Training on Financial
and Economic Project
Evaluation
(cost benefit analysis)
May 15th 2013
Learning objectives
1. Understand the concept, utility and limits of
financial/private and economic/social project
evaluation (cost benefit)
2. Know how to interpret the results of financial/economic
evaluations (cost benefit)
3. Understand the opportunities of financial/economic
evaluation being part of the PCM and its implication for
results based project management
4. Identify development projects for which the concept
can be applied, and for which kind of projects other
methods are more adequate
Group Work
Social Entrepreneur selling a technology like micro
irrigation to poor farmers
1. What do you need to know to make this business a
success and not a bankruptcy?
Objective of CBA applied to project
evaluation
Make better informed decisions on whether to
invest or not
Relying on the necessary information to
quantify variables which are related to
• investment,
• operational costs and
• incomes
Market / feasibility
Study
Technical Study
Organisational study Financial Evaluation
Important studies needed for project
formulation and evaluation
Economic Evaluation
The different studies provide information for
the project evaluation - business approach -
Benefits / Costs Return on investment
Market Study
Objective: Determine the
existence of the unmet
demand and quantify it
Technical Study
Objective: Verify the
technical feasibility
Organisational Study
Objective: define the
optimal organisational
structure
 Analysis of demand
 Analysis of supply
 Price or fee
 Marketing strategy
 Production capacity
 Technology
 Infrastructure
 Human resources
 Information system
 Legal aspects
What is cost-benefit analysis (CBA)?
The aim of the cost benefit analysis is to assess the
profitability of investments over time, by comparing the
costs of a project with its benefits
COSTS =  investment costs
 running costs or operational costs
 financial costs
 support costs
Only real costs are considered in the CBA, i.e. costs that correspond to flows of
cash, and the costs are computed at the time when they occur during project life.
BENEFITS:  increased production, project sales
 reduced costs
 social benefits,  improved  livelihood,  reduced  poverty,…
Quantification is required!
CBA requires to quantify all the costs and benefits, which is sometimes rather
challenging. Where quantification is not possible, benefits and costs should be
included in the discussion and interpretation of the models, or another method
should be selected (e.g. Cost effectiveness)
Whose costs should be considered ?
Beyond financial evaluation: all costs need to be taken into account
• SDC project costs
• Other counterpart costs
• Costs beneficiaries bear (incl. in-kind contributions)
Note: the CBA compares additional costs and additional benefits
for the users / for the enterprise, etc. i.e. the costs and benefits WITH
or WITHOUT the project
Example of a CBA
Note: year 0 is only virtual, so that the project can start in year 1 it is necessary to have the
funds available on the day before the project starts
Year 0 Year 1 Year 2 Year 3 Year 4 Year 5
COSTS -100 -12 -13 -11 -13 -12
Investment -100
Operations -10 -10 -10 -10 -10
Other costs -2 -3 -1 -3 -2
BENEFITS 0 12 20 50 50 100
Sales 12 20 50 50 50
Residual
value
50
CASH FLOW -100 0 7 39 37 88
DISCOUNTING
Principle:
1 dollar today is worth more than 1 dollar tomorrow
Question: what is the value today of the money you will earn next year,
or in 2, 3 or 10 years from now?
Example: on your savings account you have 5’000  CHF  
earning 2% per year
How much will you have on your account after 5 years? (assuming that
you have no transaction costs and that the interest rate remains
unchanged)
Interest 1st year = 5’000  * 2% = 5’100  CHF
Interest 2nd year = 5’100  *  2%  = 5’202  CHF  
Etc…  
Compound interest Discounting
capital (P) = today 5'000 capital (P) = today 4’528
interest (r) 2% interest (r) 2%
time (years) (n) 5 time (years) (n) 5
accumulated capital (A) 5’520 accumulated capital (A) 5’000
A = P(1 + r)n P= A(1+r)-n
Net Present Value and Internal Rate of Return
Net present value (NPV) = value today of the cash flow of
each year of the analysed period
In Excel, use +NPV(10%;year1...year5)+year 0 (here = 15.00)
Internal Rate of Return (IRR) = rate that the project generates
over time (this rate can be compared with interest rate of banks
or alternative use of the capital
In Excel, use +IRR(year0 ... Year5) (here = 13.81%)
Year 0 Year 1 Year 2 Year 3 Year 4 Year 5
COSTS -100 -12 -13 -11 -13 -12
BENEFITS 0 12 20 50 50 100
CASH FLOW -100 0 7 39 37 88
Evaluation criteria
Net present value (NPV)
• Expresses the difference
between total
expenditure and income
of the project (cash flow)
but discounted to the
value of money at
project start.
• Shows the surplus after
having received the
demanded profitability
(discount factor) and
having retrieved the total
investment
• The convention is to
accept the project if the
NPV is bigger or equal
to 0.
Internal rate of return
(IRR))
• Shows the maximal
profitability that can be
expected of the
investment.
• The project is accepted
if the IRR is bigger or
equal to the discount
factor.
• IRR only tells us if the
project is better than the
alternative use of funds
(IRR does not allow to
compare different
project)
Benefit – Cost Relation
(BC)
• Compares the present
value of the benefits with
the present value of the
costs including the
investment, shown as a
ratio
• The project is accepted
if the ratio is bigger or
equal to zero.one
EXTERNALITIES
Externalities are “side  effects”  of projects or enterprises
which are not included in the costs and benefits; they can be
positive (external benefits) or negative (externals costs). In the
case of negative externalities, the costs are usually paid by the
society
Examples of external benefits
 Access to electricity for villagers after a factory was installed in
the neighbourhood
