SlideShare une entreprise Scribd logo
1  sur  13
Critical Path
Vazi Okhandiar, PMP, MCT, MBA, MSCS, BSEE
NR Computer Learning
Center
1835 W. Orangewood, #200
Orange . CA 92868
(714) 505-3475
www.nrclc.com
Critical Path Method (CPM)
 The critical path method is a project modeling

technique developed in the late 1950s by Morgan
R. Walker of DuPont and James E. Kelley, Jr. of
Remington Rand. - Wikipedia
Critical Path
 The critical path method was examined by the

United States Navy, and established a version in
1958 called a PERT (Program Evaluation and
Review Technique) analysis. PERT claimed to
reduce project management time by up to 42
percent, and was first used in the development of
the Polaris missile.
Ref: http://www.ehow.com/about_4703555_whatcritical-path.html#ixzz2igTEV3Q7
Critical Path
 A Critical Path is the path with the least amount of

float or slack time. A float time is the amount of
time that an activity can be delayed without
delaying the project.
 A Critical Path is the longest amount of time it will
take to complete the project.
 A Critical Path usually has 0 float but may have
negative float if the end task is constrained to an
early finish date.
 If any of the task identified in the critical path is
late, then the project will be late.
6. Steps for identifying Critical
Path
1.
2.
3.

Specify the activates, duration and dependencies
Draw a network diagram.
Perform the forward pass to identify all Early Start and Early
Finish times for the network.
Early Finish = Early Start + Duration

4.

Perform the backward pass to identify all Late Start and Late
Finish times for the network.
Late Start = Late Finish – Duration

5.

Calculate the slack time.
Float = Late Start (LS) – Early Start (ES)

6.

Identify the task on critical path with 0 float (slack) time.
1. Task/Duration/Predecessor
TAS
K
A
B
C
D
E
F
G

Duratio Predecess
n
or
2
---2
A
1
A
3
A
1
C,D
3
B
2
E,F
Terminologies
 ID – Task ID
 D- Duration
 ES – Early Start
 EF – Early Finish
 LS – Late Start

ES

 LF – Late Finish

F ID DR
LS
LF

 S - Slack

EF
2. Network Diagram
B 2

F 3

Activity
A 2

C 1

G 2

Duratio
n
ES

D 3

E 1

F
LS

EF
ID DR
LF
3. Forward Pass
2

Early
Start

4
B 2

1st

2
A 2

7
F 3

Early

Duration=
9days

Finish
2

5
D 3

7

3
C 1

2

0

4

5

task starts at 0
EF = ES + DR
ES = EF of predecessor
When more than one predecessor, pick the
larger #

6
E 1

9
G 2

ES
F
LS

EF
ID DR
LF
4. Backward Pass
2

4
B 2

1st task should
end with LS = 0.

2

0

2
A 2
0
2
Late
Start

2

4

4

7
F 3
4
7
7

9
G 2
7
9

3

C 1
5

6

Late
Finish

2

LS = LF - DR
LF = LS of successor

5
D 3
3
6

5

6
E 1
6
7

When more than one successor, pick the
smallest #

ES
F
LS

EF
ID DR
LF
5. Slack / Float
2
4
0 B 2
2
4

0
2
0 A 2
0
2

4
7
0 F 3
4
7
7
9
0 G 2
7
9

2
3
3 C 1
5
6

Float = LS – ES

2
5
1 D 3
3
6

5
6
1 E 1
6
7

Float = Late Start (LS) – Early Start (ES)

ES
F
LS

EF
ID DR
LF
6. Critical Path
The path with 0 Float
is the critical path.

