SlideShare une entreprise Scribd logo
1  sur  44
“Trials and Tribulations
of Shutting Down a
Chemical Plant.”
Willard Vaughan, PE, CIH
Environmental Specialist
PMC Group (formerly Dow , formerly Rohm and
Haas, Formerly Morton Chemical)
Cape Hatteras
What Does Shut Down Mean?
• Last one out turn off the lights and lock the
door?
• EPA calls it:
Cessation of Regulated Operations
When Does Shutdown Occur?
• The simple answer is, when you stop doing
the regulated activity.
• What activities are regulated by:
Why?
PMC Air Permit
• When:
– Production stops
– Materials are removed from site
– All cleaning of the permitted equipment and
storage equipment is completed,
– Equipment is inactivated
PMC Air Permit
• Then
– PMC will/can no longer discharge regulated VOCs.
– Go into eBiz and notify Ohio EPA that the is
decommissioned and no longer in service.
SARA
• Once all materials are off site submit a revised
Tier II report, AND
• Notify LEPA, Fire Department that materials
are off site and processes have been
shutdown
SARA Form R
• Don’t forget to gather your data while you can
for next year’s Form R.
Waste Water
• MSD has its own 7 step procedure for Process
Closure / Transfer
Waste Water Equipment
Run Off?
• SPCC
RCRA
• There is a whole section in the regulations
dealing with Cessation of Regulated Activities.
Ohio Administrative Code 3745 – 66
3745-66-10 Closure and post-closure: applicability.
Except as rule 3745-65-01 of the Administrative Code provides otherwise:
(A) Rules 3745-66-11 to 3745-66-15 of the Administrative Code, which concern
closure, apply to the owners and operators of all hazardous waste management
facilities; and
(B) Rules 3745-66-16 to 3745-66-20 of the Administrative Code, which concern post-
closure care, apply to the owners and operators of:
(1) All hazardous waste disposal facilities;
(2) Waste piles and surface impoundments for which the owner or operator
intends to remove the wastes at closure to the extent that these rules are made
applicable to such facilities in rule 3745-67-28 or 3745-67-58 of the Administrative
Code;
(3) Tank systems that are required under rule 3745-66-97 of the
Administrative Code to meet requirements for landfills; and
3745-66 -11
Closure Performance Standard
The owner or operator must close his facility in a manner
that:
(A) Minimizes the need for further maintenance; and
(B) Controls, minimizes, or eliminates, to the extent necessary to
protect human health and the environment, post-closure escape of
hazardous waste, hazardous constituents, leachate, contaminated
run-off, or hazardous waste decomposition products to the ground
water, or surface waters, or to the atmosphere; and
(C) Complies with the closure requirements of rules 3745-66-10 to
3745-66-21, including, but not limited to, the requirements of rules
3745-66-97, 3745-67-28, 3745-67-58, 3745-67-80, 3745-68-10, 3745-
68-51, 3745-68-81, 3745-69-04, and 3745-205-1023745-256-102 of
the Administrative Code.
3745-66 Closure performance
standard
• 3745-66-97 deals with hazardous waste tanks
• 3745-67-28 deals with surface impoundments
• 3745-67-58 deals with waste piles
• 3745-67-80 deals with land treatment
• 3745-68-10 deals with landfills
There is even a website!
CRO Links
Haz Waste Storage Area
Permanent/Temporary CRO and Contact Person Form (30/45 Day Form)
epa0327.pdf
Regulated Substance & Equipment Removal Form (90 Day-Final Form)
epa0329.pdf
Holder of the First Mortgage/Fiduciary/Indentured Trustee/Receiver Form
(15/60 Day Form)
epa0330.pdf
Government Forms
Closure Plan
• 3745-66-12 Closure plan; amendment of plan.
(A) Written plan. On April 15, 1981, the owner or
operator of a hazardous waste management facility
must have a written closure plan. Until final closure is
completed and certified in accordance with rule 3745-
66-15 of the Administrative Code, a copy of the most
current closure plan must be furnished to the director
upon request, including request by mail. In addition, for
facilities without approved plans, it must also be
provided during site inspections, on the day of
inspection, to any officer, employee, or representative of
Ohio EPA who is duly designated by the director.
Other things to think of
• Freon
• Asbestos/Lead
• Florescent Bulbs – Universal Waste
• Oils and Glycols
• Mercury Switches
• Lab Waste
Issues
• What are you going to do with documents like
RCRA records?
• Who is going to do annual reports?
What to do with all the Stuff
Cleaning out Tanks
What to do with Leftovers
Clearing out transfer lines
Problems
• Half way through the process, the other
facility can’t make the product and you have
to start back up.
• If your plant has been in operation for more
than 20 years, you have things in the closet
that you never knew was there.
www.linkedin.com/in/willardvaughan/
Plant shutdown