 After a village installed electricity supply, an enterprise decides
to settle in the neighbourhood ( job creation)
Examples of external costs
 Pollution, noise, traffic, etc.
Economic analysis
SHADOW PRICES / economic prices
(also called opportunity costs)
Market prices do not always reflect the real value of products. This
is the case for instance when subsidies or taxes are paid / charged.
Example:
fertiliser  price  on  the  market  =  100’000  VND
subsidy from the Government = 25%
real  value  of  fertiliser  =  100’000  VND  +  25%  =  125’000  VND
In this case, farmers get fertilisers cheaper than the real value, the
financial value is lower than the economic value
FINANCIAL VS ECONOMIC ANALYSIS
Financial Economic
CBA shows
the interests
of ...
Private enterprise: is
the project profitable
for the investor?
Society: is the project
beneficial to the society
(whole economy)
Prices
considered
Costs and benefits at
market prices
Shadow prices
(opportunity prices), i.e.
prices are corrected from
subsidies, taxes, etc.
Externalities Not considered Considered
Excel data
Reserve Slide: Structure of the flow of
funds statement
+ Income (tax relevant)
- Expenditure (tax relevant)
- Expenditure not implying cash flows, but tax relevant
(depreciation and amortization)
= Profit before taxes
- Taxes
= Profit after taxes
+ Adjustment for expenditures not implying cash flows
(depreciation and amortization)
- Expenditure not relevant for taxes (investments)
+ Benefits not relevant for taxes (residual value)
= Cash Flow
Consideration concerning the cash flow
Time horizon of the evaluation
• Is highly dependent on the characteristics of each project.
• If the project life time can be foreseen, and is not long term, the most
convenient is to construct the flow of funds for this number of years.
• If the enterprise (or structure) the project wants to create will stay in
the market (no exit strategy), the general convention is to project the
flow of funds for 10 years.
• The expected benefits beyond the 10th year are then reflected in the
residual value.
Risk within projects
When preparing and evaluating projects one has to rely
on assumptions, e.g. with respect to
– population growth,
– demand,
– supply,
– technologies,
– availability of inputs,
– estimation of costs,
– estimation of benefits,
– etc., etc., etc.
…  where  there  are  assumption  there  are  
risks
Mainly serves for :
a. Determine critical variables and their ranges of
variation.
b. Study and determine the effects of the critical
variables on the results of the project.
c. Evaluate the project with different external
conditions.
Sensitivity analysis
Methods for sensitivity analysis
Select the critical variables :
Consider the variables that are difficult to predict
Select the variable with the biggest impact on the NPV
… or those with the highest uncertainty.
Move one variable at a time (Ceteris Paribus)
Construct different scenarios for a group of the above
variables and re-calculate the project criteria.
Possible Alternative: Cost Effectiveness
Analysis
• Applied when benefits cannot be quantified (with
reasonable effort)
• Instrument for comparing different approaches to reach a
certain benefit
• Choose the approach that creates the biggest and lasting
benefit for the beneficiaries
• Used to justify an approach for funding (as compared to
alternatives)
Cost Effectiveness Analysis
Impacts that the project
is supposed to reach
Distinguish major impact
and side impacts (or
secondary impacts)
Starting point =
project design
COSTS =
Direct costs
Investment costs,
Support costs
(coaching,
backstopping, etc.)
Maintenance costs
Costs for SDC and
costs for partner
organisations
Indirect costs may also
be considered
BENEFITS: are the
benefits really the same,
how sustainable are the
benefits, etc.
Important to remember
1. You need solid numbers
a) to construct financial and economic
evaluations, evaluate results before, after,
during
b) to formulate your project: market studies etc.
2. Financial (private) evaluation shows whether
private sector part is viable or what the project
needs to do to make it viable
Important to remember
3. Financial and economic evaluation are key
tools to improve result management:
 Identify benefits
 Quantify benefits
 Establish causality
… even if no precise NPV can be calculated.
Important to remember
4. Economic/social evaluation provides valuable,
additional decision criteria (not the only ones!)
a) to approve or reject projects
b) to identify more objectively and quantified
what works and can be scaled up
1. Reserve Slide: Domains of application of
CBA in development cooperation
• CBA can be applied in a wide range of projects, key condition is
the quantification of costs and benefits
• CBA can be applied to entire projects or to selected project
components
Difficulty to apply
Low Medium High
Project
dealing with
Income generation,
livelihood, economic
development
Health, education,
nature conservation,
biodiversity, etc.
Governance, policy
dialogue, institutional
development
Examples of
CBAs (done
or in
preparation)
Vietnam, Mongolia,
South Africa, Latin
America
Macedonia,
Moldavia
Balkan region
2. Reserve Slide: Basic steps to conduct
meaningful CBAs
• First step: define the boundaries of the project or
component that is to be analysed
 What exactly is to be analysed? What is the purpose of the analysis?
(includes geographic, institutional, topical boundaries, etc.)
• Second step: what are the outcome / impact hypotheses?
 How do costs relate to benefits, what are the expected outcome/impact
chains?
• Third step: list all the costs related to the selected project /
component (including local contributions, investment costs,
operational costs and management costs) and the benefits (in three
categories:
i) easy to quantify, ii) difficult to quantify, iii) non quantifiable)
• Fourth step: assess data availability; plan and implement data
collection
• Fifth step: set up CBA model and interpret it