0
2
0 A 2
0
2

2
4
0 B 2
2
4

4
7
0 F 3
4
7

A-B-F-G is the critical
5
path. 6
0 C 1
5
6

2
5
0 D 3
2
5
LS = LF - DR
LF = LS of successor

7

0 G 2
7

5
6
1 E 1
6
7

9
9

ES
F
LS

EF
ID DR
LF
Thank You!
Vazi Okhandiar, PMP, MCT, MBA, MSCS, BSEE
NR Computer Learning Center
1835 W. Orangewood, Suite 200
Orange, CA 92868
www.nrclc.com . (714) 505. 3475
info@nrclc.com

Contenu connexe

Tendances

Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Zulfiquer Ahmed Amin
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksPrasad Thanthratey
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTS.Vijaya Bhaskar
 
Project controls
Project controlsProject controls
Project controlsAshok Kumar
 
Lect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMLect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMMubashir Ali
 
Project Controlling and Project Monitoring
Project Controlling and Project MonitoringProject Controlling and Project Monitoring
Project Controlling and Project Monitoringharoldtaylor1113
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project schedulingSoe Naing Win
 
Critical path method
Critical path methodCritical path method
Critical path methodDhruv Shah
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniquesShivangi Saini
 

Tendances (20)

Project Planning
Project PlanningProject Planning
Project Planning
 
Pert
PertPert
Pert
 
Pert and cpm
Pert and cpmPert and cpm
Pert and cpm
 
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
 
Gantt PERT and CPM
Gantt PERT and CPMGantt PERT and CPM
Gantt PERT and CPM
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Schedule Updates
Schedule UpdatesSchedule Updates
Schedule Updates
 
Project controls
Project controlsProject controls
Project controls
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Lect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMLect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPM
 
Project Controlling and Project Monitoring
Project Controlling and Project MonitoringProject Controlling and Project Monitoring
Project Controlling and Project Monitoring
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 

En vedette

Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysistutor2u
 
The Network Diagram and Critical Path
The Network Diagram and Critical PathThe Network Diagram and Critical Path
The Network Diagram and Critical Pathdmdk12
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path MethodNicola2903
 
Constructing a network diagram
Constructing a network diagramConstructing a network diagram
Constructing a network diagramnelramlawy
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path MethodSimplilearn
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)Areef Khan
 
How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013Ong-Art Sanpinit
 
Scrum und Agile Software Entwicklung
Scrum und Agile Software EntwicklungScrum und Agile Software Entwicklung
Scrum und Agile Software EntwicklungAniello Bove
 
Critical chain and buffer management
Critical chain and buffer managementCritical chain and buffer management
Critical chain and buffer managementpinalti
 
Critical path method example by myassignmenthelp
Critical path method example by myassignmenthelpCritical path method example by myassignmenthelp
Critical path method example by myassignmenthelpwww.myassignmenthelp.net
 
Apics Pdm Buffer Mgt. 1 09 07
Apics Pdm Buffer Mgt. 1 09 07Apics Pdm Buffer Mgt. 1 09 07
Apics Pdm Buffer Mgt. 1 09 07rbernett
 
Critical path method
Critical path methodCritical path method
Critical path methodShubhi Verma
 
Critical path method (CPM)
Critical path method (CPM)Critical path method (CPM)
Critical path method (CPM)Nikhil Raj
 
C10 project management
C10 project managementC10 project management
C10 project managementhakimizaki
 
Critical path method
Critical path methodCritical path method
Critical path methodNicola2903
 

En vedette (19)

Critical path method
Critical path methodCritical path method
Critical path method
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
 
The Network Diagram and Critical Path
The Network Diagram and Critical PathThe Network Diagram and Critical Path
The Network Diagram and Critical Path
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path Method
 
Constructing a network diagram
Constructing a network diagramConstructing a network diagram
Constructing a network diagram
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)
 
The Project's Network Diagram
The Project's Network DiagramThe Project's Network Diagram
The Project's Network Diagram
 
How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013
 
Scrum und Agile Software Entwicklung
Scrum und Agile Software EntwicklungScrum und Agile Software Entwicklung
Scrum und Agile Software Entwicklung
 
Planning and facilitating focus groups - University of Cambridge
Planning and facilitating focus groups - University of CambridgePlanning and facilitating focus groups - University of Cambridge
Planning and facilitating focus groups - University of Cambridge
 