Contenu connexe

Tendances

Process Safety Management System
Process Safety Management SystemProcess Safety Management System
Process Safety Management SystemACM Facility Safety
 
Mechanical Integrity.pdf
Mechanical Integrity.pdfMechanical Integrity.pdf
Mechanical Integrity.pdfaashir14
 
Fish bone diagram & 6 sigma for piper alpha accident
Fish  bone diagram & 6 sigma for piper alpha accidentFish  bone diagram & 6 sigma for piper alpha accident
Fish bone diagram & 6 sigma for piper alpha accidentAliff Sabri
 
World Class Manufacturing:Plant Start Up and Commissioning Procedure
World  Class Manufacturing:Plant Start Up and Commissioning Procedure World  Class Manufacturing:Plant Start Up and Commissioning Procedure
World Class Manufacturing:Plant Start Up and Commissioning Procedure HIMADRI BANERJI
 
2 Fire Risk Assessment Template Risk Assessment Templates.docx
2 Fire Risk Assessment Template Risk Assessment Templates.docx2 Fire Risk Assessment Template Risk Assessment Templates.docx
2 Fire Risk Assessment Template Risk Assessment Templates.docxDwarika Bhushan Sharma
 
Process safety ADNOC STANDARD
Process safety ADNOC STANDARDProcess safety ADNOC STANDARD
Process safety ADNOC STANDARDPersonal Secret
 
13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templates13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templatesDwarika Bhushan Sharma
 
Elements of Process Safety Management
Elements of Process Safety ManagementElements of Process Safety Management
Elements of Process Safety ManagementShirazeh arghami
 
Work Permit System
Work Permit SystemWork Permit System
Work Permit SystemGagan Tanwar
 
Prestartup Safety Review (PSSR)
Prestartup Safety Review (PSSR)Prestartup Safety Review (PSSR)
Prestartup Safety Review (PSSR)TheSafetyGuru
 
HEALT & SAFETY IN THE OIL & GAS INDUSTRY
HEALT & SAFETY IN THE OIL & GAS INDUSTRYHEALT & SAFETY IN THE OIL & GAS INDUSTRY
HEALT & SAFETY IN THE OIL & GAS INDUSTRYAlex TX
 
21 confined space working risk assessment templates
21 confined space working risk assessment templates21 confined space working risk assessment templates
21 confined space working risk assessment templatesDwarika Bhushan Sharma
 

Tendances (20)

Hazop ppt
Hazop pptHazop ppt
Hazop ppt
 
Process Safety Management System
Process Safety Management SystemProcess Safety Management System
Process Safety Management System
 
Mechanical Integrity.pdf
Mechanical Integrity.pdfMechanical Integrity.pdf
Mechanical Integrity.pdf
 
Jsa heat-treatment
Jsa  heat-treatmentJsa  heat-treatment
Jsa heat-treatment
 
Hazop Study
Hazop StudyHazop Study
Hazop Study
 
Fish bone diagram & 6 sigma for piper alpha accident
Fish  bone diagram & 6 sigma for piper alpha accidentFish  bone diagram & 6 sigma for piper alpha accident
Fish bone diagram & 6 sigma for piper alpha accident
 
World Class Manufacturing:Plant Start Up and Commissioning Procedure
World  Class Manufacturing:Plant Start Up and Commissioning Procedure World  Class Manufacturing:Plant Start Up and Commissioning Procedure
World Class Manufacturing:Plant Start Up and Commissioning Procedure
 
2 Fire Risk Assessment Template Risk Assessment Templates.docx
2 Fire Risk Assessment Template Risk Assessment Templates.docx2 Fire Risk Assessment Template Risk Assessment Templates.docx
2 Fire Risk Assessment Template Risk Assessment Templates.docx
 