Contenu connexe

Tendances

1 introduction to engineering economics
1  introduction to engineering economics1  introduction to engineering economics
1 introduction to engineering economicsMohsin Siddique
 
UNIT – I.ppt
UNIT – I.pptUNIT – I.ppt
UNIT – I.pptAsha A
 
Notes on Engineering Economics Unit I
Notes on Engineering Economics Unit INotes on Engineering Economics Unit I
Notes on Engineering Economics Unit IDeepak Srivastava
 
MG 6863 Engineering Economics notes
MG 6863 Engineering Economics notesMG 6863 Engineering Economics notes
MG 6863 Engineering Economics notesmechrmkcet2017
 
Cost Benefit Analysis in Public Project Appraisal (PPAC)
Cost Benefit Analysis in Public Project Appraisal (PPAC)Cost Benefit Analysis in Public Project Appraisal (PPAC)
Cost Benefit Analysis in Public Project Appraisal (PPAC)Neil Mathew
 
Unit 4 Capital Budgeting
Unit 4 Capital BudgetingUnit 4 Capital Budgeting
Unit 4 Capital BudgetingParrthipan B K
 
Cost Benifit Analysis
Cost Benifit AnalysisCost Benifit Analysis
Cost Benifit AnalysisTareq Zarouni
 
Cost analysis of Project
Cost analysis of ProjectCost analysis of Project
Cost analysis of ProjectPravin176
 
Cie 210 ps notes sessions 9 & 10 basic cost concepts & engg econ
Cie 210 ps notes sessions 9 & 10   basic cost concepts & engg econCie 210 ps notes sessions 9 & 10   basic cost concepts & engg econ
Cie 210 ps notes sessions 9 & 10 basic cost concepts & engg econNur Azrina Mohammad Zawawi
 
Engineering economic importance & application
Engineering economic importance & applicationEngineering economic importance & application
Engineering economic importance & applicationabdus sobhan
 
MG6863 Engineering Economics
MG6863 Engineering EconomicsMG6863 Engineering Economics
MG6863 Engineering EconomicsP Manimaran
 
Unit 2 Demand and Supply Analysis
Unit 2 Demand and Supply AnalysisUnit 2 Demand and Supply Analysis
Unit 2 Demand and Supply AnalysisParrthipan B K
 
Preparation and approaches of cost estimates
Preparation and approaches of cost estimatesPreparation and approaches of cost estimates
Preparation and approaches of cost estimatesnagashree123
 
3. eng. cost and estimation
3. eng. cost and estimation3. eng. cost and estimation
3. eng. cost and estimationMohsin Siddique
 
2.9 skill economic analysis
2.9 skill economic analysis2.9 skill economic analysis
2.9 skill economic analysisNigestAbebaw1
 
PE998.Upstream Petroleum Economics, Risk & Fiscal Analysis
PE998.Upstream Petroleum Economics, Risk & Fiscal AnalysisPE998.Upstream Petroleum Economics, Risk & Fiscal Analysis
PE998.Upstream Petroleum Economics, Risk & Fiscal AnalysispetroEDGE
 
Lo4a benefit cost analysis (nabil)
Lo4a benefit  cost analysis (nabil)Lo4a benefit  cost analysis (nabil)
Lo4a benefit cost analysis (nabil)Abdulaziz AlSuwaidi
 

Tendances (20)

1 introduction to engineering economics
1  introduction to engineering economics1  introduction to engineering economics
1 introduction to engineering economics
 
UNIT – I.ppt
UNIT – I.pptUNIT – I.ppt
UNIT – I.ppt
 
Notes on Engineering Economics Unit I
Notes on Engineering Economics Unit INotes on Engineering Economics Unit I
Notes on Engineering Economics Unit I
 
MG 6863 Engineering Economics notes
MG 6863 Engineering Economics notesMG 6863 Engineering Economics notes
MG 6863 Engineering Economics notes
 
Cost Benefit Analysis in Public Project Appraisal (PPAC)
Cost Benefit Analysis in Public Project Appraisal (PPAC)Cost Benefit Analysis in Public Project Appraisal (PPAC)
Cost Benefit Analysis in Public Project Appraisal (PPAC)
 
CCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost EstimatingCCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost Estimating
 
Unit 4 Capital Budgeting
Unit 4 Capital BudgetingUnit 4 Capital Budgeting
Unit 4 Capital Budgeting
 
Cost Benifit Analysis
Cost Benifit AnalysisCost Benifit Analysis
Cost Benifit Analysis
 
Cost analysis of Project
Cost analysis of ProjectCost analysis of Project
Cost analysis of Project
 
Cost benefit analysis
Cost benefit analysisCost benefit analysis
Cost benefit analysis
 
Cie 210 ps notes sessions 9 & 10 basic cost concepts & engg econ
Cie 210 ps notes sessions 9 & 10   basic cost concepts & engg econCie 210 ps notes sessions 9 & 10   basic cost concepts & engg econ
Cie 210 ps notes sessions 9 & 10 basic cost concepts & engg econ
 
Engineering economic importance & application
Engineering economic importance & applicationEngineering economic importance & application
Engineering economic importance & application
 
MG6863 Engineering Economics
MG6863 Engineering EconomicsMG6863 Engineering Economics
MG6863 Engineering Economics
 
Unit 2 Demand and Supply Analysis
Unit 2 Demand and Supply AnalysisUnit 2 Demand and Supply Analysis
Unit 2 Demand and Supply Analysis
 
Preparation and approaches of cost estimates
Preparation and approaches of cost estimatesPreparation and approaches of cost estimates
Preparation and approaches of cost estimates
 
3. eng. cost and estimation
3. eng. cost and estimation3. eng. cost and estimation
3. eng. cost and estimation
 
Petroleum economics
Petroleum economicsPetroleum economics
Petroleum economics
 
2.9 skill economic analysis
2.9 skill economic analysis2.9 skill economic analysis
2.9 skill economic analysis
 
PE998.Upstream Petroleum Economics, Risk & Fiscal Analysis
PE998.Upstream Petroleum Economics, Risk & Fiscal AnalysisPE998.Upstream Petroleum Economics, Risk & Fiscal Analysis
PE998.Upstream Petroleum Economics, Risk & Fiscal Analysis
 
Lo4a benefit cost analysis (nabil)
Lo4a benefit  cost analysis (nabil)Lo4a benefit  cost analysis (nabil)
Lo4a benefit cost analysis (nabil)
 

En vedette

iMPD Equipment
iMPD EquipmentiMPD Equipment
iMPD EquipmentKen Angus
 
Managed Pressure Drilling
Managed Pressure DrillingManaged Pressure Drilling
Managed Pressure DrillingKen Angus
 
Recycle wastewater oilfield - agriculture - 1-16-16 ar
Recycle wastewater   oilfield - agriculture -   1-16-16 arRecycle wastewater   oilfield - agriculture -   1-16-16 ar
Recycle wastewater oilfield - agriculture - 1-16-16 arEner-Corr Solutions, LLC
 
New Method for Simulation Of Fractures
New Method for Simulation Of FracturesNew Method for Simulation Of Fractures
New Method for Simulation Of Fracturesdavid_schechter
 
Project Cycle Management (PCM) & Logical Framework Analysis (LFA)
Project Cycle Management (PCM) & Logical Framework Analysis (LFA)Project Cycle Management (PCM) & Logical Framework Analysis (LFA)
Project Cycle Management (PCM) & Logical Framework Analysis (LFA)Erik Kijne
 
Advanced Full Mission Drilling Training Simulators
Advanced Full Mission Drilling Training SimulatorsAdvanced Full Mission Drilling Training Simulators
Advanced Full Mission Drilling Training Simulatorsarisimulation
 
Digital globalization: The new era of global flows
Digital globalization: The new era of global flowsDigital globalization: The new era of global flows
Digital globalization: The new era of global flowsMcKinsey & Company
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital BudgetingDayasagar S
 

En vedette (11)

Thesis_livia
Thesis_liviaThesis_livia
Thesis_livia
 
iMPD Equipment
iMPD EquipmentiMPD Equipment
iMPD Equipment
 
DISCOVERY DRILLING EQUIPMENT
DISCOVERY DRILLING EQUIPMENTDISCOVERY DRILLING EQUIPMENT
DISCOVERY DRILLING EQUIPMENT
 
Managed Pressure Drilling
Managed Pressure DrillingManaged Pressure Drilling
Managed Pressure Drilling
 
Recycle wastewater oilfield - agriculture - 1-16-16 ar
Recycle wastewater   oilfield - agriculture -   1-16-16 arRecycle wastewater   oilfield - agriculture -   1-16-16 ar
Recycle wastewater oilfield - agriculture - 1-16-16 ar
 
New Method for Simulation Of Fractures
New Method for Simulation Of FracturesNew Method for Simulation Of Fractures
New Method for Simulation Of Fractures
 
Project Cycle Management (PCM) & Logical Framework Analysis (LFA)
Project Cycle Management (PCM) & Logical Framework Analysis (LFA)Project Cycle Management (PCM) & Logical Framework Analysis (LFA)
Project Cycle Management (PCM) & Logical Framework Analysis (LFA)
 