Critical chain and buffer management
Critical chain and buffer managementCritical chain and buffer management
Critical chain and buffer management
 
Critical path method example by myassignmenthelp
Critical path method example by myassignmenthelpCritical path method example by myassignmenthelp
Critical path method example by myassignmenthelp
 
Apics Pdm Buffer Mgt. 1 09 07
Apics Pdm Buffer Mgt. 1 09 07Apics Pdm Buffer Mgt. 1 09 07
Apics Pdm Buffer Mgt. 1 09 07
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Critical path method (CPM)
Critical path method (CPM)Critical path method (CPM)
Critical path method (CPM)
 
C10 project management
C10 project managementC10 project management
C10 project management
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Lecture 6
Lecture 6Lecture 6
Lecture 6
 

Similaire à Project Management - Critical path method

Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering EconomicsDeepak Paithankar
 
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.pptNitin137794
 
Project managemen PERT VS CPM
Project managemen  PERT VS CPMProject managemen  PERT VS CPM
Project managemen PERT VS CPMPadamNepal1
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1adeelmunir158
 
CPM.pptx
CPM.pptxCPM.pptx
CPM.pptxLJay7
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7Akihisa Akimoto
 
Management science
Management scienceManagement science
Management sciencekamrul islam
 
DEFINITION OF TERMS IN A NETWORK.pdf
DEFINITION OF TERMS IN A NETWORK.pdfDEFINITION OF TERMS IN A NETWORK.pdf
DEFINITION OF TERMS IN A NETWORK.pdfssuserc9c6261
 
chapter 8 examples of networks.pdf
chapter 8 examples of networks.pdfchapter 8 examples of networks.pdf
chapter 8 examples of networks.pdfssuserc9c6261
 
EXAMPLES OF THE USE OF DUMMYACTIVITY.pdf
EXAMPLES OF THE USE OF DUMMYACTIVITY.pdfEXAMPLES OF THE USE OF DUMMYACTIVITY.pdf
EXAMPLES OF THE USE OF DUMMYACTIVITY.pdfssuserc9c6261
 
Scheduling, PERT, Critical Path Analysis.pdf
Scheduling, PERT, Critical Path Analysis.pdfScheduling, PERT, Critical Path Analysis.pdf
Scheduling, PERT, Critical Path Analysis.pdfssuserc9c6261
 
network techniquies.pdf
network techniquies.pdfnetwork techniquies.pdf
network techniquies.pdfssuserc9c6261
 
Activity, duration, ES, EF, LS, LF–.pdf
Activity, duration, ES, EF, LS, LF–.pdfActivity, duration, ES, EF, LS, LF–.pdf
Activity, duration, ES, EF, LS, LF–.pdfssuserc9c6261
 
Arc with ES & EF time –.pdf
Arc with ES & EF time –.pdfArc with ES & EF time –.pdf
Arc with ES & EF time –.pdfssuserc9c6261
 

Similaire à Project Management - Critical path method (20)

Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering Economics
 
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
 
Project managemen PERT VS CPM
Project managemen  PERT VS CPMProject managemen  PERT VS CPM
Project managemen PERT VS CPM
 
Project admin lu3
Project admin   lu3Project admin   lu3
Project admin lu3
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
 
CPM.pptx
CPM.pptxCPM.pptx
CPM.pptx
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Project management
Project managementProject management
Project management
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7
 
Management science
Management scienceManagement science
Management science
 
DEFINITION OF TERMS IN A NETWORK.pdf
DEFINITION OF TERMS IN A NETWORK.pdfDEFINITION OF TERMS IN A NETWORK.pdf
DEFINITION OF TERMS IN A NETWORK.pdf
 
chapter 8 examples of networks.pdf
chapter 8 examples of networks.pdfchapter 8 examples of networks.pdf
chapter 8 examples of networks.pdf
 