Hazop method
Hazop methodHazop method
Hazop method
 
Process safety ADNOC STANDARD
Process safety ADNOC STANDARDProcess safety ADNOC STANDARD
Process safety ADNOC STANDARD
 
13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templates13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templates
 
Elements of Process Safety Management
Elements of Process Safety ManagementElements of Process Safety Management
Elements of Process Safety Management
 
Work Permit System
Work Permit SystemWork Permit System
Work Permit System
 
Prestartup Safety Review (PSSR)
Prestartup Safety Review (PSSR)Prestartup Safety Review (PSSR)
Prestartup Safety Review (PSSR)
 
Hot Works Safety Training
Hot Works Safety TrainingHot Works Safety Training
Hot Works Safety Training
 
API STD 521
API STD 521API STD 521
API STD 521
 
Hazop Study
Hazop StudyHazop Study
Hazop Study
 
HEALT & SAFETY IN THE OIL & GAS INDUSTRY
HEALT & SAFETY IN THE OIL & GAS INDUSTRYHEALT & SAFETY IN THE OIL & GAS INDUSTRY
HEALT & SAFETY IN THE OIL & GAS INDUSTRY
 
Presentation hazop introduction
Presentation hazop introductionPresentation hazop introduction
Presentation hazop introduction
 
21 confined space working risk assessment templates
21 confined space working risk assessment templates21 confined space working risk assessment templates
21 confined space working risk assessment templates
 

Similaire à Plant shutdown

PA DEP: Methane Reduction Strategies for Natural Gas Operations
PA DEP: Methane Reduction Strategies for Natural Gas OperationsPA DEP: Methane Reduction Strategies for Natural Gas Operations
PA DEP: Methane Reduction Strategies for Natural Gas OperationsMarcellus Drilling News
 
BlueScape Learn Air Permits & Compliance Training 7-28-15
BlueScape Learn Air Permits & Compliance Training 7-28-15BlueScape Learn Air Permits & Compliance Training 7-28-15
BlueScape Learn Air Permits & Compliance Training 7-28-15BlueScape
 
Hazardous Materials Assessments for Renovation/Demolition Projects
Hazardous Materials Assessments for Renovation/Demolition ProjectsHazardous Materials Assessments for Renovation/Demolition Projects
Hazardous Materials Assessments for Renovation/Demolition ProjectsGuy Sylvester
 
A Deep Dive into the RCRA Regulations: Are You Aware of These Lesser Known Re...
A Deep Dive into the RCRA Regulations: Are You Aware of These Lesser Known Re...A Deep Dive into the RCRA Regulations: Are You Aware of These Lesser Known Re...
A Deep Dive into the RCRA Regulations: Are You Aware of These Lesser Known Re...Triumvirate Environmental
 
NSPS Subpart OOOO: Applicability and Compliance Basics
NSPS Subpart OOOO: Applicability and Compliance BasicsNSPS Subpart OOOO: Applicability and Compliance Basics
NSPS Subpart OOOO: Applicability and Compliance BasicsAll4 Inc.
 
Aet presentation-hazardous-waste-generator-improvement-rule-mar.24.17
Aet presentation-hazardous-waste-generator-improvement-rule-mar.24.17Aet presentation-hazardous-waste-generator-improvement-rule-mar.24.17
Aet presentation-hazardous-waste-generator-improvement-rule-mar.24.17Michael Habig
 
Tim Eiken, MDNR, Overview of Recent Rule Changes, Missouri Hazardous Waste Se...
Tim Eiken, MDNR, Overview of Recent Rule Changes, Missouri Hazardous Waste Se...Tim Eiken, MDNR, Overview of Recent Rule Changes, Missouri Hazardous Waste Se...
Tim Eiken, MDNR, Overview of Recent Rule Changes, Missouri Hazardous Waste Se...Kevin Perry
 
Update to CAA: How the EPA's Refrigerant Management Program Has Changed
Update to CAA: How the EPA's Refrigerant Management Program Has ChangedUpdate to CAA: How the EPA's Refrigerant Management Program Has Changed
Update to CAA: How the EPA's Refrigerant Management Program Has ChangedTriumvirate Environmental
 