Advanced Full Mission Drilling Training Simulators
Advanced Full Mission Drilling Training SimulatorsAdvanced Full Mission Drilling Training Simulators
Advanced Full Mission Drilling Training Simulators
 
Economic project report
Economic project reportEconomic project report
Economic project report
 
Digital globalization: The new era of global flows
Digital globalization: The new era of global flowsDigital globalization: The new era of global flows
Digital globalization: The new era of global flows
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgeting
 

Similaire à Training on Financial and Economic Project Evaluation

Economic incentieves and water demand mamangent 2
Economic incentieves and water demand mamangent 2Economic incentieves and water demand mamangent 2
Economic incentieves and water demand mamangent 2Hemesiri Kotagama
 
L03 integration management
L03 integration managementL03 integration management
L03 integration managementAsa Chan
 
Engineering economics Slides for Postgraduates
Engineering economics Slides for PostgraduatesEngineering economics Slides for Postgraduates
Engineering economics Slides for Postgraduatesssuser50050d1
 
Pm evaluationand selection1
Pm evaluationand selection1Pm evaluationand selection1
Pm evaluationand selection1eshang0904
 
Unit 10 Investment decisions.pdf
Unit 10 Investment decisions.pdfUnit 10 Investment decisions.pdf
Unit 10 Investment decisions.pdfPrabin Pandit
 
Intro to engineering economy
Intro to engineering economyIntro to engineering economy
Intro to engineering economyKwesi Kissiedu
 
The Discounted Cash Flow Valuation.pptx
The Discounted Cash Flow Valuation.pptxThe Discounted Cash Flow Valuation.pptx
The Discounted Cash Flow Valuation.pptxasde13
 
Project_selectionProject_selectionnn.ppt
Project_selectionProject_selectionnn.pptProject_selectionProject_selectionnn.ppt
Project_selectionProject_selectionnn.pptssdongre1
 
Financial Analysis for Project Management.ppt
Financial Analysis for Project Management.pptFinancial Analysis for Project Management.ppt
Financial Analysis for Project Management.pptIndranilGanguly21
 
Cost-Benefit Analysis
Cost-Benefit AnalysisCost-Benefit Analysis
Cost-Benefit AnalysisSakshi Sharma
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsEssam Lotffy, PMP®, CCP®
 
Engineering economics ECO-202
Engineering economics ECO-202Engineering economics ECO-202
Engineering economics ECO-202Saqib Imran
 
Engineering economics eco202
Engineering economics eco202Engineering economics eco202
Engineering economics eco202Saqib Imran
 

Similaire à Training on Financial and Economic Project Evaluation (20)

Economic incentieves and water demand mamangent 2
Economic incentieves and water demand mamangent 2Economic incentieves and water demand mamangent 2
Economic incentieves and water demand mamangent 2
 
Nce603 mod unit3
Nce603 mod unit3Nce603 mod unit3
Nce603 mod unit3
 
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
 
Pmp inititating process group
Pmp inititating process groupPmp inititating process group
Pmp inititating process group
 
L03 integration management
L03 integration managementL03 integration management
L03 integration management
 
Pm assignment
Pm assignmentPm assignment
Pm assignment
 
Engineering economics Slides for Postgraduates
Engineering economics Slides for PostgraduatesEngineering economics Slides for Postgraduates
Engineering economics Slides for Postgraduates
 
Pm evaluationand selection1
Pm evaluationand selection1Pm evaluationand selection1
Pm evaluationand selection1
 
Unit 10 Investment decisions.pdf
Unit 10 Investment decisions.pdfUnit 10 Investment decisions.pdf
Unit 10 Investment decisions.pdf
 
SPM Evaluation
SPM EvaluationSPM Evaluation
SPM Evaluation
 
Mod 3 construction economics
Mod 3 construction economicsMod 3 construction economics
Mod 3 construction economics
 
Intro to engineering economy
Intro to engineering economyIntro to engineering economy
Intro to engineering economy
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
The Discounted Cash Flow Valuation.pptx
The Discounted Cash Flow Valuation.pptxThe Discounted Cash Flow Valuation.pptx
The Discounted Cash Flow Valuation.pptx
 
Project_selectionProject_selectionnn.ppt
Project_selectionProject_selectionnn.pptProject_selectionProject_selectionnn.ppt
Project_selectionProject_selectionnn.ppt
 
Financial Analysis for Project Management.ppt
Financial Analysis for Project Management.pptFinancial Analysis for Project Management.ppt
Financial Analysis for Project Management.ppt
 
Cost-Benefit Analysis
Cost-Benefit AnalysisCost-Benefit Analysis
Cost-Benefit Analysis
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projects
 
Engineering economics ECO-202
Engineering economics ECO-202Engineering economics ECO-202
Engineering economics ECO-202
 
Engineering economics eco202
Engineering economics eco202Engineering economics eco202
Engineering economics eco202
 