EXAMPLES OF THE USE OF DUMMYACTIVITY.pdf
EXAMPLES OF THE USE OF DUMMYACTIVITY.pdfEXAMPLES OF THE USE OF DUMMYACTIVITY.pdf
EXAMPLES OF THE USE OF DUMMYACTIVITY.pdf
 
Scheduling, PERT, Critical Path Analysis.pdf
Scheduling, PERT, Critical Path Analysis.pdfScheduling, PERT, Critical Path Analysis.pdf
Scheduling, PERT, Critical Path Analysis.pdf
 
network techniquies.pdf
network techniquies.pdfnetwork techniquies.pdf
network techniquies.pdf
 
Activity, duration, ES, EF, LS, LF–.pdf
Activity, duration, ES, EF, LS, LF–.pdfActivity, duration, ES, EF, LS, LF–.pdf
Activity, duration, ES, EF, LS, LF–.pdf
 
Arc with ES & EF time –.pdf
Arc with ES & EF time –.pdfArc with ES & EF time –.pdf
Arc with ES & EF time –.pdf
 

Plus de NR Computer Learning Center

App Development with Apple Swift Certification at Certiport Centers
App Development with Apple Swift Certification at Certiport CentersApp Development with Apple Swift Certification at Certiport Centers
App Development with Apple Swift Certification at Certiport CentersNR Computer Learning Center
 
Building a Dashboard in an hour with Power Pivot and Power BI
Building a Dashboard in an hour with Power Pivot and Power BIBuilding a Dashboard in an hour with Power Pivot and Power BI
Building a Dashboard in an hour with Power Pivot and Power BINR Computer Learning Center
 
Introduction to the basic mathematical concept with Python Turtle.
Introduction to the basic mathematical concept with Python Turtle.Introduction to the basic mathematical concept with Python Turtle.
Introduction to the basic mathematical concept with Python Turtle.NR Computer Learning Center
 
Stem presentation - Pathways to Technology Oriented Careers
Stem presentation - Pathways to Technology Oriented CareersStem presentation - Pathways to Technology Oriented Careers
Stem presentation - Pathways to Technology Oriented CareersNR Computer Learning Center
 
Building a Dashboard in an Hour using Microsoft PowerPivot & Power BI
Building a Dashboard in an Hour using Microsoft PowerPivot & Power BIBuilding a Dashboard in an Hour using Microsoft PowerPivot & Power BI
Building a Dashboard in an Hour using Microsoft PowerPivot & Power BINR Computer Learning Center
 

Plus de NR Computer Learning Center (20)

Power BI Desktop Overview
Power BI Desktop Overview Power BI Desktop Overview
Power BI Desktop Overview
 
Building Dashboard with Excel
Building Dashboard with ExcelBuilding Dashboard with Excel
Building Dashboard with Excel
 
Introduction to Data Analytics
Introduction to Data AnalyticsIntroduction to Data Analytics
Introduction to Data Analytics
 
Python - Data Structures
Python - Data StructuresPython - Data Structures
Python - Data Structures
 
Introduction to SQL
Introduction to SQLIntroduction to SQL
Introduction to SQL
 
Office 2019 tips & tricks
Office 2019 tips & tricksOffice 2019 tips & tricks
Office 2019 tips & tricks
 
App Development with Apple Swift Certification at Certiport Centers
App Development with Apple Swift Certification at Certiport CentersApp Development with Apple Swift Certification at Certiport Centers
App Development with Apple Swift Certification at Certiport Centers
 
Project management fundamentals
Project management fundamentalsProject management fundamentals
Project management fundamentals
 
National College Testing Association (NCTA)
National College Testing Association (NCTA)National College Testing Association (NCTA)
National College Testing Association (NCTA)
 
National College Testing Association (NCTA)
National College Testing Association (NCTA)National College Testing Association (NCTA)
National College Testing Association (NCTA)
 
Building a Dashboard in an hour with Power Pivot and Power BI
Building a Dashboard in an hour with Power Pivot and Power BIBuilding a Dashboard in an hour with Power Pivot and Power BI
Building a Dashboard in an hour with Power Pivot and Power BI
 
Introduction to the basic mathematical concept with Python Turtle.
Introduction to the basic mathematical concept with Python Turtle.Introduction to the basic mathematical concept with Python Turtle.
Introduction to the basic mathematical concept with Python Turtle.
 
