-mentioned


     These tests have to be done two hours before and after                                                  V
     the local midday and the global irradiance has to be a
     over 700W/m2


     Nowadays we can find specific equipments to obtain the
     C-V curve of a PV generator and move it into standard
     conditions

47
                    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Testing of the inverter electrical characteristics


     Is the second most important element in a PV facility

     Objective: To determine the characteristics which define the
     energetic performance of an inverter:
       • Efficiency
       • Maximum Power Point Tracking


     The European efficiency of the inverter, has to be
     verified with the measures commented in the previous
     slides, attaching the power measure and the voltage
     in the DC side


     Furthermore, it must be verified the inverter capacity
     to track the Maximum Power Point (MPP)

                                                                        Source: SMA




48
                 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
End of Session 2




                         Thank you for attending




           http://www.leonardo-energy.org/training-pv-systems-design-
                    construction-operation-and-maintenance




49

Contenu connexe

Tendances

Solar PV Codes and Standards
Solar PV Codes and StandardsSolar PV Codes and Standards
Solar PV Codes and StandardsSolar Reference
 
A Report on solar power plant installation
A Report on solar power plant installationA Report on solar power plant installation
A Report on solar power plant installationAmitesh Kumar
 
SOLAR DESIGN -PREMKUMAR-1
SOLAR DESIGN -PREMKUMAR-1SOLAR DESIGN -PREMKUMAR-1
SOLAR DESIGN -PREMKUMAR-1Murugappa Group
 
Photovoltaics Case Study
Photovoltaics Case StudyPhotovoltaics Case Study
Photovoltaics Case StudyLeonardo ENERGY
 
10 pv system_design
10 pv system_design10 pv system_design
10 pv system_designmemoaden
 
ABB Training Colombia Inverters - Focus on residential and commercial solutio...
ABB Training Colombia Inverters - Focus on residential and commercial solutio...ABB Training Colombia Inverters - Focus on residential and commercial solutio...
ABB Training Colombia Inverters - Focus on residential and commercial solutio...Jesús Leyton P
 
Net metering requirements in punjab for grid interactive rooftop SPV Power Plant
Net metering requirements in punjab for grid interactive rooftop SPV Power PlantNet metering requirements in punjab for grid interactive rooftop SPV Power Plant
Net metering requirements in punjab for grid interactive rooftop SPV Power PlantHarish Sharma
 
Performance paramter and suggestion to optizing the performnce of grid connec...
Performance paramter and suggestion to optizing the performnce of grid connec...Performance paramter and suggestion to optizing the performnce of grid connec...
Performance paramter and suggestion to optizing the performnce of grid connec...Ashish Verma
 
PV inverter's instruction by thinkpower
PV inverter's instruction by thinkpowerPV inverter's instruction by thinkpower
PV inverter's instruction by thinkpowerChengdong Li
 
Photovoltaic Training - Session 4 - Plant Maintenance
Photovoltaic Training - Session 4 - Plant MaintenancePhotovoltaic Training - Session 4 - Plant Maintenance
Photovoltaic Training - Session 4 - Plant MaintenanceLeonardo ENERGY
 
Solar power sector: Technology, BoS, Pre Feasbility and phase of project dev...
Solar power sector: Technology, BoS, Pre Feasbility and  phase of project dev...Solar power sector: Technology, BoS, Pre Feasbility and  phase of project dev...
Solar power sector: Technology, BoS, Pre Feasbility and phase of project dev...Ashish Verma
 
Project of Solar ppt
Project of Solar pptProject of Solar ppt
Project of Solar pptSOUMYA DATTA
 
Photovoltaic Charge Controller
Photovoltaic Charge ControllerPhotovoltaic Charge Controller
Photovoltaic Charge ControllerAvinav Prince
 
DESIGN AND DEVELOPMENT OF SOLAR CHARGE CONTROLLER WITH SUN TRACKING
DESIGN AND DEVELOPMENT OF SOLAR CHARGE CONTROLLER WITH SUN TRACKINGDESIGN AND DEVELOPMENT OF SOLAR CHARGE CONTROLLER WITH SUN TRACKING
DESIGN AND DEVELOPMENT OF SOLAR CHARGE CONTROLLER WITH SUN TRACKINGChukka Nikhil Chakravarthy
 
Tarining Report on Siemens
Tarining Report on SiemensTarining Report on Siemens
Tarining Report on SiemensStudent
 

Tendances (20)

Inspecting Photovoltaic (PV) Systems for Code Compliance
Inspecting Photovoltaic (PV) Systems for Code ComplianceInspecting Photovoltaic (PV) Systems for Code Compliance
Inspecting Photovoltaic (PV) Systems for Code Compliance
 
Solar PV Codes and Standards
Solar PV Codes and StandardsSolar PV Codes and Standards
Solar PV Codes and Standards
 
A Report on solar power plant installation
A Report on solar power plant installationA Report on solar power plant installation
A Report on solar power plant installation
 
Designing Solar PV Systems ( Utility Scale)
Designing Solar PV Systems ( Utility Scale)Designing Solar PV Systems ( Utility Scale)
Designing Solar PV Systems ( Utility Scale)
 
SOLAR DESIGN -PREMKUMAR-1
SOLAR DESIGN -PREMKUMAR-1SOLAR DESIGN -PREMKUMAR-1
SOLAR DESIGN -PREMKUMAR-1
 
Photovoltaics Case Study
Photovoltaics Case StudyPhotovoltaics Case Study
Photovoltaics Case Study
 
10 pv system_design
10 pv system_design10 pv system_design
10 pv system_design
 
ajit-cv-2015
ajit-cv-2015ajit-cv-2015
ajit-cv-2015
 
Final Year Project Presentation
Final Year Project Presentation Final Year Project Presentation
Final Year Project Presentation
 
ABB Training Colombia Inverters - Focus on residential and commercial solutio...
ABB Training Colombia Inverters - Focus on residential and commercial solutio...ABB Training Colombia Inverters - Focus on residential and commercial solutio...
ABB Training Colombia Inverters - Focus on residential and commercial solutio...
 
Net metering requirements in punjab for grid interactive rooftop SPV Power Plant
Net metering requirements in punjab for grid interactive rooftop SPV Power PlantNet metering requirements in punjab for grid interactive rooftop SPV Power Plant
Net metering requirements in punjab for grid interactive rooftop SPV Power Plant
 
Performance paramter and suggestion to optizing the performnce of grid connec...
Performance paramter and suggestion to optizing the performnce of grid connec...Performance paramter and suggestion to optizing the performnce of grid connec...
Performance paramter and suggestion to optizing the performnce of grid connec...
 