2 beth knauss - florida finishers association outreach
2   beth knauss - florida finishers association outreach2   beth knauss - florida finishers association outreach
2 beth knauss - florida finishers association outreachElabQuality
 
BlueScape Get the Air Permit for Energy Projects Webinar 9-10-13
BlueScape Get the Air Permit for Energy Projects Webinar 9-10-13BlueScape Get the Air Permit for Energy Projects Webinar 9-10-13
BlueScape Get the Air Permit for Energy Projects Webinar 9-10-13BlueScape
 
Do a Safety Checkup for your Facility OSHA/EPA/DOT Minimum Program and Train...
Do a Safety Checkup for your Facility OSHA/EPA/DOT Minimum Program and  Train...Do a Safety Checkup for your Facility OSHA/EPA/DOT Minimum Program and  Train...
Do a Safety Checkup for your Facility OSHA/EPA/DOT Minimum Program and Train...KPADealerWebinars
 
2015-07-22 Why is an Environmental Audit Important
2015-07-22 Why is an Environmental Audit Important2015-07-22 Why is an Environmental Audit Important
2015-07-22 Why is an Environmental Audit ImportantEd Callahan
 
design of common hazardous waste treatment, storage and ....
 design of common hazardous waste treatment, storage and .... design of common hazardous waste treatment, storage and ....
design of common hazardous waste treatment, storage and ....arvind kumar
 
Tighe & Bond Breakfast Seminar Series 2015
Tighe & Bond Breakfast Seminar Series 2015Tighe & Bond Breakfast Seminar Series 2015
Tighe & Bond Breakfast Seminar Series 2015David Horowitz
 

Similaire à Plant shutdown (20)

MDE's Stormwater Permitting Requirements
MDE's Stormwater Permitting RequirementsMDE's Stormwater Permitting Requirements
MDE's Stormwater Permitting Requirements
 
PA DEP: Methane Reduction Strategies for Natural Gas Operations
PA DEP: Methane Reduction Strategies for Natural Gas OperationsPA DEP: Methane Reduction Strategies for Natural Gas Operations
PA DEP: Methane Reduction Strategies for Natural Gas Operations
 
CAC Meeting 18 September 2013
CAC Meeting 18 September 2013CAC Meeting 18 September 2013
CAC Meeting 18 September 2013
 
BlueScape Learn Air Permits & Compliance Training 7-28-15
BlueScape Learn Air Permits & Compliance Training 7-28-15BlueScape Learn Air Permits & Compliance Training 7-28-15
BlueScape Learn Air Permits & Compliance Training 7-28-15
 
An Overview of PCAPP’s Pilot Demonstration Testing
An Overview of PCAPP’s Pilot Demonstration TestingAn Overview of PCAPP’s Pilot Demonstration Testing
An Overview of PCAPP’s Pilot Demonstration Testing
 
Hazardous Materials Assessments for Renovation/Demolition Projects
Hazardous Materials Assessments for Renovation/Demolition ProjectsHazardous Materials Assessments for Renovation/Demolition Projects
Hazardous Materials Assessments for Renovation/Demolition Projects
 
A Deep Dive into the RCRA Regulations: Are You Aware of These Lesser Known Re...
A Deep Dive into the RCRA Regulations: Are You Aware of These Lesser Known Re...A Deep Dive into the RCRA Regulations: Are You Aware of These Lesser Known Re...
A Deep Dive into the RCRA Regulations: Are You Aware of These Lesser Known Re...
 
NSPS Subpart OOOO: Applicability and Compliance Basics
NSPS Subpart OOOO: Applicability and Compliance BasicsNSPS Subpart OOOO: Applicability and Compliance Basics
NSPS Subpart OOOO: Applicability and Compliance Basics
 
ADBA Spring Regulatory Forum - May 2016
ADBA Spring Regulatory Forum - May 2016ADBA Spring Regulatory Forum - May 2016
ADBA Spring Regulatory Forum - May 2016
 
Aet presentation-hazardous-waste-generator-improvement-rule-mar.24.17
Aet presentation-hazardous-waste-generator-improvement-rule-mar.24.17Aet presentation-hazardous-waste-generator-improvement-rule-mar.24.17
Aet presentation-hazardous-waste-generator-improvement-rule-mar.24.17
 
Tim Eiken, MDNR, Overview of Recent Rule Changes, Missouri Hazardous Waste Se...
Tim Eiken, MDNR, Overview of Recent Rule Changes, Missouri Hazardous Waste Se...Tim Eiken, MDNR, Overview of Recent Rule Changes, Missouri Hazardous Waste Se...
Tim Eiken, MDNR, Overview of Recent Rule Changes, Missouri Hazardous Waste Se...
 