Plus de tobiassommer2013

Ppt formation professionnelle agricole au bénin - alidou salihou mamadou
Ppt   formation professionnelle agricole au bénin - alidou salihou mamadouPpt   formation professionnelle agricole au bénin - alidou salihou mamadou
Ppt formation professionnelle agricole au bénin - alidou salihou mamadoutobiassommer2013
 
Ppt vsd – johann-peter porten
Ppt   vsd – johann-peter portenPpt   vsd – johann-peter porten
Ppt vsd – johann-peter portentobiassommer2013
 
Ppt analysis of vet results frameworks - franz kehl & markus engler
Ppt   analysis of vet results frameworks - franz kehl & markus englerPpt   analysis of vet results frameworks - franz kehl & markus engler
Ppt analysis of vet results frameworks - franz kehl & markus englertobiassommer2013
 
Ppt co is in vsd - simon junker
Ppt   co is in vsd - simon junkerPpt   co is in vsd - simon junker
Ppt co is in vsd - simon junkertobiassommer2013
 
Ppt co is field test - sirocco messerli
Ppt   co is field test - sirocco messerliPpt   co is field test - sirocco messerli
Ppt co is field test - sirocco messerlitobiassommer2013
 
Results Measurement in Conflict-Affected environments
Results Measurement in Conflict-Affected environmentsResults Measurement in Conflict-Affected environments
Results Measurement in Conflict-Affected environmentstobiassommer2013
 
M4P and Financial Development
M4P and Financial DevelopmentM4P and Financial Development
M4P and Financial Developmenttobiassommer2013
 
M4P and Women's Economic Empowerment Guideline
M4P and Women's Economic Empowerment GuidelineM4P and Women's Economic Empowerment Guideline
M4P and Women's Economic Empowerment Guidelinetobiassommer2013
 
PPT Schweizer Hagel – Hansueli Lusti
PPT Schweizer Hagel – Hansueli LustiPPT Schweizer Hagel – Hansueli Lusti
PPT Schweizer Hagel – Hansueli Lustitobiassommer2013
 
Market systems development in fragile contexts 13 may dj
Market systems development in fragile contexts 13 may djMarket systems development in fragile contexts 13 may dj
Market systems development in fragile contexts 13 may djtobiassommer2013
 

Plus de tobiassommer2013 (11)

Ppt formation professionnelle agricole au bénin - alidou salihou mamadou
Ppt   formation professionnelle agricole au bénin - alidou salihou mamadouPpt   formation professionnelle agricole au bénin - alidou salihou mamadou
Ppt formation professionnelle agricole au bénin - alidou salihou mamadou
 
Ppt vsd – johann-peter porten
Ppt   vsd – johann-peter portenPpt   vsd – johann-peter porten
Ppt vsd – johann-peter porten
 
Ppt analysis of vet results frameworks - franz kehl & markus engler
Ppt   analysis of vet results frameworks - franz kehl & markus englerPpt   analysis of vet results frameworks - franz kehl & markus engler
Ppt analysis of vet results frameworks - franz kehl & markus engler
 
Ppt co is in vsd - simon junker
Ppt   co is in vsd - simon junkerPpt   co is in vsd - simon junker
Ppt co is in vsd - simon junker
 
Ppt co is field test - sirocco messerli
Ppt   co is field test - sirocco messerliPpt   co is field test - sirocco messerli
Ppt co is field test - sirocco messerli
 
Ppt cspm markus heiniger
Ppt cspm markus heinigerPpt cspm markus heiniger
Ppt cspm markus heiniger
 
Results Measurement in Conflict-Affected environments
Results Measurement in Conflict-Affected environmentsResults Measurement in Conflict-Affected environments
Results Measurement in Conflict-Affected environments
 
M4P and Financial Development
M4P and Financial DevelopmentM4P and Financial Development
M4P and Financial Development
 
M4P and Women's Economic Empowerment Guideline
M4P and Women's Economic Empowerment GuidelineM4P and Women's Economic Empowerment Guideline
M4P and Women's Economic Empowerment Guideline
 
PPT Schweizer Hagel – Hansueli Lusti
PPT Schweizer Hagel – Hansueli LustiPPT Schweizer Hagel – Hansueli Lusti
PPT Schweizer Hagel – Hansueli Lusti
 
Market systems development in fragile contexts 13 may dj
Market systems development in fragile contexts 13 may djMarket systems development in fragile contexts 13 may dj
Market systems development in fragile contexts 13 may dj
 

Dernier

Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Pereraictsugar
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfrichard876048
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditNhtLNguyn9
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Peter Ward
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menzaictsugar
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfJos Voskuil
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 

Dernier (20)

Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Perera
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdf
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal audit
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdf
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
 