PV inverter's instruction by thinkpower
PV inverter's instruction by thinkpowerPV inverter's instruction by thinkpower
PV inverter's instruction by thinkpower
 
Photovoltaic Training - Session 4 - Plant Maintenance
Photovoltaic Training - Session 4 - Plant MaintenancePhotovoltaic Training - Session 4 - Plant Maintenance
Photovoltaic Training - Session 4 - Plant Maintenance
 
Solar power sector: Technology, BoS, Pre Feasbility and phase of project dev...
Solar power sector: Technology, BoS, Pre Feasbility and  phase of project dev...Solar power sector: Technology, BoS, Pre Feasbility and  phase of project dev...
Solar power sector: Technology, BoS, Pre Feasbility and phase of project dev...
 
Project of Solar ppt
Project of Solar pptProject of Solar ppt
Project of Solar ppt
 
Photovoltaic Charge Controller
Photovoltaic Charge ControllerPhotovoltaic Charge Controller
Photovoltaic Charge Controller
 
DESIGN AND DEVELOPMENT OF SOLAR CHARGE CONTROLLER WITH SUN TRACKING
DESIGN AND DEVELOPMENT OF SOLAR CHARGE CONTROLLER WITH SUN TRACKINGDESIGN AND DEVELOPMENT OF SOLAR CHARGE CONTROLLER WITH SUN TRACKING
DESIGN AND DEVELOPMENT OF SOLAR CHARGE CONTROLLER WITH SUN TRACKING
 
On grid
On gridOn grid
On grid
 
Tarining Report on Siemens
Tarining Report on SiemensTarining Report on Siemens
Tarining Report on Siemens
 

En vedette

Photovoltaic Training - Session 5 - Economic and Financial Analysis
Photovoltaic Training - Session 5 - Economic and Financial AnalysisPhotovoltaic Training - Session 5 - Economic and Financial Analysis
Photovoltaic Training - Session 5 - Economic and Financial AnalysisLeonardo ENERGY
 
053013 pv system site assessment (1)
053013 pv system site assessment (1)053013 pv system site assessment (1)
053013 pv system site assessment (1)solpowerpeople
 
Solar photovoltaic systems
Solar photovoltaic systemsSolar photovoltaic systems
Solar photovoltaic systemsanish_hercules
 
Presentation on solar cell
Presentation on solar cellPresentation on solar cell
Presentation on solar cellOmar SYED
 
Analisi del degrado delle caratteristiche dei moduli affetti dai fenomeni ‘PI...
Analisi del degrado delle caratteristiche dei moduli affetti dai fenomeni ‘PI...Analisi del degrado delle caratteristiche dei moduli affetti dai fenomeni ‘PI...
Analisi del degrado delle caratteristiche dei moduli affetti dai fenomeni ‘PI...Claudio Liciotti
 
Presentation glyndwr ch stu 2
Presentation glyndwr ch stu 2Presentation glyndwr ch stu 2
Presentation glyndwr ch stu 2Alex Veligorsky
 
Resume- Keara Gaffey LPC
Resume- Keara Gaffey LPCResume- Keara Gaffey LPC
Resume- Keara Gaffey LPCKeara Gaffey
 
Hybrid converter
Hybrid converterHybrid converter
Hybrid converterNiraj Muley
 
Co2 emission prospect
Co2 emission prospectCo2 emission prospect
Co2 emission prospectGaetan Lion
 
Global Energy Consumption and alternative technologies
Global Energy Consumption and alternative technologiesGlobal Energy Consumption and alternative technologies
Global Energy Consumption and alternative technologiesKnut Linke
 
power generation through solar power for PV module applications
power generation through solar power  for PV module applicationspower generation through solar power  for PV module applications
power generation through solar power for PV module applicationsSai Kumar
 
Residential distribution system harmonic[final]
Residential distribution system harmonic[final]Residential distribution system harmonic[final]
Residential distribution system harmonic[final]Bishwarup Mukherjee
 
Five Design Solutions - Portfolio Case Studies
Five Design Solutions - Portfolio Case StudiesFive Design Solutions - Portfolio Case Studies
Five Design Solutions - Portfolio Case StudiesDarren Ryan
 
Photovoltaic Project
Photovoltaic ProjectPhotovoltaic Project
Photovoltaic ProjectHarry Indig
 
Fuel cells project_maree
Fuel cells project_mareeFuel cells project_maree
Fuel cells project_mareemareenotmarie
 
Interactive inverters
Interactive invertersInteractive inverters
Interactive invertersmareenotmarie
 
A MULTILEVEL MEDIUM VOLTAGE INVERTER FOR STEP UP TRANSFORMER LESS GRID CONNEC...
A MULTILEVEL MEDIUM VOLTAGE INVERTER FOR STEP UP TRANSFORMER LESS GRID CONNEC...A MULTILEVEL MEDIUM VOLTAGE INVERTER FOR STEP UP TRANSFORMER LESS GRID CONNEC...
A MULTILEVEL MEDIUM VOLTAGE INVERTER FOR STEP UP TRANSFORMER LESS GRID CONNEC...saif ulla baig
 

En vedette (20)

Photovoltaic Training - Session 5 - Economic and Financial Analysis
Photovoltaic Training - Session 5 - Economic and Financial AnalysisPhotovoltaic Training - Session 5 - Economic and Financial Analysis
Photovoltaic Training - Session 5 - Economic and Financial Analysis
 
053013 pv system site assessment (1)
053013 pv system site assessment (1)053013 pv system site assessment (1)
053013 pv system site assessment (1)
 
Solar photovoltaic systems
Solar photovoltaic systemsSolar photovoltaic systems
Solar photovoltaic systems
 
Presentation on solar cell
Presentation on solar cellPresentation on solar cell
Presentation on solar cell
 
Analisi del degrado delle caratteristiche dei moduli affetti dai fenomeni ‘PI...
Analisi del degrado delle caratteristiche dei moduli affetti dai fenomeni ‘PI...Analisi del degrado delle caratteristiche dei moduli affetti dai fenomeni ‘PI...
Analisi del degrado delle caratteristiche dei moduli affetti dai fenomeni ‘PI...
 
Presentation glyndwr ch stu 2
Presentation glyndwr ch stu 2Presentation glyndwr ch stu 2
Presentation glyndwr ch stu 2
 
Resume- Keara Gaffey LPC
Resume- Keara Gaffey LPCResume- Keara Gaffey LPC
Resume- Keara Gaffey LPC
 
The Power of Data
The Power of DataThe Power of Data
The Power of Data
 
Residential Photovoltaics in Hawaii
Residential Photovoltaics in HawaiiResidential Photovoltaics in Hawaii
Residential Photovoltaics in Hawaii
 
Hybrid converter
Hybrid converterHybrid converter
Hybrid converter
 
Co2 emission prospect
Co2 emission prospectCo2 emission prospect
Co2 emission prospect
 
Global Energy Consumption and alternative technologies
Global Energy Consumption and alternative technologiesGlobal Energy Consumption and alternative technologies
Global Energy Consumption and alternative technologies
 
power generation through solar power for PV module applications
power generation through solar power  for PV module applicationspower generation through solar power  for PV module applications
power generation through solar power for PV module applications
 