Update to CAA: How the EPA's Refrigerant Management Program Has Changed
Update to CAA: How the EPA's Refrigerant Management Program Has ChangedUpdate to CAA: How the EPA's Refrigerant Management Program Has Changed
Update to CAA: How the EPA's Refrigerant Management Program Has Changed
 
2 beth knauss - florida finishers association outreach
2   beth knauss - florida finishers association outreach2   beth knauss - florida finishers association outreach
2 beth knauss - florida finishers association outreach
 
BlueScape Get the Air Permit for Energy Projects Webinar 9-10-13
BlueScape Get the Air Permit for Energy Projects Webinar 9-10-13BlueScape Get the Air Permit for Energy Projects Webinar 9-10-13
BlueScape Get the Air Permit for Energy Projects Webinar 9-10-13
 
Do a Safety Checkup for your Facility OSHA/EPA/DOT Minimum Program and Train...
Do a Safety Checkup for your Facility OSHA/EPA/DOT Minimum Program and  Train...Do a Safety Checkup for your Facility OSHA/EPA/DOT Minimum Program and  Train...
Do a Safety Checkup for your Facility OSHA/EPA/DOT Minimum Program and Train...
 
Pueblo Chemical Agent-Destruction Pilot Plant Explosive Destruction System (...
Pueblo Chemical Agent-Destruction Pilot Plant Explosive Destruction System (...Pueblo Chemical Agent-Destruction Pilot Plant Explosive Destruction System (...
Pueblo Chemical Agent-Destruction Pilot Plant Explosive Destruction System (...
 
EPA’s NSPS OOOOa(Quad Oa) Rule
EPA’s NSPS OOOOa(Quad Oa) RuleEPA’s NSPS OOOOa(Quad Oa) Rule
EPA’s NSPS OOOOa(Quad Oa) Rule
 
2015-07-22 Why is an Environmental Audit Important
2015-07-22 Why is an Environmental Audit Important2015-07-22 Why is an Environmental Audit Important
2015-07-22 Why is an Environmental Audit Important
 
design of common hazardous waste treatment, storage and ....
 design of common hazardous waste treatment, storage and .... design of common hazardous waste treatment, storage and ....
design of common hazardous waste treatment, storage and ....
 
Tighe & Bond Breakfast Seminar Series 2015
Tighe & Bond Breakfast Seminar Series 2015Tighe & Bond Breakfast Seminar Series 2015
Tighe & Bond Breakfast Seminar Series 2015
 

Dernier

Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitterShivangiSharma879191
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 

Dernier (20)

Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 

Plant shutdown

  • 1. “Trials and Tribulations of Shutting Down a Chemical Plant.” Willard Vaughan, PE, CIH Environmental Specialist
  • 2. PMC Group (formerly Dow , formerly Rohm and Haas, Formerly Morton Chemical)
  • 3.
  • 5. What Does Shut Down Mean? • Last one out turn off the lights and lock the door? • EPA calls it: Cessation of Regulated Operations
  • 6. When Does Shutdown Occur? • The simple answer is, when you stop doing the regulated activity. • What activities are regulated by:
  • 8. PMC Air Permit • When: – Production stops – Materials are removed from site – All cleaning of the permitted equipment and storage equipment is completed, – Equipment is inactivated
  • 9. PMC Air Permit • Then – PMC will/can no longer discharge regulated VOCs. – Go into eBiz and notify Ohio EPA that the is decommissioned and no longer in service.
  • 10.
  • 11. SARA • Once all materials are off site submit a revised Tier II report, AND • Notify LEPA, Fire Department that materials are off site and processes have been shutdown
  • 12.
  • 13. SARA Form R • Don’t forget to gather your data while you can for next year’s Form R.
  • 14. Waste Water • MSD has its own 7 step procedure for Process Closure / Transfer
  • 15.
  • 18.
  • 19.
  • 20.
  • 21. RCRA • There is a whole section in the regulations dealing with Cessation of Regulated Activities. Ohio Administrative Code 3745 – 66
  • 22.
  • 23. 3745-66-10 Closure and post-closure: applicability. Except as rule 3745-65-01 of the Administrative Code provides otherwise: (A) Rules 3745-66-11 to 3745-66-15 of the Administrative Code, which concern closure, apply to the owners and operators of all hazardous waste management facilities; and (B) Rules 3745-66-16 to 3745-66-20 of the Administrative Code, which concern post- closure care, apply to the owners and operators of: (1) All hazardous waste disposal facilities; (2) Waste piles and surface impoundments for which the owner or operator intends to remove the wastes at closure to the extent that these rules are made applicable to such facilities in rule 3745-67-28 or 3745-67-58 of the Administrative Code; (3) Tank systems that are required under rule 3745-66-97 of the Administrative Code to meet requirements for landfills; and
  • 24. 3745-66 -11 Closure Performance Standard The owner or operator must close his facility in a manner that: (A) Minimizes the need for further maintenance; and (B) Controls, minimizes, or eliminates, to the extent necessary to protect human health and the environment, post-closure escape of hazardous waste, hazardous constituents, leachate, contaminated run-off, or hazardous waste decomposition products to the ground water, or surface waters, or to the atmosphere; and (C) Complies with the closure requirements of rules 3745-66-10 to 3745-66-21, including, but not limited to, the requirements of rules 3745-66-97, 3745-67-28, 3745-67-58, 3745-67-80, 3745-68-10, 3745- 68-51, 3745-68-81, 3745-69-04, and 3745-205-1023745-256-102 of the Administrative Code.
  • 25. 3745-66 Closure performance standard • 3745-66-97 deals with hazardous waste tanks • 3745-67-28 deals with surface impoundments • 3745-67-58 deals with waste piles • 3745-67-80 deals with land treatment • 3745-68-10 deals with landfills
  • 26. There is even a website!
  • 29. Permanent/Temporary CRO and Contact Person Form (30/45 Day Form) epa0327.pdf Regulated Substance & Equipment Removal Form (90 Day-Final Form) epa0329.pdf Holder of the First Mortgage/Fiduciary/Indentured Trustee/Receiver Form (15/60 Day Form) epa0330.pdf Government Forms
  • 30.
  • 31.
  • 32.
  • 33. Closure Plan • 3745-66-12 Closure plan; amendment of plan. (A) Written plan. On April 15, 1981, the owner or operator of a hazardous waste management facility must have a written closure plan. Until final closure is completed and certified in accordance with rule 3745- 66-15 of the Administrative Code, a copy of the most current closure plan must be furnished to the director upon request, including request by mail. In addition, for facilities without approved plans, it must also be provided during site inspections, on the day of inspection, to any officer, employee, or representative of Ohio EPA who is duly designated by the director.
  • 34. Other things to think of • Freon • Asbestos/Lead • Florescent Bulbs – Universal Waste • Oils and Glycols • Mercury Switches • Lab Waste
  • 35. Issues • What are you going to do with documents like RCRA records? • Who is going to do annual reports?
  • 36. What to do with all the Stuff
  • 38. What to do with Leftovers
  • 40. Problems • Half way through the process, the other facility can’t make the product and you have to start back up. • If your plant has been in operation for more than 20 years, you have things in the closet that you never knew was there.
  • 41.
  • 42.