Stem presentation - Pathways to Technology Oriented Careers
Stem presentation - Pathways to Technology Oriented CareersStem presentation - Pathways to Technology Oriented Careers
Stem presentation - Pathways to Technology Oriented Careers
 
MTA 98 364 - database fundamentals
MTA 98 364 - database fundamentalsMTA 98 364 - database fundamentals
MTA 98 364 - database fundamentals
 
MTA 361 software development fundamentals
MTA 361   software development fundamentalsMTA 361   software development fundamentals
MTA 361 software development fundamentals
 
Introduction to java
Introduction to javaIntroduction to java
Introduction to java
 
Introduction to c++
Introduction to c++Introduction to c++
Introduction to c++
 
Executive dashboard for small business
Executive dashboard for small businessExecutive dashboard for small business
Executive dashboard for small business
 
Building a Dashboard in an Hour using Microsoft PowerPivot & Power BI
Building a Dashboard in an Hour using Microsoft PowerPivot & Power BIBuilding a Dashboard in an Hour using Microsoft PowerPivot & Power BI
Building a Dashboard in an Hour using Microsoft PowerPivot & Power BI
 
Arduino for teens
Arduino for teensArduino for teens
Arduino for teens
 

Dernier

Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management SystemChristalin Nelson
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management systemChristalin Nelson
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfPatidar M
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfVanessa Camilleri
 
Millenials and Fillennials (Ethical Challenge and Responses).pptx
Millenials and Fillennials (Ethical Challenge and Responses).pptxMillenials and Fillennials (Ethical Challenge and Responses).pptx
Millenials and Fillennials (Ethical Challenge and Responses).pptxJanEmmanBrigoli
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4MiaBumagat1
 
Expanded definition: technical and operational
Expanded definition: technical and operationalExpanded definition: technical and operational
Expanded definition: technical and operationalssuser3e220a
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Celine George
 
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxlancelewisportillo
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptxiammrhaywood
 
Oppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmOppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmStan Meyer
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)lakshayb543
 
Integumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptIntegumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptshraddhaparab530
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17Celine George
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSJoshuaGantuangco2
 
EMBODO Lesson Plan Grade 9 Law of Sines.docx
EMBODO Lesson Plan Grade 9 Law of Sines.docxEMBODO Lesson Plan Grade 9 Law of Sines.docx
EMBODO Lesson Plan Grade 9 Law of Sines.docxElton John Embodo
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfTechSoup
 

Dernier (20)

Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management System
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management system
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdf
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdf
 
Millenials and Fillennials (Ethical Challenge and Responses).pptx
Millenials and Fillennials (Ethical Challenge and Responses).pptxMillenials and Fillennials (Ethical Challenge and Responses).pptx
Millenials and Fillennials (Ethical Challenge and Responses).pptx
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4
 
Expanded definition: technical and operational
Expanded definition: technical and operationalExpanded definition: technical and operational
Expanded definition: technical and operational
 
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptxLEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
 
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptxYOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17
 
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
 
Oppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmOppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and Film
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
 
Integumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptIntegumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.ppt
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
 
EMBODO Lesson Plan Grade 9 Law of Sines.docx
EMBODO Lesson Plan Grade 9 Law of Sines.docxEMBODO Lesson Plan Grade 9 Law of Sines.docx
EMBODO Lesson Plan Grade 9 Law of Sines.docx
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
 
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptxFINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
 