Residential distribution system harmonic[final]
Residential distribution system harmonic[final]Residential distribution system harmonic[final]
Residential distribution system harmonic[final]
 
Five Design Solutions - Portfolio Case Studies
Five Design Solutions - Portfolio Case StudiesFive Design Solutions - Portfolio Case Studies
Five Design Solutions - Portfolio Case Studies
 
Photovoltaic Project
Photovoltaic ProjectPhotovoltaic Project
Photovoltaic Project
 
Fuel cells project_maree
Fuel cells project_mareeFuel cells project_maree
Fuel cells project_maree
 
Interactive inverters
Interactive invertersInteractive inverters
Interactive inverters
 
51 b wittmer_latest_features_of_p_vsyst
51 b wittmer_latest_features_of_p_vsyst51 b wittmer_latest_features_of_p_vsyst
51 b wittmer_latest_features_of_p_vsyst
 
A MULTILEVEL MEDIUM VOLTAGE INVERTER FOR STEP UP TRANSFORMER LESS GRID CONNEC...
A MULTILEVEL MEDIUM VOLTAGE INVERTER FOR STEP UP TRANSFORMER LESS GRID CONNEC...A MULTILEVEL MEDIUM VOLTAGE INVERTER FOR STEP UP TRANSFORMER LESS GRID CONNEC...
A MULTILEVEL MEDIUM VOLTAGE INVERTER FOR STEP UP TRANSFORMER LESS GRID CONNEC...
 

Similaire à Photovoltaic Training - Session 2 - Construction and Start-Up

Photovoltaic Training Course - Module 2.1 - Civil works
Photovoltaic Training Course - Module 2.1 - Civil worksPhotovoltaic Training Course - Module 2.1 - Civil works
Photovoltaic Training Course - Module 2.1 - Civil worksLeonardo ENERGY
 
IRJET- Parametric Study of RC Deck Slab Bridge with Varying Thickness: Techni...
IRJET- Parametric Study of RC Deck Slab Bridge with Varying Thickness: Techni...IRJET- Parametric Study of RC Deck Slab Bridge with Varying Thickness: Techni...
IRJET- Parametric Study of RC Deck Slab Bridge with Varying Thickness: Techni...IRJET Journal
 
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...Egyptian Engineers Association
 
Parametric Comparison of Rectangular and Trapezoidal Box Girder Bridge Deck S...
Parametric Comparison of Rectangular and Trapezoidal Box Girder Bridge Deck S...Parametric Comparison of Rectangular and Trapezoidal Box Girder Bridge Deck S...
Parametric Comparison of Rectangular and Trapezoidal Box Girder Bridge Deck S...IRJET Journal
 
IRJET- A Review Article on Study Analysis of T-Beam Bridges by Finite Ele...
IRJET-  	  A Review Article on Study Analysis of T-Beam Bridges by Finite Ele...IRJET-  	  A Review Article on Study Analysis of T-Beam Bridges by Finite Ele...
IRJET- A Review Article on Study Analysis of T-Beam Bridges by Finite Ele...IRJET Journal
 
IRJET- Analysis of Prestressed Concrete Girder for Bridges
IRJET- Analysis of Prestressed Concrete Girder for BridgesIRJET- Analysis of Prestressed Concrete Girder for Bridges
IRJET- Analysis of Prestressed Concrete Girder for BridgesIRJET Journal
 
IRJET- Design and Analysis of Composite Top Frame of Hydraulic Valve Test...
IRJET-  	  Design and Analysis of Composite Top Frame of Hydraulic Valve Test...IRJET-  	  Design and Analysis of Composite Top Frame of Hydraulic Valve Test...
IRJET- Design and Analysis of Composite Top Frame of Hydraulic Valve Test...IRJET Journal
 
Analysing the role of Cable Anchor in Hydroelectric project A case study
Analysing the role of Cable Anchor in Hydroelectric project A case studyAnalysing the role of Cable Anchor in Hydroelectric project A case study
Analysing the role of Cable Anchor in Hydroelectric project A case studyIRJET Journal
 
Viapont® - Lightened asphalt concrete
Viapont® - Lightened asphalt concreteViapont® - Lightened asphalt concrete
Viapont® - Lightened asphalt concreteEurovia_Group
 
IRJET- A Review on Box Pushing Technique
IRJET- A Review on Box Pushing TechniqueIRJET- A Review on Box Pushing Technique
IRJET- A Review on Box Pushing TechniqueIRJET Journal
 
Jaipur metro rail corporation summer training report
Jaipur metro rail corporation summer training reportJaipur metro rail corporation summer training report
Jaipur metro rail corporation summer training reportRajendra Jhurawat
 
Construction using Precast technology
Construction using Precast technologyConstruction using Precast technology
Construction using Precast technologyShubham Arora
 
IRJET- Finite Element Analysis of Stempipe Used in Deepwater Pipeline Install...
IRJET- Finite Element Analysis of Stempipe Used in Deepwater Pipeline Install...IRJET- Finite Element Analysis of Stempipe Used in Deepwater Pipeline Install...
IRJET- Finite Element Analysis of Stempipe Used in Deepwater Pipeline Install...IRJET Journal
 
Km234 car hydraulic jack using internal car battery
Km234 car hydraulic jack using internal car batteryKm234 car hydraulic jack using internal car battery
Km234 car hydraulic jack using internal car battery1000kv technologies
 
IRJET- Structural Analysis and Design of Pump House
IRJET- Structural Analysis and Design of Pump HouseIRJET- Structural Analysis and Design of Pump House
IRJET- Structural Analysis and Design of Pump HouseIRJET Journal
 
ANALYTICAL STUDY OF STEEL ARCH BRIDGE
ANALYTICAL STUDY OF STEEL ARCH BRIDGEANALYTICAL STUDY OF STEEL ARCH BRIDGE
ANALYTICAL STUDY OF STEEL ARCH BRIDGEIRJET Journal
 
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...IRJET Journal
 
IMPROVING THE STRUCTURAL EFFICIENCY OF STEEL TRUSSES BY COMPARATIVE STUDY
IMPROVING THE STRUCTURAL EFFICIENCY OF STEEL TRUSSES BY COMPARATIVE STUDYIMPROVING THE STRUCTURAL EFFICIENCY OF STEEL TRUSSES BY COMPARATIVE STUDY
IMPROVING THE STRUCTURAL EFFICIENCY OF STEEL TRUSSES BY COMPARATIVE STUDYIRJET Journal
 
Etd 02-05 - concrete sleepers - design
Etd 02-05 - concrete sleepers - designEtd 02-05 - concrete sleepers - design
Etd 02-05 - concrete sleepers - designNECB
 

Similaire à Photovoltaic Training - Session 2 - Construction and Start-Up (20)

Photovoltaic Training Course - Module 2.1 - Civil works
Photovoltaic Training Course - Module 2.1 - Civil worksPhotovoltaic Training Course - Module 2.1 - Civil works
Photovoltaic Training Course - Module 2.1 - Civil works
 
IRJET- Parametric Study of RC Deck Slab Bridge with Varying Thickness: Techni...
IRJET- Parametric Study of RC Deck Slab Bridge with Varying Thickness: Techni...IRJET- Parametric Study of RC Deck Slab Bridge with Varying Thickness: Techni...
IRJET- Parametric Study of RC Deck Slab Bridge with Varying Thickness: Techni...
 