Training on Financial and Economic Project Evaluation

  • 1. Training on Financial and Economic Project Evaluation (cost benefit analysis) May 15th 2013
  • 2. Learning objectives 1. Understand the concept, utility and limits of financial/private and economic/social project evaluation (cost benefit) 2. Know how to interpret the results of financial/economic evaluations (cost benefit) 3. Understand the opportunities of financial/economic evaluation being part of the PCM and its implication for results based project management 4. Identify development projects for which the concept can be applied, and for which kind of projects other methods are more adequate
  • 3. Group Work Social Entrepreneur selling a technology like micro irrigation to poor farmers 1. What do you need to know to make this business a success and not a bankruptcy?
  • 4. Objective of CBA applied to project evaluation Make better informed decisions on whether to invest or not Relying on the necessary information to quantify variables which are related to • investment, • operational costs and • incomes
  • 5. Market / feasibility Study Technical Study Organisational study Financial Evaluation Important studies needed for project formulation and evaluation Economic Evaluation
  • 6. The different studies provide information for the project evaluation - business approach - Benefits / Costs Return on investment Market Study Objective: Determine the existence of the unmet demand and quantify it Technical Study Objective: Verify the technical feasibility Organisational Study Objective: define the optimal organisational structure  Analysis of demand  Analysis of supply  Price or fee  Marketing strategy  Production capacity  Technology  Infrastructure  Human resources  Information system  Legal aspects
  • 7. What is cost-benefit analysis (CBA)? The aim of the cost benefit analysis is to assess the profitability of investments over time, by comparing the costs of a project with its benefits COSTS =  investment costs  running costs or operational costs  financial costs  support costs Only real costs are considered in the CBA, i.e. costs that correspond to flows of cash, and the costs are computed at the time when they occur during project life. BENEFITS:  increased production, project sales  reduced costs  social benefits,  improved  livelihood,  reduced  poverty,…
  • 8. Quantification is required! CBA requires to quantify all the costs and benefits, which is sometimes rather challenging. Where quantification is not possible, benefits and costs should be included in the discussion and interpretation of the models, or another method should be selected (e.g. Cost effectiveness) Whose costs should be considered ? Beyond financial evaluation: all costs need to be taken into account • SDC project costs • Other counterpart costs • Costs beneficiaries bear (incl. in-kind contributions)
  • 9. Note: the CBA compares additional costs and additional benefits for the users / for the enterprise, etc. i.e. the costs and benefits WITH or WITHOUT the project Example of a CBA Note: year 0 is only virtual, so that the project can start in year 1 it is necessary to have the funds available on the day before the project starts Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 COSTS -100 -12 -13 -11 -13 -12 Investment -100 Operations -10 -10 -10 -10 -10 Other costs -2 -3 -1 -3 -2 BENEFITS 0 12 20 50 50 100 Sales 12 20 50 50 50 Residual value 50 CASH FLOW -100 0 7 39 37 88
  • 10. DISCOUNTING Principle: 1 dollar today is worth more than 1 dollar tomorrow Question: what is the value today of the money you will earn next year, or in 2, 3 or 10 years from now? Example: on your savings account you have 5’000  CHF   earning 2% per year How much will you have on your account after 5 years? (assuming that you have no transaction costs and that the interest rate remains unchanged) Interest 1st year = 5’000  * 2% = 5’100  CHF Interest 2nd year = 5’100  *  2%  = 5’202  CHF   Etc…  
  • 11. Compound interest Discounting capital (P) = today 5'000 capital (P) = today 4’528 interest (r) 2% interest (r) 2% time (years) (n) 5 time (years) (n) 5 accumulated capital (A) 5’520 accumulated capital (A) 5’000 A = P(1 + r)n P= A(1+r)-n
  • 12. Net Present Value and Internal Rate of Return Net present value (NPV) = value today of the cash flow of each year of the analysed period In Excel, use +NPV(10%;year1...year5)+year 0 (here = 15.00) Internal Rate of Return (IRR) = rate that the project generates over time (this rate can be compared with interest rate of banks or alternative use of the capital In Excel, use +IRR(year0 ... Year5) (here = 13.81%) Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 COSTS -100 -12 -13 -11 -13 -12 BENEFITS 0 12 20 50 50 100 CASH FLOW -100 0 7 39 37 88
  • 13. Evaluation criteria Net present value (NPV) • Expresses the difference between total expenditure and income of the project (cash flow) but discounted to the value of money at project start. • Shows the surplus after having received the demanded profitability (discount factor) and having retrieved the total investment • The convention is to accept the project if the NPV is bigger or equal to 0. Internal rate of return (IRR)) • Shows the maximal profitability that can be expected of the investment. • The project is accepted if the IRR is bigger or equal to the discount factor. • IRR only tells us if the project is better than the alternative use of funds (IRR does not allow to compare different project) Benefit – Cost Relation (BC) • Compares the present value of the benefits with the present value of the costs including the investment, shown as a ratio • The project is accepted if the ratio is bigger or equal to zero.one
  • 14. EXTERNALITIES Externalities are “side  effects”  of projects or enterprises which are not included in the costs and benefits; they can be positive (external benefits) or negative (externals costs). In the case of negative externalities, the costs are usually paid by the society Examples of external benefits  Access to electricity for villagers after a factory was installed in the neighbourhood  After a village installed electricity supply, an enterprise decides to settle in the neighbourhood ( job creation) Examples of external costs  Pollution, noise, traffic, etc.