Notes de l'éditeur

  1. Good afternoon and welcome to my presentation on the Trails an Tribulations of Shutting Dow a Chemical Plant.
  2. Well everything comes to an end at some time and there are times we just got to give it and move on – or take a nap. PMC purchased the facility in Feb 2013 and announced in July 2013 that they would consolidate the operations of Cincinnati and Carrolton, KY together in Carrolton, KY. In September, 2013 Cincinnati personnel were informed of their state and some were offered positions in Carrolton and some where not. I was not. BUT this being said, while everyone stated looking for work, there is a dedicated professional staff that has continued working to make sure all goes correctly without getting anyone hurt or spills/leaking of materials. This is a Google map shot of the plant. PMC owns the property including the ball fields out front. However the ball fields are rented for something like a dollar for 10 years but in reality is a buffer for the plant to the residential south of the plant. The plant was begun right after World War II and has been a manufacturing facility every since but as the title shows, it has gone through a number ownership changes. With each change, the products and process did remain somewhat constant and the real changes came from the management culture of each corporate purchase. We are a chemical plant with a variety of materials railcars of Chlorine and methyl Chloride Tanks of various organics Tin in both solid and liquid states We have the normal Large Quantity Hazardous Waste permits, We submit Sara Tier II and Form R reports, We have an air permit, discharge industrial waste to MSD under a permit. Further more the plant under went a RCRA 3013 inspection before me and had just finished up remediation of the site but had never gotten Federal EPA in Chicago to close out the account. So while we are not complicated, there are a number of issues that will need to be addressed. Also, we are shutting down because we want to not under orders from anyone.
  3. But moving large objects does get complicated and a lot of people will have to be involved otherwise things can go really wrong quickly.
  4. However even very large objects can be moved with the right equipment, personal and planning. This is Cape Hatteras lighthouse on the outer banks of North Carolina. For the full story and more photos go to http://www.nps.gov/caha/historyculture/movingthelighthouse.htm But it can be done so where to begin?
  5. So what do we mean by the term shutdown? Easiest answer, the date the last person walks out the gates and turns off the lights. Stop bringing materials on site To most this means end of production - but this is misleading in that stopping production does not mean you have shutdown
  6. There are a number of regulations and laws that apply to each site depending on what you do. Each of these agencies above have a different issue and determine shutdown a bit differently. Air Emissions Waste Water Discharges Hazardous and Solid Waste SARA reporting TSCA regulated materials (asbestos and lead) Lets start with the easiest – Air emissions.
  7. The end of production is simple enough Production stops, you are not making anything, nothing goes in and nothing comes out. Materials are removed from site – raw materials are off site and can not be used, leak or spill All cleaning of the permitted equipment and storage equipment is completed – opening a tank or container to wash it out can release more air toxics, VOCs or other regulated substances which need to be measured or estimated for reporting. Equipment is inactivated – Air gaped, disconnecting equipment with piping or removal of equipment from site.
  8. Once all the above occurs, then you
  9. This is a screen shot of PMC’s Emission Unit (EU) for a major process – all I have to do is edit this profile and at the bottom of the screen is a button that I click to say shut it down. There are a number of clicks you have to make for each of the sections. Each time, the software will warn you that once the equipment is removed, it can not be re-actived without a full permit application. So if all the sudden they want to put the system back on line for just one more day, you have to get a new permit. And once all the equipment is removed, all that is left is a final quarterly report and I will go ahead and do an annual report for submittal. This is the easy process. Now we go to the next step.
  10. This is just page one of three pages – could not find a link on MSD’s web page but they will be very happy to get you a copy if you request it. Nothing really surprising – required notification dates, need for contact person after transfer or closure and such and a closure plan.
  11. This is the big one since And if in doubt,
  12. http://codes.ohio.gov/oac/3745-66
  13. This is the big one since And if in doubt that it applies to you – the question to ask is, does anyone know about your operations? If yes then this applies.
  14. http://www.epa.ohio.gov/dmwm/Home/Cro.aspx
  15. http://epa.ohio.gov/portals/32/pdf/epa0327.pdf
  16. http://epa.ohio.gov/portals/32/pdf/epa0329.pdf
  17. http://epa.ohio.gov/portals/32/pdf/epa0330.pdf
  18. So What’s Next? For the facility we will continue working down the road in clearing out all the products and materials, removing and shipping all equipment and tanks other PMC facilities want, and cleaning the place up so that it will be safe for the salvage / demolition crews to come in and do their work. For me personally,
  19. Well its time for this super hero to take a short nap – I am looking around for a position but since I have some time before everything ends, I am taking my time
  20. But if you know of somewhere south within 100 miles of the Chattanooga, TN area feel free to let me know!! if you want a copy of this power point with the links to all the documents and information I hope to have this up on my linked in page – just look me up at Willard Vaughan.
  21. Thanks for you time and are there any further questions?