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
 
Parametric Comparison of Rectangular and Trapezoidal Box Girder Bridge Deck S...
Parametric Comparison of Rectangular and Trapezoidal Box Girder Bridge Deck S...Parametric Comparison of Rectangular and Trapezoidal Box Girder Bridge Deck S...
Parametric Comparison of Rectangular and Trapezoidal Box Girder Bridge Deck S...
 
IRJET- A Review Article on Study Analysis of T-Beam Bridges by Finite Ele...
IRJET-  	  A Review Article on Study Analysis of T-Beam Bridges by Finite Ele...IRJET-  	  A Review Article on Study Analysis of T-Beam Bridges by Finite Ele...
IRJET- A Review Article on Study Analysis of T-Beam Bridges by Finite Ele...
 
IRJET- Analysis of Prestressed Concrete Girder for Bridges
IRJET- Analysis of Prestressed Concrete Girder for BridgesIRJET- Analysis of Prestressed Concrete Girder for Bridges
IRJET- Analysis of Prestressed Concrete Girder for Bridges
 
IRJET- Design and Analysis of Composite Top Frame of Hydraulic Valve Test...
IRJET-  	  Design and Analysis of Composite Top Frame of Hydraulic Valve Test...IRJET-  	  Design and Analysis of Composite Top Frame of Hydraulic Valve Test...
IRJET- Design and Analysis of Composite Top Frame of Hydraulic Valve Test...
 
Analysing the role of Cable Anchor in Hydroelectric project A case study
Analysing the role of Cable Anchor in Hydroelectric project A case studyAnalysing the role of Cable Anchor in Hydroelectric project A case study
Analysing the role of Cable Anchor in Hydroelectric project A case study
 
Viapont® - Lightened asphalt concrete
Viapont® - Lightened asphalt concreteViapont® - Lightened asphalt concrete
Viapont® - Lightened asphalt concrete
 
Road Map
Road MapRoad Map
Road Map
 
IRJET- A Review on Box Pushing Technique
IRJET- A Review on Box Pushing TechniqueIRJET- A Review on Box Pushing Technique
IRJET- A Review on Box Pushing Technique
 
Jaipur metro rail corporation summer training report
Jaipur metro rail corporation summer training reportJaipur metro rail corporation summer training report
Jaipur metro rail corporation summer training report
 
Construction using Precast technology
Construction using Precast technologyConstruction using Precast technology
Construction using Precast technology
 
IRJET- Finite Element Analysis of Stempipe Used in Deepwater Pipeline Install...
IRJET- Finite Element Analysis of Stempipe Used in Deepwater Pipeline Install...IRJET- Finite Element Analysis of Stempipe Used in Deepwater Pipeline Install...
IRJET- Finite Element Analysis of Stempipe Used in Deepwater Pipeline Install...
 
Km234 car hydraulic jack using internal car battery
Km234 car hydraulic jack using internal car batteryKm234 car hydraulic jack using internal car battery
Km234 car hydraulic jack using internal car battery
 
IRJET- Structural Analysis and Design of Pump House
IRJET- Structural Analysis and Design of Pump HouseIRJET- Structural Analysis and Design of Pump House
IRJET- Structural Analysis and Design of Pump House
 
ANALYTICAL STUDY OF STEEL ARCH BRIDGE
ANALYTICAL STUDY OF STEEL ARCH BRIDGEANALYTICAL STUDY OF STEEL ARCH BRIDGE
ANALYTICAL STUDY OF STEEL ARCH BRIDGE
 
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
 
IMPROVING THE STRUCTURAL EFFICIENCY OF STEEL TRUSSES BY COMPARATIVE STUDY
IMPROVING THE STRUCTURAL EFFICIENCY OF STEEL TRUSSES BY COMPARATIVE STUDYIMPROVING THE STRUCTURAL EFFICIENCY OF STEEL TRUSSES BY COMPARATIVE STUDY
IMPROVING THE STRUCTURAL EFFICIENCY OF STEEL TRUSSES BY COMPARATIVE STUDY
 
Etd 02-05 - concrete sleepers - design
Etd 02-05 - concrete sleepers - designEtd 02-05 - concrete sleepers - design
Etd 02-05 - concrete sleepers - design
 

Plus de Leonardo ENERGY

A new generation of instruments and tools to monitor buildings performance
A new generation of instruments and tools to monitor buildings performanceA new generation of instruments and tools to monitor buildings performance
A new generation of instruments and tools to monitor buildings performanceLeonardo ENERGY
 
Addressing the Energy Efficiency First Principle in a National Energy and Cli...
Addressing the Energy Efficiency First Principle in a National Energy and Cli...Addressing the Energy Efficiency First Principle in a National Energy and Cli...
Addressing the Energy Efficiency First Principle in a National Energy and Cli...Leonardo ENERGY
 
Auctions for energy efficiency and the experience of renewables
 Auctions for energy efficiency and the experience of renewables Auctions for energy efficiency and the experience of renewables
Auctions for energy efficiency and the experience of renewablesLeonardo ENERGY
 
Energy efficiency first – retrofitting the building stock final
Energy efficiency first – retrofitting the building stock finalEnergy efficiency first – retrofitting the building stock final
Energy efficiency first – retrofitting the building stock finalLeonardo ENERGY
 
How auction design affects the financing of renewable energy projects
How auction design affects the financing of renewable energy projects How auction design affects the financing of renewable energy projects
How auction design affects the financing of renewable energy projects Leonardo ENERGY
 
Energy Efficiency Funds in Europe (updated)
Energy Efficiency Funds in Europe (updated)Energy Efficiency Funds in Europe (updated)
Energy Efficiency Funds in Europe (updated)Leonardo ENERGY
 
Energy Efficiency Funds in Europe
Energy Efficiency Funds in EuropeEnergy Efficiency Funds in Europe
Energy Efficiency Funds in EuropeLeonardo ENERGY
 
Five actions fit for 55: streamlining energy savings calculations
Five actions fit for 55: streamlining energy savings calculationsFive actions fit for 55: streamlining energy savings calculations
Five actions fit for 55: streamlining energy savings calculationsLeonardo ENERGY
 
Recent energy efficiency trends in the EU
Recent energy efficiency trends in the EURecent energy efficiency trends in the EU
Recent energy efficiency trends in the EULeonardo ENERGY
 
Energy and mobility poverty: Will the Social Climate Fund be enough to delive...
Energy and mobility poverty: Will the Social Climate Fund be enough to delive...Energy and mobility poverty: Will the Social Climate Fund be enough to delive...
Energy and mobility poverty: Will the Social Climate Fund be enough to delive...Leonardo ENERGY
 