Project Management - Critical path method

  • 1. Critical Path Vazi Okhandiar, PMP, MCT, MBA, MSCS, BSEE NR Computer Learning Center 1835 W. Orangewood, #200 Orange . CA 92868 (714) 505-3475 www.nrclc.com
  • 2. Critical Path Method (CPM)  The critical path method is a project modeling technique developed in the late 1950s by Morgan R. Walker of DuPont and James E. Kelley, Jr. of Remington Rand. - Wikipedia
  • 3. Critical Path  The critical path method was examined by the United States Navy, and established a version in 1958 called a PERT (Program Evaluation and Review Technique) analysis. PERT claimed to reduce project management time by up to 42 percent, and was first used in the development of the Polaris missile. Ref: http://www.ehow.com/about_4703555_whatcritical-path.html#ixzz2igTEV3Q7
  • 4. Critical Path  A Critical Path is the path with the least amount of float or slack time. A float time is the amount of time that an activity can be delayed without delaying the project.  A Critical Path is the longest amount of time it will take to complete the project.  A Critical Path usually has 0 float but may have negative float if the end task is constrained to an early finish date.  If any of the task identified in the critical path is late, then the project will be late.
  • 5. 6. Steps for identifying Critical Path 1. 2. 3. Specify the activates, duration and dependencies Draw a network diagram. Perform the forward pass to identify all Early Start and Early Finish times for the network. Early Finish = Early Start + Duration 4. Perform the backward pass to identify all Late Start and Late Finish times for the network. Late Start = Late Finish – Duration 5. Calculate the slack time. Float = Late Start (LS) – Early Start (ES) 6. Identify the task on critical path with 0 float (slack) time.
  • 7. Terminologies  ID – Task ID  D- Duration  ES – Early Start  EF – Early Finish  LS – Late Start ES  LF – Late Finish F ID DR LS LF  S - Slack EF
  • 8. 2. Network Diagram B 2 F 3 Activity A 2 C 1 G 2 Duratio n ES D 3 E 1 F LS EF ID DR LF
  • 9. 3. Forward Pass 2 Early Start 4 B 2 1st 2 A 2 7 F 3 Early Duration= 9days Finish 2 5 D 3 7 3 C 1 2 0 4 5 task starts at 0 EF = ES + DR ES = EF of predecessor When more than one predecessor, pick the larger # 6 E 1 9 G 2 ES F LS EF ID DR LF
  • 10. 4. Backward Pass 2 4 B 2 1st task should end with LS = 0. 2 0 2 A 2 0 2 Late Start 2 4 4 7 F 3 4 7 7 9 G 2 7 9 3 C 1 5 6 Late Finish 2 LS = LF - DR LF = LS of successor 5 D 3 3 6 5 6 E 1 6 7 When more than one successor, pick the smallest # ES F LS EF ID DR LF
  • 11. 5. Slack / Float 2 4 0 B 2 2 4 0 2 0 A 2 0 2 4 7 0 F 3 4 7 7 9 0 G 2 7 9 2 3 3 C 1 5 6 Float = LS – ES 2 5 1 D 3 3 6 5 6 1 E 1 6 7 Float = Late Start (LS) – Early Start (ES) ES F LS EF ID DR LF
  • 12. 6. Critical Path The path with 0 Float is the critical path. 0 2 0 A 2 0 2 2 4 0 B 2 2 4 4 7 0 F 3 4 7 A-B-F-G is the critical 5 path. 6 0 C 1 5 6 2 5 0 D 3 2 5 LS = LF - DR LF = LS of successor 7 0 G 2 7 5 6 1 E 1 6 7 9 9 ES F LS EF ID DR LF
  • 13. Thank You! Vazi Okhandiar, PMP, MCT, MBA, MSCS, BSEE NR Computer Learning Center 1835 W. Orangewood, Suite 200 Orange, CA 92868 www.nrclc.com . (714) 505. 3475 info@nrclc.com

Notes de l'éditeur

  1. https://www.wyzant.com/Tutor/mail?eid=OK90XlU3Y%2BjE9p4CLHNjsQ%3D%3D&act=Sent
  2. http://hadm.sph.sc.edu/courses/J716/CPM/CPM.html