  • 15. Economic analysis SHADOW PRICES / economic prices (also called opportunity costs) Market prices do not always reflect the real value of products. This is the case for instance when subsidies or taxes are paid / charged. Example: fertiliser  price  on  the  market  =  100’000  VND subsidy from the Government = 25% real  value  of  fertiliser  =  100’000  VND  +  25%  =  125’000  VND In this case, farmers get fertilisers cheaper than the real value, the financial value is lower than the economic value
  • 16. FINANCIAL VS ECONOMIC ANALYSIS Financial Economic CBA shows the interests of ... Private enterprise: is the project profitable for the investor? Society: is the project beneficial to the society (whole economy) Prices considered Costs and benefits at market prices Shadow prices (opportunity prices), i.e. prices are corrected from subsidies, taxes, etc. Externalities Not considered Considered
  • 18. Reserve Slide: Structure of the flow of funds statement + Income (tax relevant) - Expenditure (tax relevant) - Expenditure not implying cash flows, but tax relevant (depreciation and amortization) = Profit before taxes - Taxes = Profit after taxes + Adjustment for expenditures not implying cash flows (depreciation and amortization) - Expenditure not relevant for taxes (investments) + Benefits not relevant for taxes (residual value) = Cash Flow
  • 19. Consideration concerning the cash flow Time horizon of the evaluation • Is highly dependent on the characteristics of each project. • If the project life time can be foreseen, and is not long term, the most convenient is to construct the flow of funds for this number of years. • If the enterprise (or structure) the project wants to create will stay in the market (no exit strategy), the general convention is to project the flow of funds for 10 years. • The expected benefits beyond the 10th year are then reflected in the residual value.
  • 20. Risk within projects When preparing and evaluating projects one has to rely on assumptions, e.g. with respect to – population growth, – demand, – supply, – technologies, – availability of inputs, – estimation of costs, – estimation of benefits, – etc., etc., etc. …  where  there  are  assumption  there  are   risks
  • 21. Mainly serves for : a. Determine critical variables and their ranges of variation. b. Study and determine the effects of the critical variables on the results of the project. c. Evaluate the project with different external conditions. Sensitivity analysis
  • 22. Methods for sensitivity analysis Select the critical variables : Consider the variables that are difficult to predict Select the variable with the biggest impact on the NPV … or those with the highest uncertainty. Move one variable at a time (Ceteris Paribus) Construct different scenarios for a group of the above variables and re-calculate the project criteria.
  • 23. Possible Alternative: Cost Effectiveness Analysis • Applied when benefits cannot be quantified (with reasonable effort) • Instrument for comparing different approaches to reach a certain benefit • Choose the approach that creates the biggest and lasting benefit for the beneficiaries • Used to justify an approach for funding (as compared to alternatives)
  • 24. Cost Effectiveness Analysis Impacts that the project is supposed to reach Distinguish major impact and side impacts (or secondary impacts) Starting point = project design COSTS = Direct costs Investment costs, Support costs (coaching, backstopping, etc.) Maintenance costs Costs for SDC and costs for partner organisations Indirect costs may also be considered BENEFITS: are the benefits really the same, how sustainable are the benefits, etc.
  • 25. Important to remember 1. You need solid numbers a) to construct financial and economic evaluations, evaluate results before, after, during b) to formulate your project: market studies etc. 2. Financial (private) evaluation shows whether private sector part is viable or what the project needs to do to make it viable
  • 26. Important to remember 3. Financial and economic evaluation are key tools to improve result management:  Identify benefits  Quantify benefits  Establish causality … even if no precise NPV can be calculated.
  • 27. Important to remember 4. Economic/social evaluation provides valuable, additional decision criteria (not the only ones!) a) to approve or reject projects b) to identify more objectively and quantified what works and can be scaled up
  • 28. 1. Reserve Slide: Domains of application of CBA in development cooperation • CBA can be applied in a wide range of projects, key condition is the quantification of costs and benefits • CBA can be applied to entire projects or to selected project components Difficulty to apply Low Medium High Project dealing with Income generation, livelihood, economic development Health, education, nature conservation, biodiversity, etc. Governance, policy dialogue, institutional development Examples of CBAs (done or in preparation) Vietnam, Mongolia, South Africa, Latin America Macedonia, Moldavia Balkan region
  • 29. 2. Reserve Slide: Basic steps to conduct meaningful CBAs • First step: define the boundaries of the project or component that is to be analysed  What exactly is to be analysed? What is the purpose of the analysis? (includes geographic, institutional, topical boundaries, etc.) • Second step: what are the outcome / impact hypotheses?  How do costs relate to benefits, what are the expected outcome/impact chains? • Third step: list all the costs related to the selected project / component (including local contributions, investment costs, operational costs and management costs) and the benefits (in three categories: i) easy to quantify, ii) difficult to quantify, iii) non quantifiable) • Fourth step: assess data availability; plan and implement data collection • Fifth step: set up CBA model and interpret it