Does the EU Emission Trading Scheme ETS Promote Energy Efficiency?
Does the EU Emission Trading Scheme ETS Promote Energy Efficiency?Does the EU Emission Trading Scheme ETS Promote Energy Efficiency?
Does the EU Emission Trading Scheme ETS Promote Energy Efficiency?Leonardo ENERGY
 
Energy efficiency, structural change and energy savings in the manufacturing ...
Energy efficiency, structural change and energy savings in the manufacturing ...Energy efficiency, structural change and energy savings in the manufacturing ...
Energy efficiency, structural change and energy savings in the manufacturing ...Leonardo ENERGY
 
Energy Sufficiency Indicators and Policies (Lea Gynther, Motiva)
Energy Sufficiency Indicators and Policies (Lea Gynther, Motiva)Energy Sufficiency Indicators and Policies (Lea Gynther, Motiva)
Energy Sufficiency Indicators and Policies (Lea Gynther, Motiva)Leonardo ENERGY
 
The Super-efficient Equipment and Appliance Deployment (SEAD) Initiative Prod...
The Super-efficient Equipment and Appliance Deployment (SEAD) Initiative Prod...The Super-efficient Equipment and Appliance Deployment (SEAD) Initiative Prod...
The Super-efficient Equipment and Appliance Deployment (SEAD) Initiative Prod...Leonardo ENERGY
 
Modelling and optimisation of electric motors with hairpin windings
Modelling and optimisation of electric motors with hairpin windingsModelling and optimisation of electric motors with hairpin windings
Modelling and optimisation of electric motors with hairpin windingsLeonardo ENERGY
 
Casting zero porosity rotors
Casting zero porosity rotorsCasting zero porosity rotors
Casting zero porosity rotorsLeonardo ENERGY
 
Direct coil cooling through hollow wire
Direct coil cooling through hollow wireDirect coil cooling through hollow wire
Direct coil cooling through hollow wireLeonardo ENERGY
 
Motor renovation - Potential savings and views from various EU Member States
Motor renovation - Potential savings and views from various EU Member StatesMotor renovation - Potential savings and views from various EU Member States
Motor renovation - Potential savings and views from various EU Member StatesLeonardo ENERGY
 
The need for an updated European Motor Study - key findings from the 2021 US...
The need for  an updated European Motor Study - key findings from the 2021 US...The need for  an updated European Motor Study - key findings from the 2021 US...
The need for an updated European Motor Study - key findings from the 2021 US...Leonardo ENERGY
 
Efficient motor systems for a Net Zero world, by Conrad U. Brunner - Impact E...
Efficient motor systems for a Net Zero world, by Conrad U. Brunner - Impact E...Efficient motor systems for a Net Zero world, by Conrad U. Brunner - Impact E...
Efficient motor systems for a Net Zero world, by Conrad U. Brunner - Impact E...Leonardo ENERGY
 

Plus de Leonardo ENERGY (20)

A new generation of instruments and tools to monitor buildings performance
A new generation of instruments and tools to monitor buildings performanceA new generation of instruments and tools to monitor buildings performance
A new generation of instruments and tools to monitor buildings performance
 
Addressing the Energy Efficiency First Principle in a National Energy and Cli...
Addressing the Energy Efficiency First Principle in a National Energy and Cli...Addressing the Energy Efficiency First Principle in a National Energy and Cli...
Addressing the Energy Efficiency First Principle in a National Energy and Cli...
 
Auctions for energy efficiency and the experience of renewables
 Auctions for energy efficiency and the experience of renewables Auctions for energy efficiency and the experience of renewables
Auctions for energy efficiency and the experience of renewables
 
Energy efficiency first – retrofitting the building stock final
Energy efficiency first – retrofitting the building stock finalEnergy efficiency first – retrofitting the building stock final
Energy efficiency first – retrofitting the building stock final
 
How auction design affects the financing of renewable energy projects
How auction design affects the financing of renewable energy projects How auction design affects the financing of renewable energy projects
How auction design affects the financing of renewable energy projects
 
Energy Efficiency Funds in Europe (updated)
Energy Efficiency Funds in Europe (updated)Energy Efficiency Funds in Europe (updated)
Energy Efficiency Funds in Europe (updated)
 
Energy Efficiency Funds in Europe
Energy Efficiency Funds in EuropeEnergy Efficiency Funds in Europe
Energy Efficiency Funds in Europe
 
Five actions fit for 55: streamlining energy savings calculations
Five actions fit for 55: streamlining energy savings calculationsFive actions fit for 55: streamlining energy savings calculations
Five actions fit for 55: streamlining energy savings calculations
 
Recent energy efficiency trends in the EU
Recent energy efficiency trends in the EURecent energy efficiency trends in the EU
Recent energy efficiency trends in the EU
 
Energy and mobility poverty: Will the Social Climate Fund be enough to delive...
Energy and mobility poverty: Will the Social Climate Fund be enough to delive...Energy and mobility poverty: Will the Social Climate Fund be enough to delive...
Energy and mobility poverty: Will the Social Climate Fund be enough to delive...
 
Does the EU Emission Trading Scheme ETS Promote Energy Efficiency?
Does the EU Emission Trading Scheme ETS Promote Energy Efficiency?Does the EU Emission Trading Scheme ETS Promote Energy Efficiency?
Does the EU Emission Trading Scheme ETS Promote Energy Efficiency?
 
Energy efficiency, structural change and energy savings in the manufacturing ...
Energy efficiency, structural change and energy savings in the manufacturing ...Energy efficiency, structural change and energy savings in the manufacturing ...
Energy efficiency, structural change and energy savings in the manufacturing ...
 
Energy Sufficiency Indicators and Policies (Lea Gynther, Motiva)
Energy Sufficiency Indicators and Policies (Lea Gynther, Motiva)Energy Sufficiency Indicators and Policies (Lea Gynther, Motiva)
Energy Sufficiency Indicators and Policies (Lea Gynther, Motiva)
 
The Super-efficient Equipment and Appliance Deployment (SEAD) Initiative Prod...
The Super-efficient Equipment and Appliance Deployment (SEAD) Initiative Prod...The Super-efficient Equipment and Appliance Deployment (SEAD) Initiative Prod...
The Super-efficient Equipment and Appliance Deployment (SEAD) Initiative Prod...
 
Modelling and optimisation of electric motors with hairpin windings
Modelling and optimisation of electric motors with hairpin windingsModelling and optimisation of electric motors with hairpin windings
Modelling and optimisation of electric motors with hairpin windings
 
Casting zero porosity rotors
Casting zero porosity rotorsCasting zero porosity rotors
Casting zero porosity rotors
 
Direct coil cooling through hollow wire
Direct coil cooling through hollow wireDirect coil cooling through hollow wire
Direct coil cooling through hollow wire
 
Motor renovation - Potential savings and views from various EU Member States
Motor renovation - Potential savings and views from various EU Member StatesMotor renovation - Potential savings and views from various EU Member States
Motor renovation - Potential savings and views from various EU Member States
 
The need for an updated European Motor Study - key findings from the 2021 US...
The need for  an updated European Motor Study - key findings from the 2021 US...The need for  an updated European Motor Study - key findings from the 2021 US...
The need for an updated European Motor Study - key findings from the 2021 US...
 
Efficient motor systems for a Net Zero world, by Conrad U. Brunner - Impact E...
Efficient motor systems for a Net Zero world, by Conrad U. Brunner - Impact E...Efficient motor systems for a Net Zero world, by Conrad U. Brunner - Impact E...
Efficient motor systems for a Net Zero world, by Conrad U. Brunner - Impact E...
 

Dernier

"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr BaganFwdays
 
Story boards and shot lists for my a level piece
Story boards and shot lists for my a level pieceStory boards and shot lists for my a level piece
Story boards and shot lists for my a level piececharlottematthew16
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsPixlogix Infotech
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLScyllaDB
 
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity PlanDatabarracks
 
What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024Stephanie Beckett
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxhariprasad279825
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationSlibray Presentation
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .Alan Dix
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek SchlawackFwdays
 
Search Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfSearch Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfRankYa
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyAlfredo García Lavilla
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii SoldatenkoFwdays
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 3652toLead Limited
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfPrecisely
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupFlorian Wilhelm
 
Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clashcharlottematthew16
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxLoriGlavin3
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfAlex Barbosa Coqueiro
 

Dernier (20)

"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan
 
Story boards and shot lists for my a level piece
Story boards and shot lists for my a level pieceStory boards and shot lists for my a level piece
Story boards and shot lists for my a level piece
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and Cons
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQL
 
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity Plan
 
What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptx
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck Presentation
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
 
Search Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfSearch Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdf
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easy
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project Setup
 
Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clash
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdf
 

Photovoltaic Training - Session 2 - Construction and Start-Up

  • 2. PHOTOVOLTAIC SYSTEM Design, Execution, Operation & Maintenance EXECUTION AND COMMISSIONING Javier Relancio. Generalia Group.  16/09/2010 www.generalia.es 2 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 3. INDEX Civil works. Infrastructure preparation Mechanical works Electrical works Environmental issues Quality. Critical issues during execution Safety & Labor risks Commissioning tests. Key points 3 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 4. INDEX Civil works. Infrastructure preparation Mechanical works Electrical works Environmental issues Quality. Critical issues during execution Safety & Labor risks Commissioning tests. Key points 4 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 5. Civil Works: Infrastructure preparation Rooftop projects We may find little civil works, but it will be reduced to the trench opening for the connection of the inverters and the meters Ground projects Civil works are very important A good definition for the civil works could mean an important saving in the project. Main civil works are: Terrain leveling Accesses and inside roads/paths Trench opening (AC & DC) 5 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 6. Terrain leveling It might be avoided as much as possible in order to reduce the environmental impact Only required works should be done: Selecting a flat terrain may avoid its leveling Selecting a structure type which can be fixed to the terrain by a “ground anchor”, instead of a concrete base Depending on the solution design, the choice between fixed or suntracking project can be determinant Source: QHOELET 6 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 7. Internal roads & paths It is recommended to use already existing paths We must take into account that the roads or paths have to allow the circulation of trucks. Truck turning radius must be considered: Length Minimum radius for Minimum radius Vehicle Type Nomenclature Height Width Length between external front- for internal back- axis wheel wheel Light vehicle VL 1,30 2,10 5,80 3,40 7,30 4,20 2-Axis Omnibus B2 4,10 2,60 9,10 6,10 12,80 8,50 3-Axis Omnibus B3 4,10 2,60 12,10 7,60 12,80 7,40 2-Axis simple truck C2 4,10 2,60 9,10 6,10 12,80 8,50 3-Axis simple truck C3 / C4 4,10 2,60 12,20 7.6 12,80 7,40 4,00 / Trailer (Semi) T2S1/ 2 / 3 4,10 * 2,60 15,20 12,20 5,80 7,00 4,90 / Trailer (Semi) T3S1 / 2 / 3 4,10 2,60 16,70 13,70 5,90 7,90 3,80 / 2 Axis trailer + 1 Double C2 - R2 / 3 4,10 2,60 19,90 6,10 / 13,70 6,80 6,40 3,80 / C3 - R2 / 3 / 3 Axis trailer + 1 Double 4,10 2,60 19,90 6,10 13,70 6,80 4 /6,40 7 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 8. Internal roads & paths Once the installation has been commissioned, internal paths & roads will not be used too much, so a 25 cm depth path of a mixture 75% gravel, 25 % river sand, may be enough. Minimal turning radius for B3/C3 vehicles Accesses and roads/paths detail 75% gravel, 25 % river sand Natural terrain 8 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 9. Trenches In a PV project, all the cable must be buried underground Each 40 meters or each direction change, a manhole will be placed to ease the cable laying The project design might try to use the same section for all the trenches 9 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 10. Trenches The trenches will have: A river sand base Space for the pipes Backfill of sifted soil and soft sand Cable caution tape In the case it is a vehicle passing area, it will have a concrete layer at the top 10 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 11. INDEX Civil works. Infrastructure preparation Mechanical works Electrical works Environmental issues Quality. Critical issues during execution Safety & Labor risks Commissioning tests. Key points 11 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 12. Mechanical works Structure type Weight Anticorrosion protection Mechanical   performance Galvanized steel Resistant rooftops 8 years (non salty atmosphere) Good Hot galvanized steel Resistant rooftops More than 25 years Good Anodizing Aluminum Light rooftops More than 20 years Medium No structure Light rooftops ‐ ‐ For fixed installations, the structure can be set parallel to the surface where it is to be installed (flat), or with the optimum tilt for each latitude (Tilted) Flat Tilted No wind action Important wind action Worse cooling Best natural cooling Lower cost (Both for structure &  Higher cost (Both for structure &  mounting) mounting) Photo: Krannich 12 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 13. Mechanical works The structure anchor for a ground installation may have the following possibilities: Ground anchor These screws have an average length between 1 -1,6 meters Easy to be dismounted They can be adapted to the terrain orography Source: Conectavol They can’t be used in a rocky terrain Concrete basement Above or under the ground It requires a flat surface Easy to be dismounted (if it is above the ground) 13 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 14. Roof anchorage Metal roof anchors: We have two options: Direct to purlins anchorage Specially designed anchors to be fixed directly to the roof sheathing It is recommended to use the direct to purlin anchorage. If tilted structure is being used, other choice could be risky. Tile roof anchorage: A typical solution is using a “U” shaped piece which is anchored directly to the roof, avoiding to drill the tile It is necessary to move the tiles (danger of leaks) With a special piece we can go through the tile Danger to break the tile Source: SoportesSolares 14 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 15. PV Roofs Roof state: The following aspects are to be evaluated: Safety We have to verify if the roof is safe. If not, we may install “lifeline”, “skylight network” Roof type Asbestos (Uralita) roofs are the most difficult ones, as it may be cracked by stepping on it, producing leaks, or it could even be broken, being really risky for the installers. In this case, it is recommended to change the whole roof to metal roof. Sealing It is important to use the most indicated sealing to avoid leaking. This sealers must have great elasticity and good mechanical resistance. They may be complemented by EPDM* bands 15 * a type of synthetic rubber (ethylene propylene diene Monomer)
  • 16. PV Roofs Loads on the roof Material weight (average weight by square meter) Element Weight Structure 2KG Crystalline panels 15KG Thin film glass‐glass panel 22KG Thin film laminated panel 6KG Wind effect During the design, both panel height and exposed surface must be considered Extra loads during the execution: such us tools, workers, materials… Accesses: The accesses will be distributed all along the roof surface, guaranteeing the worker safety and allowing them to carry up small materials and tools 16 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 17. INDEX Civil works. Infrastructure preparation Mechanical works Electrical works Environmental issues Quality. Critical issues during execution Safety & Labor risks Commissioning tests. Key points 17 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 18. Electrical works Cable for the panel strings • We usually use the cable included by the panel manufacturers. Important to confirm with the manufacturer that this cable is included • This cable are composed of copper: 4mm; 0,6/1kV • This cables usually are ended in “fast connectors”: Multicontact, Tyco, etc Source: Eastech Solar 18 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 19. Electrical works Roof installations Cable canalization might be done under hot galvanized cable tray or tubular conduit Cable tray canalization simplifies mounting works, and eases the maintenance tasks. Indoor, plastic(or metallic) cable tray might be used, as well as halogen-free cable 19 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 20. Electrical works Ground installations Electrical works will be done in the trenches, so the cable must be designed for this use. It is recommended to use anti-mice cable, inside a tubular conduit. Cable trenches might be really long, so the trench design, number of cables by pipeline, extra space by pipeline, manholes, etc.. could be decisive to optimize the electrical works duration The cable should be previously marked in order to avoid connecting issues It is important to avoid corners or any element which may cause any damage in the cable isolation. 20 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 21. Electrical cabinets Depending on its location, a different IP may be required • For outdoor installations, at least IP 65 will be required • For indoor installations, IP 21 could be enough (except for special conditions: water, powder…) It is really important to pay attention at the element connections, and the identification of each cable & component in the project documentation The thermal study of the cabinet is also important, verifying the minimal required volume for the heat dissipation, and raising additional solutions as the incorporation of a heat resistance in case of outdoor installations in very cold zones 21
  • 22. Earthing system The following elements must be earth connected PV panel frameworks Structure Metal cable tray Metal elements in electrical cabinets PV inverters For small facilities, the earthing system would be quite simple: 2 – 3 pegs, depending on the soil resistivity For bigger facilities, a cable grid is usually implemented, using the trench already opened for the energy cables, placing an uncovered copper cable below the energy cables. EARTH CABLE The section of this cable is to be calculated during the design 22 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 23. INDEX Civil works. Infrastructure preparation Mechanical works Electrical works Environmental issues Quality. Critical issues during execution Safety & Labor risks Commissioning tests. Key points 23 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 24. Our solar facility and the environment Nowadays we can find A change in the social sensibility for the environmental impacts. The society begins to have a greater conscience and a harder implication. This will be the real engine for the new environmental initiatives to be managed in a suitable way. The ISO Certification 14001, allows us to take and to show the others, our environmental commitment. For all this, the solar power companies should demonstrate the coherence with their ecological message, developing a good environmental policy 24 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 25. Environmental aspects & impacts Definitions (ISO 14001): Environmental aspect: Any element of the activities, products or services that is causing some type of impact on the environment can be considered as an environmental aspect. Environmental impact: Any change in the environment, either adverse or beneficial, resulting from the activities, products and services of an Organization. Residue: Any substance or object from which his holder detaches or has the obligation to become detached following the European rules & standards 25 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 26. Environmental aspects & impacts We must take into account the environmental management of our solar facility a. To know the in force legislation b. To know the environmental aspects that concern our business c. To evaluate the impact that has on the environment d. To propose indicators that give us a tangible evidence about the measured aspects, and their impacts, and to use them to develop new preventive and corrective measures e. To have an emergency plan derived from the knowledge of the different environmental aspects f. To do the suitable management of the generated residues The environmental management becomes necessary in the execution, as well as the operation of the solar plant, therefore, an individual analysis of every project will be required 26 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 27. Example: Environmental management during the project execution 1. List of aspects and impacts Activity Aspect N/E Impact Atmospheric contaminations Electric energy consumption N Visual Impacts PV installations (and  Fuel consumption N Atmospheric pollution Suntrackers, in case  Powder generation N Atmospheric pollution of being used) Residues generation N Space in the dumpsite Atmospheric pollution Fire E Impact on the fauna & flora. N: Normal; E: Extraordinary 2. Emergency classification Significant Aspect P S A YES=Y; NO=N Fire 2 4 8 Y P: Probability; S: Seriousness; A: Assessment 27 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 28. Example: Environmental management during the project execution 3. Aspect classification (Normal aspects) SIGNIFICANT ASPECTS F S C A YES/ NO Electrical energy consumption 5 2 2 20 YES Dangerous residues generation 3 2 2 12 NO Urban residues generation 4 1 2 12 NO Noise generation 3 1 1 6 NO Fuel consumption 3 2 2 12 NO Powder generation 3 1 1 6 NO Paper consumption 5 1 2 15 YES Packages 4 1 2 12 NO F: Frequency; S: Seriousness; C: Consequence; A: Assessment 28 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 29. Example: Environmental management during the project execution 4. Emergency plan EVENT/ EMERGENCY: FIRE Preventive measures Adaptation to the electrical and construction regulations. Fire‐extinguishers. • The work manager is the person in charge of the extinction of fire.  • In case of non‐controllable emergency, the work manager will take charge of  warning the external emergency services.  Actuation plan • The work responsible is the person in charge of giving the alarm and  controlling the evacuation of the whole staff. He must check that the  evacuation has been completed Practice Fire The response time will be measured for the following aspects: • The fire warning. Practice description    • Staff evacuation. • The checking that the evacuation has been completed. Frequency Yearly 29 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 30. Example: Environmental management during the project execution 5. Residue management general process: In every moment, we must: To develop a study of the residues that are being produced, in the execution and the operation of the solar power facility; To quantify the quantity of each one, and to do a management of the residue according to its type. Urban residues Dangerous residues Paper Toner with metallic components Plastic Batteries Tins & Cans Fluorescents Toner without metallic components Oils (Vehicles / Motors) 30 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 31. INDEX Civil works. Infrastructure preparation Mechanical works Electrical works Environmental issues Quality. Critical issues during execution Safety & Labor risks Commissioning tests. Key points 31 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 32. Quality: Critical aspects The critical aspects referred to quality in the phase of execution are: Materials Checking that we have received the goods that have been requested Inspection of the goods at their arrival to check possible material faults/defects This process will be developed for a certain number of samples previously defined by the quality department The checking of the electrical and mechanical parameters of the material, to avoid early breakdowns Work execution Correct planning of the work: in order to avoid delays, dead times of the workers, managing the activities in “critical way” Updated documentation for the works: It is important to check that the workers have the latest edition of the information 32 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 33. Quality: Critical aspects Work Manager 1.Checking that the ordered material fits with the projects real requirements 2.Checking that the real project conditions matched with the project design 3.Managing the material administration and reception Material Administration Material Reception 1.Checking that the items indicated in 1.Checking that the items that have the delivery notes corresponds with arrived correspond to the items of the ordered ones the delivery note 2. Checking any lacking item in the 2.Visual checking order and claiming for it 3.Checking of electrical and 3. Checking the payments mechanical characteristics 33 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 34. Quality: Critical aspects Work Manager 1. Fulfillment of the planning deadlines 2. Checking the documentation of the work orders 3. Checking the quality in the intermediate milestones of the project Worker 4. Checking the management of the residues during and at the end of the project 1. Work execution according to the 5. Final checking of the work work order 2. To notify incidents in the accomplishment of the works 3. Accomplishment of the checking indicated in the work order 34 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 35. Panel inspections Samples selection VISUAL ELECTRICAL THERMAL Packages OF Panel arrays Panels Panels The electrical • Frame defects characteristics differ from Cell defects • Glass defects the technical specs, used Hot spots DETECTION • Connection box defects for the design and they Cell bubbles OF • Cable & connector defects are out of the required range Although it might be true that the panels are the most expensive element in the installation, a similar table should be done for the rest of the elements 35 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 36. Thermography The Thermography is a simple method to detect defaults in the solar panels The checking of the installation is developed in a rapid and visual form It saves time, as it identifies directly the problematic panel without having to do complex checks in the different strings 36 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 37. INDEX Civil works. Infrastructure preparation Mechanical works Electrical works Environmental issues Quality. Critical issues during execution Safety & Labor risks Commissioning tests. Key points 37 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 38. Labor risks evaluation plan 1. Introduction Within every company it is obligatory to have a labor risk evaluation plan. Even in the case that we subcontract other companies, it is necessary to check that each company has its labor risk evaluation plan adapted to our activity. Knowledge of the particularities  of the company activities Risk analysis for each activity Actions depending on the risks 38 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 39. Labor risks evaluation plan 2. Activitie characteristics PV on the roof PV on the ground (Fix) PV on the ground (Suntracking) Small facilities: From 2‐3 KW to 100KW  Larger facilities: >100 KW Larger facilities: >100 KW (Or even more) Working at great heights Working on the ground Working on the ground Different types of roofs Earth movements Earth movements Different tilts of roofs Trench openings Trench openings Sharing the work with the industry  Larger number of workers Larger number of workers where our plant is located Electrical cabling and inverter  Usage of cranes to fix the panel structure  Possibility of using cranes commissioning to the Suntrackers Electrical cabling and inverter  Electrical cabling and inverter  commissioning commissioning 39 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 40. Labor risks evaluation plan 3. Activity risks PV on the roof PV on the ground (Fix) PV on the ground (Suntracking) Falls from the roof Falls into trenches Falls into trenches Accidents due to material falling To be run over by working vehicles To be run over by working vehicles Risk from the industry where the  Electrocution risk Electrocution risk plant is located Electrocution risk Accidents due to material falling Accidents due to material falling Accident due to collision with the suntracker 40 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 41. Labor risks evaluation plan 4. Activitie summary To analyze the photovoltaic activities, to know and to evaluate the risks of every job inside every activity. To train the staff on the risks depending on their job or workstation To distribute the equipments of individual protection adapted to every workstation To designate a person in charge of checking the correct execution of the prevention plans To develop an emergency and evacuation plan 41 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 42. INDEX Civil works. Infrastructure preparation Mechanical works Electrical works Environmental issues Quality. Critical issues during execution Safety & Labor risks Commissioning tests. Key points 42 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 43. Project commissioning Technical documentation Project design Plans Operation & Engineering Maintenance Technical datasheets Equipment manuals Preventive maintenance plan Suntracker manual Corrective maintenance plan Commissioning Monitoring system manual Execution Commissioning checklist Plant production checking Project modification Generator production checking Done inspections Inverter production checking Element identification 43 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 44. Plant production checking As the aim that we pretend is to maximize the productive capacity of the photovoltaic solar plant, we need to check, from time to time, a test of the plant productive capacity (i.e. every three years) If the plant is very large, it could be worthy to do a test every year The plant performance can be measured up by the instantaneous response to: Cell temperature (Depending on the outdoor temperature, wind, irradiance) Irradiance We will evaluate: The power, in alternating current at the plant output (meter) Global and direct irradiance in a calibrated cell (from a similar technology to the one used for the generator and parallel with it) Cell temperature: sticking a thermal sensor to the calibrated cell 44 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 45. Plant production checking Outdoor temperature For the capture of the indicated (Optional) variables we will need to have: Irradiance A meteorological station where the information of Temperature and irradiance will be registered Source: Geonica A meter (with integrated communications) from which AC Power (at the we can read the output meter output) power TEMP. PANEL FV 45 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 46. Plant production checking In the case of using suntrackers, we have to verify the equipment performance every hour by testing the shadow projected by a rod perpendicular to the plane of the generator Minimal measure period: 5 consecutive days dawn - dusk Condition: The minimal period of irradiance over 600W/m2 must be at least 12 hours Periodicity of the measure of output power - irradiance-temperature: 10 mins The obtained measures of output power-irradiance-temperature are compared to the expected ones and the deviations between both are analyzed If the legislation allows it in the future, the modernization or extension of the plant for repowering might be recommended 46 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 47. Testing of PV Generator electrical characteristics Objective: To determine the electrical characteristics under the “Standard metering conditions”, defined by: • Irradiance: G = 1000 W/m2 • Cell temperature: CT=25ºC. We obtain the C-V curve from the generator and the I one from a standard module, and both are compared under the conditions above-mentioned These tests have to be done two hours before and after V the local midday and the global irradiance has to be a over 700W/m2 Nowadays we can find specific equipments to obtain the C-V curve of a PV generator and move it into standard conditions 47 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 48. Testing of the inverter electrical characteristics Is the second most important element in a PV facility Objective: To determine the characteristics which define the energetic performance of an inverter: • Efficiency • Maximum Power Point Tracking The European efficiency of the inverter, has to be verified with the measures commented in the previous slides, attaching the power measure and the voltage in the DC side Furthermore, it must be verified the inverter capacity to track the Maximum Power Point (MPP) Source: SMA 48 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
  • 49. End of Session 2 Thank you for attending http://www.leonardo-energy.org/training-pv-systems-design- construction-operation-and-maintenance 49